Legally Bharat

Orissa High Court

A.F.R. M/S. Creative Builders And vs Prabir Kumar Dash on 27 September, 2024

Author: Sashikanta Mishra

Bench: Sashikanta Mishra

               IN THE HIGH COURT OF ORISSA AT CUTTACK

                         RSA No.174 of 2024
         (From the judgment dated 29.2.2024 passed by learned 4th
         Addl. District Judge, Bhubaneswar in RFA No.85/2023 and
         the judgment dtd.23.8.2023 passed by learned Sr. Civil
         Judge (L.R & L.T.V), Bhubaneswar in Civil Suit
         No.1941/2021)


A.F.R.        M/s. Creative Builders and
              Consultants, a registered
              Partnership Firm through
              its Managing Partner-
              Nirupama Patra
                                   ...             Appellant

                                   -versus-

              Prabir Kumar Dash
              and others     ...                  Respondents


          Advocates appeared in the case through hybrid mode:


            For Appellant              : Mr. Bidyadhar Mishra
                                         Sr. Advocate.
                                         Mr. T.R.Biswal,
                                         Advocate

            For Respondent
            No.1                      : Mr.Bansidhar Baug, Advocate

            For Respondent
            Nos.2 and 3                : Mr.Bhaskar Panda, Advocate




           R.S.A. No.174 of 2024                    Page 1 of 53
            ---------------------------------------------------------------------------
                                         CORAM:
                        JUSTICE SASHIKANTA MISHRA

                                      JUDGMENT

27.9.2024.

Sashikanta Mishra,J. This is a Defendant’s appeal against a

confirming judgment. The judgment dated 29.2.2024

followed by decree passed by the 4th Addl. District

Judge, Bhubaneswar in RFA No.85/2023 is under

challenge whereby the judgment dtd.23.8.2023

followed by decree passed by the Sr. Civil Judge

(L.R & L.T.V), Bhubaneswar in Civil Suit

No.1941/2021 was confirmed.

2. For convenience, the parties are referred to as

per their respective status in the trial Court.

Case of the Plaintiff

3. The Plaintiff-Respondent No.1, being a resident

of U.S.A. instituted the suit in question through his

authorized agent. He being the owner of the suit land

R.S.A. No.174 of 2024 Page 2 of 53
executed a Development Agreement on 07.8.2020 with

the Defendant firm represented by its Managing

Partner-Bibhuti Bhusan Patra for development of the

suit property. As per said agreement, the land owner’s

allocation was limited to 50% of the super built

up/carpet area up to 4th floor while the builder-cum-

developer’s (Defendant’s Firm) allocation was limited to

the remaining portion. It was further provided that the

land owner would have no claim in case the builder

obtained sanction of the Bhubaneswar Municipal

Corporation (BMC) beyond 4th floor and the actual

allocation of flats would be declared only after approval

of the building plan by the Odisha Real Estate

Regulatory Authority (ORERA). The Plaintiff received an

amount of Rs.2,80,00,000/- on different dates prior to

execution of the agreement. The suit property being

lease-hold land, the Plaintiff deposited a sum of

Rs.3,09,91,736/- to make it free-hold on 24.7.2020

and Rs.3,44,355/- for obtaining convenience deed

R.S.A. No.174 of 2024 Page 3 of 53
from his own source. Another agreement titled

Supplementary Agreement was executed on the very

next date i.e. on 8.8.2020 by the Plaintiff with the

Defendant. As per the said agreement, the Plaintiff

agreed to receive his 50% share by way of financial

benefits to the extent of Rs.15,15,00,000/- in lieu of

flat in the proposed housing project. Thus,

after adjustment of the security amount of

Rs.2,80,00,000/-, he is entitled to the balance amount

of Rs.12,35,00,000/- within a period of 24 months

with a grace period of 6 months from the date of

approval/registration of the project under BMC and

ORERA. Further, on 03.9.2020, the Plaintiff executed a

registered General Power of Attorney (GPA) authorizing

the Defendant firm to develop the construction work

over the suit property and to obtain permission from

the appropriate authority as and when required. He

thereafter delivered possession of the suit land to the

Defendant by demolishing the existing residential

R.S.A. No.174 of 2024 Page 4 of 53
house thereon. The Managing Partner of the Defendant

firm namely, Bibhuti Bhusan Patra died on 14.12.2021

and by letter dated 21.7.2021, his widow intimated

that she had been appointed as Managing Partner and

two ordinary partners had been incorporated under a

Deed of Reconstitution of the firm. It was further given

out that the new management had accepted in

principle to honour all the official agreements executed

by the deceased Managing Partner and committed to

develop the suit land into a multi-storied apartment

complex after obtaining required approval from the

BMC and ORERA. Nothing was however, said

regarding payment of the balance amount save and

except that they would try and pay off the share given

earlier depending on the financial situation of the firm.

The Plaintiff was surprised that the permission of the

authority had not been obtained despite lapse of one

year and there was no clear-cut indication as to when

the balance amount would be paid to him. On

R.S.A. No.174 of 2024 Page 5 of 53
09.8.2021, the Plaintiff replied to the letter of the

Defendant informing that despite direction of the BMC

no action had been taken by the Defendant for

obtaining permission and yet without obtaining

ORERA Registration Certificate, the Firm was collecting

amounts from the intending purchasers by advertising

the project, which is in violation of the rules and

regulations. The Defendant in its reply dtd.17.8.2021

intimated that delay was caused in obtaining legal heir

certificate and reconstitution of the firm as also due to

the impact of COVID-19 Pandemic. Defendant further

claimed to have paid Rs.3,20,00,000/- as against

Rs.2,80,00,000/-. The Plaintiff claims that an amount

of Rs.40,00,000/- paid by the deceased-Bibhuti

Bhusan Patra by way of a post dated cheque, on being

presented was dishonoured due to insufficient funds.

All these facts created reasonable doubt in the mind of

the Plaintiff as regards honoring of the commitment by

the Defendant firm and therefore, he filed the suit

R.S.A. No.174 of 2024 Page 6 of 53
claiming the relief of declaration that the agreement

dated 7.8.2020 and 8.8.2020 and the GPA

dtd.3.9.2020 as null and void, with recovery of

possession and permanent injunction. The Plaintiff

also expressed his readiness and willingness to return

the advance amount of Rs.2,80,00,000/- to the

defendant.

Case of the Defendant

4. The Defendant questioned the maintainability of

the suit on the ground that the same had been filed by

a person without authority. The facts relating to the

execution of the Development Agreement and the GPA

by the Plaintiff in favour of the deceased Managing

Partner was admitted. It was further stated that before

execution of the agreement with the Defendant, the

Plaintiff had executed a registered Agreement for Sale

on 4.12.2017 in favour of another firm namely, M/s.

Cottage Design Private Ltd. for a consideration of

Rs.12,60,00,000/-and had received Rs.1,00,000/-. As

R.S.A. No.174 of 2024 Page 7 of 53
the Agreement could not materialize, it was cancelled

on 01.6.2020 through a registered document. As

regards the Development Agreement executed with the

Plaintiff, the terms were admitted as also the fact of

payment of Rs.2,80,00,000/- to the Plaintiff till

30.7.2020. The Defendant further claimed that a sum

of Rs.20,00,000/- was paid to the Plaintiff in the form

of cheque on 07.11.2020 and Rs.20,00,000/- also in

the form of cheque on 04.12.2020, which was

encashed by the Plaintiff but suppressed in the plaint.

It is the further case of the Defendant that there was

no delay on the part of the firm but because of

unavoidable reasons like the onset of Pandemic and

death of the Managing Partner, some delay was

caused. Nevertheless, the defendant on reconstitution

of the firm submitted building plans before the BMC,

which required compliance of several conditions which

the defendant complied and deposited the requisite

fees. The BMC thereafter approved the building plan.

R.S.A. No.174 of 2024 Page 8 of 53
The Defendant also submitted application before the

ORERA for approval of the project but because of order

of status quo by the trial Court, such application was

rejected. According to the Defendant, there is no fault

or latches on its part to perform the part of the

contract and no intention of not paying the agreed

amount within the period fixed by the agreement. As

regards dishonor of the cheque, it is the Defendant’s

case that the deceased Managing Partner had issued

three security cheques and two post dated cheques to

the Plaintiff of which the Plaintiff was to encash only

two cheques of Rs.20 lakhs each and the remaining

three cheques were to be returned to the Defendant

firm, but the Plaintiff deliberately deposited one of the

said cheques amounting to Rs.40,00,000/- on

17.8.2021, which came to be dishonoured. This,

according to the Defendant, shows the malafide

intention and oblique motive of the Plaintiff to harass

the Defendant firm. The building plan of the project

R.S.A. No.174 of 2024 Page 9 of 53
had been approved but approval of ORERA could not

be obtained because of order of status quo. On such

averments, the Defendant prayed for dismissal of the

suit.

Issues and Findings of the trial Court

5. Basing on the rival pleadings, the trial Court

framed the following issues for determination;

(i) Whether the suit is maintainable?

(ii) Whether there is cause of action for the plaintiff to
file the suit?

(iii) Whether the suit is barred by limitation?

(iv) Whether the suit is grossly undervalued ?

(v) Whether the plaintiff is entitled to a decree
declaring the development agreement dated
07.08.2020, the supplementary agreement dated
08.08.2020 and the GPA dated 03.09.2020 as null
and void?

(vi) Whether the plaintiff is entitled to a decree
directing the defendant to handover the vacant
possession of the suit land to him?

(vii) Whether the plaintiff is entitled to a decree for
permanent injunction restraining the defendant, its
men, agents, followers and assigns from interfering
in any way with his peaceful possession over the suit
land or any part thereof and from changing the
nature and character of the same after possession is
recovered on his behalf?

(viii) To what other relief(s) the parties are entitled?

R.S.A. No.174 of 2024 Page 10 of 53

6. Issue Nos.(v), (vi) and (vii) being the pivotal

issues, were taken up for consideration by the trial

Court at the outset. After analyzing the oral and

documentary evidence on record, the trial Court

observed that as there was nothing clear and specific

as to when the remaining amount would be paid by the

Defendant as per the Supplementary Agreement, the

same became the prime concern for the Plaintiff to file

the suit. It was further held that the grounds for

explaining the delay are not sufficient, when the

supposed performance of the obligations under the

Agreements are taken into consideration in the face of

the time stipulated in the supplementary agreement for

payment of plaintiff’s balance consideration.

Observing thus, the trial Court held that mere

admission of the executed agreement and power of

attorney cannot prevent the Plaintiff to repudiate the

agreements and revoke the power of attorney executed

R.S.A. No.174 of 2024 Page 11 of 53
by him. Since the Defendant failed to give any

concrete assurance as to the payment of the balance

amount, but admittedly collected money from potential

purchasers before registration of the housing complex

under the ORERA rules, the Plaintiff is justified to get

out of the agreements and the power of attorney.

Though the approval of BMC had been obtained but till

filing of the suit the Defendant had not got any project

registered under the ORERA. It was therefore held that

the Defendant willfully neglected to carry out the

proposed building plan intending to make immense

profit out of the project without giving any firm

assurance for making payment of the remaining

consideration amount to the Plaintiff for which the

Plaintiff is entitled to terminate the agreements and

revoke the power of attorney. It was also held that the

contract was indefinite and had become impossible of

performance. On such findings basically the issues

were answered in favour of the Plaintiff.

R.S.A. No.174 of 2024 Page 12 of 53

On Issue No.3 regarding limitation the trial

Court held that the suit falls under the residuary

Article 113 of the Limitation Act. Since the suit was

filed before the time stipulated in the agreement, it was

held to be in time.

As regards maintainability of the suit on the

ground of its non-presentation by the authorized

person, the trial Court held that the same is a curable

defect and cannot be fatal to the suit more so as the

defendants have themselves substantially admitted the

contentions made in the plaint. Moreover, the Plaintiff

had disclosed his intention to engage the authorized

agent for the purpose of the suit.

On Issue No.4, the trial Court held that the suit

being one for declaration along with consequential

relief, the Plaintiff valued the same at Rs.1,00,000/-

and there was no objection by the office at the initial

stage. With such findings being rendered on the main

issues, the remaining issues were answered

R.S.A. No.174 of 2024 Page 13 of 53
accordingly in favour of the Plaintiff. The suit was thus

decreed by granting the relief claimed by the Plaintiff

with further direction to him to refund Rs.3.2 crores to

the Defendant with simple interest @ 12% per annum

to be calculated from 01.5.2020 till payment.

7. Being aggrieved, the Defendant carried the

matter in appeal, which was heard and disposed of by

learned 4th Addl. District Judge.

Findings of the 1st Appellate Court

8. An application for permission to adduce

additional evidence was filed by the Defendant before

the 1st Appellate Court under Order 41, Rule 27 of

C.P.C. The 1st Appellate Court held in the impugned

judgment that the Defendant could not prove that it

had exhibited due diligence in obtaining and

presenting the same during trial even though said

documents were available at the relevant time. The

prayer for adducing additional evidence was thus

R.S.A. No.174 of 2024 Page 14 of 53
rejected. The 1st Appellate Court took note of the

findings of the trial Court and also considered the oral

and documentary evidence on record. It was held that

till institution of the suit, the Defendant firm had not

made any application for approval of the project before

the ORERA nor there is any explanation for non-

submission of the same prior to the institution of the

suit. This therefore, amounts to non-performance of

its contractual obligation by the Defendant within a

considerable period of more than a year of the

execution of the agreement. It was further held that as

the Agreements and the GPA had been declared void

due to the fault of the Defendant firm, it is not entitled

to any compensation for the loss sustained by it due to

its own fault. On the question of authority of the

person filing the suit on behalf of the Plaintiff, the 1st

Appellate Court also held that it was a mere procedural

defect and irregularity which is curable in nature and

that the same cannot be allowed to defeat substantive

R.S.A. No.174 of 2024 Page 15 of 53
rights of the plaintiff. On such findings, the 1st

Appellate Court did not find any reason to interfere

with the judgment and decree of the trial Court and

the appeal was thus dismissed.

9. Being further aggrieved, the Defendant has filed the

present appeal, which was admitted on the following

Substantial Questions of Law;

(i)Whether the Plaint which has been signed,
verified, sworn on oath and presented by
Plaintiff’s Agent Akshaya Kumar Parija is
maintainable when the said Agent. Akshaya
Kuamr Parija has admitted in course of his
evidence that he has no personal knowledge
about the contents of the Plaint nor he has any
personal knowledge about the tractions under the
Development Agreement dated 07.08.2020 (Ext.
A/Ext-8) and Supplementary Agreement dated
08.08.2020 (Ext.B/Ext.9) between the Plaintiff
and the Defendant Firm ?

(ii)Whether there is any cause of action for the
Plaintiff to file C.S. No 1941 of 2021 on
14.09.2021 before expiry of the stipulated
timelines for completion of construction of the
proposed building project specified under the
Development Agreement dated 07.08.2020
(Ext.A/Ext.8) which expires on 15.03.2025 ? AND

Whether there is any cause of action for the
Plaintiff to file C.S. No 1941 of 2021 on
14.09.2021 alleging inter alia non-payment of
total consideration amount of the suit property to
him, before expiry of the stipulated timelines for
completion of payment by the Defendant Firm to
the Plaintiff as specified under the

R.S.A. No.174 of 2024 Page 16 of 53
Supplementary Agreement dated 08.08.2020
(Ext.B/Ext.9) which expires on 15.03.2024,
particularly when the Plaintiff has already
received Rs.3.20 crores from the Defendant Firm?

(iii)Whether the Issue No.(iii) as framed by the
learned Trial Court to the effect, “Whether the suit
is barred by limitation? is to be re-casted as
“Whether the suit is prematurely filed?”

(iv) Whether the finding of the learned First
Appellate Court to the effect. “As per Section 55 of
the Indian Contract Act, the Defendant Firm has
not taken prompt steps for registration and
project approval, even though considerable period
of more than one year has elapsed not taken any
steps for payment of balance consideration
amount to the plaintiff”, is legally sustainable
particularly when the documents exhibited show
that there is no delay on the part of the
Defendant-Appellant Firm in this regard?

(v) Whether the findings of the learned Trial Court
under Paragraph-13 of its judgment is liable to be
set aside as the same are beyond pleadings and
materials on record and based upon surmises
and conjectures?

vi. Whether the findings of the learned First
Appellate Court to the effect that “the application
of the Defendant to admit documents under
Order 41 Rule 27 and to mark the same as
exhibits suffers from want of due diligence and
for such the same is rejected”, is legally
sustainable or the same is liable to set aside?”

Submissions on substantial questions of law and
findings.

10. Heard Mr. Bidyadhar Mishra learned Senior

counsel appearing with Mr. T. R. Biswal for the

Defendant-Appellant, Mr. Bansidhar Baug, learned

R.S.A. No.174 of 2024 Page 17 of 53
counsel for the Plaintiff-Respondent No.1 and Mr.

Bhaskar Panda, learned counsel appearing for the

Respondent Nos.2 and 3.

Substantial Question No.(i).

11. Learned Senior counsel Mr. Bidyadhar Mishra

submits that the suit was filed by Prabir Kumar Das

but the plaint was presented by his purported agent

namely Akshaya Kumar Parija. As per the different

provisions of C.P.C. the plaint can only be presented by

the Plaintiff or by a person duly authorized by him,

who is acquainted with the facts of the case. In the

instant case, the plaint was signed, verified and

affirmed on oath by Akshaya Kumar Parija, who being

examined as a witness (P.W.2) during trial admitted

that he was only authorized to file the suit as the

Plaintiff was residing in USA and was prevented from

travelling to India due to COVID restrictions. He

further admitted that he did not have any personal

knowledge about the agreements. According to learned

R.S.A. No.174 of 2024 Page 18 of 53
Senior counsel this is fatal to the suit. Moreover, the

authorization letter dtd.12.9.2021 is not in proper form

nor contains the approval of the Indian Embassy at

USA nor certified by the Collector and District

Magistrate, Khurdha. The required fees were also not

paid nor the authorization letter was notarized by the

Notary Public in USA. As such, the authorization letter

appended to the plaint is no authorization in the eye of

law. The original authorization letter dtd.12.9.2021

was notarized by the Notary Public of USA on

15.9.2021, which is a day after the filing of the suit

and therefore, as on the date of filling of the suit, there

was no valid authorization. Mr. Mishra has relied upon

the following judgments in support of his contention as

above;

(A)State Bank of Travancore v.

Kingston Computers India Private
Limited; (2011) 11SCC 524.

(B)A. C. Narayanan v. State of
Maharashtra and another, (2014) 11
SCC 790.

R.S.A. No.174 of 2024 Page 19 of 53

            (C)Manisha Mahendra          Gala and
           others    Vs.     Shalini     Bhagwan
           Avatramani and others;
           (2024) 4 SCR 357.


12. Per contra, Mr. Bansidhar Baug would argue

that the authorized person of the Plaintiff not only

signed the plaint but also verified the same and

furnished an affidavit stating that he is authorized by

the Plaintiff and subsequently he filed an authorization

of the Plaintiff, which was later certified by the

embassy. Said authorization not being a power of

attorney is not required to be written on a Stamp Paper

nor any fees are required to be paid. Even otherwise,

mere defect in signing of the pleading, verification and

furnishing of affidavits are curable defects, which

cannot be used to defeat the substantive rights of the

parties. In support of his contentions Mr. Baug has

relied upon the following case laws;

R.S.A. No.174 of 2024 Page 20 of 53

(A)Uday Shankar Triyar v. Ram
Kalewar Prasad Singh and another,
(2006) 1 SCC 75.

(B)United Bank of India v. Naresh
Kumar and others, (1996) 6 SCC 660.

(C)H.D. Revana v. G. Puttaswamy
Gowda and others; (1999) 2 SCC 217.

13. In order to appreciate the contentions advanced

by the parties, it would be apposite to first refer to the

following relevant statutory provisions governing

institution of suits and pleadings etc.

“Section 26 of C.P.C.-Institution of suits-(1) Every
suit shall be instituted by the presentation of a
plaint or in such other manner as may be
prescribed.

(2) In every plaint, facts shall be proved by affidavit.

Order 3, Rule (2) of C.P.C.- Recognized agents –
The recognized agents of parties by whom such
appearances, applications and acts may be made or
done are –

(a) persons holding power of attorney, authorizing
them to make and do such appearances,
applications and acts on behalf of such parties;

(b) persons carrying on trade or business for and in
names of parties not resident within the local limits
of the jurisdiction of the Court within which limits
the appearance, application or act is made or done,
in matters connected with such trade or business
only, where no other agent is expressly authorised

R.S.A. No.174 of 2024 Page 21 of 53
to make and do such appearances, applications and
acts.

Order 4, Rule (1) of C.P.C.- Appointment of
pleader-(1) No pleader shall act for any person in
any Court, unless he has been appointed for the
purpose by such person by a document in writing
signed by such person or by his recognised agent or
by some other person duly authorised by or under a
power-of-attorney to make such appointment.

Order 6, Rule (14) of C.P.C.- 14-A. Address for
service of notice (1) Every pleading, when filed by a
party, shall be accompanied by a statement in the
prescribed form, signed as provided in Rule 14,
regarding the address of the party.

(2)Such address may, from time to time, be changed
by lodging in the Court a form duly filled up and
stating the new address of the party and
accompanied by a verified petition.

(3)The address furnished in the statement made
under Sub-rule (1) shall be called the “registered
address” of the party, and shall, until duly changed
as aforesaid, be deemed to be the address of the
party for the purpose of service of all processes in
the suit or in any appeal from any decree or order
therein made and for the purpose of execution, and
shall hold good, subject as aforesaid, for a period of
two years after the final determination of the cause
or matter.

(4)Service of any process may be effected upon a
party at his registered address in all respects as
though such party resided thereat.

(5)Where the registered address of a party is
discovered by the Court to be incomplete, false or
fictious, the Court may, either on its own motion, or
on the application of any party, order-

(a) in the case where such registered
address was furnished by a plaintiff, stay of
the suit, or

R.S.A. No.174 of 2024 Page 22 of 53

(b) in the case where such registered
address was furnished by a defendant, his
defence be struck out and he be placed in the
same position as if he had not put up any
defence.

(6)Where a suit is stayed or a defence is struck out
under Sub- rule (5), the plaintiff or, as the case may
be, the defendant may, after furnishing his true
address, apply to the Court for an order to set aside
the order of stay or, as the case may be, the
order striking out the defence.

(7)The Court, if satisfied that the party was
prevented by any sufficient cause from filing the
true address at the proper time, shall set aside the
order of stay or order striking out the defence, on
such terms as to costs or otherwise as it thinks fit
and shall appoint a day for proceeding with the suit
or defence, as the case may be.

(8) Nothing in this rule shall prevent the Court from
directing the service of a process at any other
address, if, for any reason, it thinks fit to do so.

Order 6, Rule (15) of C.P.C.- Verification of
pleadings – (1) Save as otherwise provided by any
law for the time being in force, every pleading shall
be verified at the foot by the party or by one of the
parties pleading or by some other person proved to
the satisfaction of the Court to be acquainted with
the facts of the case.

(2) The person verifying shall specify, by reference
to the numbered paragraphs of the pleading, what
he verifies of his own knowledge and what he
verifies upon information received and believed to
be true.

(3)The verification shall be signed by the person
making it and shall state the date on which and the
place at which it was signed.

(4)The person verifying the pleading shall also
furnish an affidavit in support of his pleadings.”

R.S.A. No.174 of 2024 Page 23 of 53

14. From a conjoint reading of the afore quoted

provisions, it is clear that a plaint can be presented by

a person authorized by the plaintiff to do so. Further,

such person must be proved to the satisfaction of the

Court to be acquainted with the facts of the case. In

the instant case, objection has been raised by the

defendants to the plaint on the ground that the

authorized person namely, Akshaya Kumar Parija

being examined as a witness (P.W.2) admitted that he

had no personal knowledge about the Development

Agreement dated 7.8.2020 and Supplementary

Agreement dated 8.8.2020.

15. After going through the plaint averments and the

evidence of P.W.2, this Court is of the considered view

that the requirement of the statute as per Order 6,

Rule 15 of C.P.C. is for the authorized person to be

acquainted with the ‘facts of the case’. In his

examination-in-chief, P.W.2 stated that on 12.9.2021

R.S.A. No.174 of 2024 Page 24 of 53
the Plaintiff was in USA and by a letter of

authorization, he authorized him (P.W.2) to institute

the present case and as per his (Plaintiff) instruction,

the plaint has been drafted. In cross-examination, he

admitted that he does not have any personal

knowledge about the Development Agreement (Ext.A)

and Supplementary Agreement (Ext.B). Plainly

understood, this cannot be understood to mean that

P.W.2 was not aware of the facts of the case though he

was not aware of the agreements in questions. The

above statement cannot be stretched to definitely hold

that he was not aware of the facts leading to filing of

the suit. Therefore, merely because he lacked personal

knowledge about the agreements in question, it cannot

be definitely held that he had no knowledge about the

facts of the case on the whole.

16. Coming to the case laws cited by both parties, it

is seen that in the case of State Bank of Travancore

R.S.A. No.174 of 2024 Page 25 of 53
(supra), the suit was filed by a person without

requisite authority of the Board of Directors. Such is

obviously not the case here. In the case of A.C.

Narayanan (supra) referring to its earlier judgment

passed by the Supreme Court in the case of Janki

Vashdeo Bhojwani v. IndusInd Bank Ltd.;1 the

Supreme Court was dealing with the case of a power of

attorney holder and held that a complaint filed by a

power of attorney holder on behalf of the original

plaintiff is maintainable provided he has personal

knowledge of the transaction in question. Since this

Court, on facts narrated above, has held that the

authorized person cannot be treated as a person not

acquainted with the facts of the case, the judgment

cited would not be applicable. In the case of Manisha

Mahendra Gala (supra) reliance was again placed on

Janki Vashdeo Bhojwani (supra) and the question

under consideration was whether a power of attorney

1
(2005) 2 SCC 217

R.S.A. No.174 of 2024 Page 26 of 53
holder, who had no knowledge regarding transaction

would be examined as a witness. Said case would have

no application to the facts of the present case.

17. Coming to the case laws cited by Mr. Baug, in

Uday Shankar Triyar (supra), the Supreme Court

held that non-compliance with any procedural

requirement relating to a pleading should not entail

automatic dismissal or rejection unless the relevant

statute or rule so mandates. Further, procedural

defects and irregularities, which are curable, should

not be allowed to defeat substantive rights or to cause

injustice. Same view was taken in the case of United

Bank of India (supra) as also in H.D. Revanna

(supra).

18. From the foregoing narration, it is seen that

firstly, from the materials and evidence on record, this

Court is not inclined to accept the contention that the

authorized person (P.W.2) was not acquainted with the

R.S.A. No.174 of 2024 Page 27 of 53
facts of the case so as to hold that there was violation

of the provision under Order 6 Rule 15 of C.P.C.

Secondly, assuming that P.W.2’s admission of

ignorance regarding the agreements in question can be

stretched to hold that he was not acquainted with the

‘facts of the case’ and there was procedural

irregularities in the letter of authorization, the same

being curable in nature cannot be a ground to non-suit

the plaintiff. In other words even assuming there was

some defect or irregularity, the same being curable

cannot come in the way of deciding the substantive

rights of the parties.

The Substantial Question No.(i) is therefore,

answered accordingly against the defendant-appellant.

Substantial Questions Nos. (ii) & (iii).

19. Mr. Mishra learned Senior counsel has referred

to different clauses of the Development Agreement

(Ext.A), Supplementary Agreement (Ext.B) as also the

General Power of Attorney (Ext.2) in this context. He

R.S.A. No.174 of 2024 Page 28 of 53
submits, as per Clause-14 of Ext.A, the Plaintiff agreed

to receive Rs.2.80 crores from the Defendant’s Firm

and as per Clause-7 it was stipulated that the project

shall be completed within 36 months with a grace

period of 6 months from the date of final approval or

the plan. The BMC gave its approval (Ext.B) on

06.9.2021 and therefore, the stipulated period is due

to expire on 15.3.2025. Mr. Mishra further submits, as

per the Supplementary Agreement (Ext.B), the Plaintiff

agreed to receive Rs.15.15 crores in lieu of his 50%

share after adjustment of the amount of Rs.2.80 crores

already paid with the understanding that the balance

amount of Rs.12.35 crores would be paid within 24

months with the grace period of 6 months from the

date of approval/registration of the project by BMC

and ORERA. BMC accorded approval on 16.9.2021 and

therefore, the period of 30 months expired on

15.3.2024. The defendant further paid Rs.40 lakhs in

between 8.8.2020 i.e. the date of execution of the

R.S.A. No.174 of 2024 Page 29 of 53
Supplementary Agreement and 14.9.2021. Therefore,

the stipulated period was due to expire on 15.3.2024.

The Plaintiff however, filed the suit much prior to the

period stipulated for completion of the project i.e.

15.3.2025 and for payment of consideration i.e.

15.3.2024. Therefore, there was no cause of action for

the plaintiff to file the suit either before 15.3.2024 or

15.3.2025.

20. Per contra, Mr.Baug would contend that issues

are framed on the basis of pleadings. In the instant

case, there is no averment in the written statement of

the Defendant that the suit was prematurely filed.

Therefore, no issue was framed by the trial Court.

Further, whether the suit was prematurely filed is a

mixed question of fact and law, which would require

evidence for being answered. Therefore, it cannot be

treated as a substantial question of law. Mr. Baug

further submits that admittedly, the Defendant had

R.S.A. No.174 of 2024 Page 30 of 53
not obtained registration from the ORERA as per the

rules. Section 3 of the Real Estate (Regulation and

Development) Act, 2016 mandates that no promoter

shall advertise, market, book, sell or offer for sale or

invite person to purchase in manner, any plot,

apartment or building as the case may be, before

registration of the project with the ORERA. In the

instant case, however, the Defendant firm, in complete

violation of Section 3 of the Act raised funds from

intending purchasers and advertised the same. This is

also a clear breach of Clause-23 of the Agreement vide

Ext.8. The Plaintiff was therefore, constrained to file

the suit even though the period stipulated in the

agreements had not expired. In the case of Rajesh

Kumar v. Anand Kumar and others2, it was held as

follows;

“The Courts will also frown upon suits which are
not filed immediately after the breach/refusal. The
fact that the limitation is three years does not mean

2
2024 (6) SCALE 450

R.S.A. No.174 of 2024 Page 31 of 53
that a purchaser can wait for one or two years to
file a suit and obtain specific performance.”

21. From the materials and evidence on record, it is

evident that the Defendant firm had accepted money

from prospective purchasers at a time when the

registration of the project had not been obtained from

the ORERA. Though it is stated that the application for

registration was not considered because of an order of

status quo subsisting at the relevant time yet, fact

remains that in such a situation, the Defendant could

not have advertised the project to attract potential

customers or to accept deposits from them. Clause-23

of the Development Agreement is clear that the project

can be advertised only after obtaining registration. This

is therefore, a clear case of breach of contract. Such

being the fact, the Plaintiff was well within his right to

seek necessary declaration by filing the suit even

before expiry of the period stipulated in the Agreement

R.S.A. No.174 of 2024 Page 32 of 53
in view of the ratio decided in the case of Rajesh

Kumar (supra).

Substantial Question Nos.(ii) and (iii) are

therefore, answered accordingly against the Defendant-

Appellant.

Substantial Question No.(iv).

22. According to Mr. Bidyadhar Mishra, learned

Senior counsel for the appellant, the finding of the 1st

Appellate Court that as per Section 55 of the Indian

Contract Act, the Defendant firm has not taken

prompt steps for registration and project approval,

even though considerable period of more than one year

has elapsed nor taken any steps for payment of

balance consideration amount to the Plaintiff is not

legally sustainable in view of the fact that the evidence

on record clearly shows the steps taken by the

Defendant firm to obtain ORERA Registration

Certificate but because of factors beyond its control

such as death of the Managing Partner and onset of

R.S.A. No.174 of 2024 Page 33 of 53
COVID-19 Pandemic, some delay was caused.

Therefore, the finding that the Defendant has not

performed its contractual obligation within a

considerable period of more than one year of the

execution of the agreements is also not legally

sustainable. In the instant case, the time period for

completion of the project was due to expire on

15.3.2025 and that for payment of the balance amount

was 15.3.2024. Both the dates not having expired,

Section 55 of the Contract Act would not be applicable.

That apart, it has not been proved that the terms of the

agreements are uncertain so as to be declared void as

per Section 29 of the Contract Act.

23. Per contra, Mr. Baug would argue that the

original agreements were executed in favour of

M/s.Creative Builders and Consultants, a registered

Partnership firm through its Managing Partner

Bibhuti Bhusan Patra. As per the definition clause of

R.S.A. No.174 of 2024 Page 34 of 53
the agreement vide Ext.8/Ext.A, the Builder-cum-

Developer shall include its legal heirs, successors in

interest or assignees. At the relevant time, the

Partnership firm was comprised of two Partners-

Bibhuti Bhusan Patra and his wife Nirupama Patra.

As per Section 7 of the Indian Partnership Act when

there is no provision in the contract between the

Partners for the duration of their Partnership firm or

the determination of the firm, it must be treated as a

Partnership-at-will. As such, on death of the one of

the Partners the Partnership firm gets automatically

dissolved. Mr. Baug further argues that the

Partnership firm cannot run with one Partner only as

in such event, it would became a proprietorship

concern. Mr. Baug has referred to the provision of

Section 201 of the Contract Act in this regard and

Section 42 (c) of the Partnership Act. Though the

Partnership was purportedly reconstituted, according

to Mr. Baug, it must be treated as a new entity

R.S.A. No.174 of 2024 Page 35 of 53
altogether having no relationship with the earlier

Partnership firm nor it can be said to have stepped into

the shoes of the earlier firm. Therefore, with the

dissolution of the original firm w.e.f. 14.12.2020, the

GPA vide Ext.2 stood automatically terminated so also

the Development and Supplementary Agreements.

Since those documents have the potential of creating

problem in future with regard to the right, title and

interest of the Plaintiff over the suit land, he was

constrained to file the suit seeking necessary

declaration in view of Section 31 of the Specific Relief

Act.

24. There is no dispute that the original Partnership

firm was comprised of two Partners one of whom

namely, Bibhuti Bhusan Patra died on 14.12.2020.

The contentions advanced by Mr. Baug, as noted

above, contradict the stand of the Plaintiff as laid in

the plaint. Firstly, the above plea was never raised in

R.S.A. No.174 of 2024 Page 36 of 53
the plaint and secondly, the Defendant firm has been

described in the following manner;

“M/s.Creative Builders and
Consultants, a registered Partnership
Firm represented through its
Managing Partner Nirupama Patra,
W/o.Late Bibhuti Bhusan Patra, hav
ing its registered office at Plot
No.209/A, Sagheed Nagar, P.O./P.S.-

Saheed Nagar, Bhubaneswar, Dist-

Khordha.”

25. If the plaint averments are read plainly, it would

be evident that the Defendant has admitted the

subsequent developments and has accepted the newly

constituted Partnership firm as well as the existence of

the agreements with the Defendant firm. In other

words, the Plaintiff himself accepts in a way that the

newly constituted firm had stepped into the shoes of

the original firm. The contentions raised before this

Court were significantly never raised either before the

trial Court or before the 1st Appellate Court and

therefore, the same are not acceptable at this stage.

R.S.A. No.174 of 2024 Page 37 of 53

26. Be that as it may, even assuming that the

Agreements and GPA still subsist, the question is, can

the Plaintiff be held entitled to the relief claimed on the

face of non-expiry of the periods for completion of the

project and payment of the balance amount in the

agreements. As has already been held hereinbefore,

apart from raising the plea of non-performance of the

terms of the contract, the Plaintiff has also taken a

specific plea that the terms of the contract were

violated. It would be proper at this stage to refer to the

relevant provisions of the contract i.e., Clause 23 of the

Agreement dated 7.8.2000 (Ext.8/Ext.A), reads as

follows;

“That both the parties hereto agreed that the
SECOND PART the Builder-cum-Developer is free to
advertise, market for the proposed
apartment/residential/commercial units in the said
project as per prescribed rules of Orissa Real
Estate Regulatory Authority (ORERA), over the land
and receive advance from intending purchasers,
execute agreements for the same at the risk of
SECOND PART the Builder-cum-Developer only and
the land owner will not bear any civil or financial
liability for the same.”

R.S.A. No.174 of 2024 Page 38 of 53

27. Chapter-II of the Real Estate (Regulation and

Development) Act, 2016 deals with registration of Real

Estate Project and registration of Real Estate Agents.

Sub-section (1) of Section 3 thereof reads as follows;

Section 3(1)- Prior registration of real estate project
with Real Estate Regulatory Authority.(1) No
promoter shall advertise, market, book, sell sale, or
invite persons to purchase in any manner any plot,
apartment or building, as the case may be, in any
real estate project or part of it in any planning area,
without registering the real estate project with the
Real Estate Regulatory Authority established under
this Act:

Provided that projects that are ongoing on the date
of commencement of this Act and for which the
completion certificate has not been issued, the
promoter shall make an application to the Authority
for registration of the said project within a period of
three months from the date of commencement of this
Act:

Provided further that if the Authority thinks
necessary, in the interest of allottees, for projects
which are developed beyond the planning area but
with the requisite permission of the local authority,
it may, by order, direct the promoter of such project
to register with the Authority, and the provisions of
this Act or the rules and regulations made
thereunder, shall apply to such projects from that
stage of registration.”

28. Chapter-VIII relates to offences, penalties and

adjudication under which Section 59 is the penal

R.S.A. No.174 of 2024 Page 39 of 53
provision for non-registration under Section 3, which

reads as follows;

“Section 59-Punishment for non-registration under
section 3- (1) If any promoter contravenes the
provisions of section 3, he shall be liable to a
penalty which may extend up to ten per cent of the
estimated cost of the real estate project as
determined by the Authority.

(2) If any promoter does not comply with the orders,
directions issued under sub-section (1) or continues
to violate the provisions of section 3, he shall be
punishable with imprisonment for a term extend up
to three years or with fine which may extend up to a
further ten per cent of the estimated cost of the real
estate project, or with both.

This clause relates to the punishment for non-
registration under clause 3.

Sub-clause (1) provides that if any promoter
contravenes the provisions of clause 3, he shall be
liable to a penalty which may extend up to ten per
cent of the estimated cost of the real estate project
as determined by the Authority.

Sub-clause (2) provides that if any promoter does
not comply with the orders, decisions or directions
issued under sub-section (1) or continues to violate
the provisions of clause 3, he shall be punishable
with imprisonment for a term which may extend up
to three years or with fine which may extend up to a
further ten per cent of the estimated cost of the real
estate project, or with both. (Notes on Clauses).”

29. Coming to the facts of the case, it is the specific

case of the Plaintiff that the Defendant firm without

obtaining ORERA Registration Certificate collected

money from the intending purchasers by advertising

R.S.A. No.174 of 2024 Page 40 of 53
the project in violation of the rules and regulations

prescribed by ORERA. It would be profitable to refer to

the specific pleadings of the parties in this regard.

Paragraph-8 of the plaint is relevant and is extracted

herein below;

“That, after receiving the letter from the
defendant the plaintiff became great shocked
that even after lapse of almost one (1) year the
defendant has not able to obtain permission from
the authority and there is no clear specific as to
when the defendant is going to pay the balance
amount which he is entitled to get. Soon after
receiving the letter the plaintiff on dtd.09.08.2021
through email tendered reply to the defendant
stating therein that ‘the BMC Vide its letter no
2217 dated 13.01.21 has directed you to comply
all necessary requirements as per the decision
taken in 2nd DP and BP Committee meeting but,
till date no action has been taken from your side
for obtaining permission. Besides that it is learnt
that without obtaining ORERA registration
certificate, the defendant Firm are collecting
amount from the intending purchasers by
advertising the project which is complete violation
of the rule & regulation prescribed by ORERA. All
the acts done by the defendant’s amounts to
implied refusal to perform the promise under the
agreements and entitling the plaintiff to rescind
the contract. Even such questionable, illegal and
unconscious mechanism of the defendant act will
not only put the project into litigation but the
Plaintiff will be dragged without any fault to such
litigation which will cause immense hardship for
him. This action of the defendant is done in a
calculated manner to siphon off the whopping
amount putting the plaintiff to irreparable loss
and to grab the suit land without giving anything
to the plaintiff. It is hereby stated that the
Defendant Firm is under a lawful obligation pay

R.S.A. No.174 of 2024 Page 41 of 53
the rest amount of Rs.12,35,00,000/- within a
period of 24 months with a grace period of six
months from the date of approval/registration of
the project by the competent authority i.e BMC
and ORERA. It does not mean for an indefinite
period that the defendant at its own will & wish
will obtain the required permission and thereafter
the Plaintiff will be counting the date for getting
the money as per the agreement.”

30. In the written statement filed by the Defendant,

the above referred plaint averments have been

answered in the following manner;

“That, the averment made in paragrpah-8 is
absolutely false and baseless designed for the
purpose of the case, hence denied. There is
nothing to shock after receipt of the letter of the
Defendant Firm rather he will happy that the
Defendant Firm trying to pay off the share of the
owner even before the contractual date.

That, be it stated that the Defendant Firm never
delayed the matter rather during the pandemic
period and demise of the managing partner on
14.12.2020 trying desperately to reconstituted
the Firm and there after submitted the building
plan before the BMC with immediate effect.

That, BMC vide letter No.2217, dt.13.01.2021
directed to comply about 6 conditions and this
defendant firm with much difficulties due to
Covid-19 restriction collected NOC and
compliances as required by the BMC and
deposited the same along with requisite fees of
Rs.64,72,556/- on 25.08.2021 and thereafter the
BMC approved the building plan.

That, after obtaining the building plan the
defendant firm deposited the necessity
application for project approval before the ORERA
but unfortunately the plaintiff submitted an order
of status quo passed by this Court before the

R.S.A. No.174 of 2024 Page 42 of 53
ORERA authority and according the application
for approval of project has been rejected.”

31. Thus, the specific allegation that the Defendant

firm had advertised the project and had collected

money from the intending purchasers has not been

specifically denied. Rather, it is admitted that there

was no registration obtained from the ORERA. Further,

Defendant No.1, being examined as D.W.1, apart from

admitting in her evidence that the project was not

registered with ORERA also clearly admitted of having

received Rs.35 lakhs from her nephew (husband’s

brother) and also described him as ‘prospective buyer’.

Of course, she also said that said Rs.35 lakhs was paid

as part of Rs.2.8 crores paid to the plaintiff but, as

held by both the Courts below, there is no evidence in

support of such stand. Further, both the Courts below

have taken note of the above admission of D.W.1 to

hold that there was violation of the contractual

obligations by the defendant firm. This Court, after

R.S.A. No.174 of 2024 Page 43 of 53
considering the evidence independently, finds no

reason to differ.

32. That apart, the plea that non-registration of the

project with ORERA was because of an order of status

quo passed by the trial Court is hardly acceptable in

the absence of any order or communication made by

the ORERA with the defendant firm indicating non-

grant of the registration and more so, for the reason

cited above. Even otherwise, accepting for a moment

that non-registration of the project by ORERA was

because of reasons beyond control of the defendant, it

is immaterial in the present context because the same

cannot justify collection of amount from the

prospective buyer as mentioned above. This is a clear

violation of Section 3 read with Section 59 of the RERA

Act. There was specific contract between the parties as

reflected in Clause-23 that the Defendant Firm was

free to advertise and market for the proposed project

‘as per prescribed rules of ORERA’ and receive advance

R.S.A. No.174 of 2024 Page 44 of 53
from intending purchasers, execute agreements for the

same at its own risk and the land owner would not

bear any civil or financial liability for the same.

Therefore, this amounts to a clear breach of the

contract. As has already been held hereinbefore,

despite non-expiry of the period stipulated in the

contract for its performance, the Plaintiff was justified

in filing the suit in view of the breach of the contract.

Though the 1st Appellate Court has not approached the

issue from the above perspective yet, this Court

concurs with its findings for the reasons indicated

above.

The substantial question No.(iv) is therefore,

answered against the Defendant.

Substantial Question No.(v).

33. In this context, in assailing the findings of the

trial Court in paragraph-13 of its judgment, Mr.

Mishra, learned Senior counsel would argue that the

Defendant firm has spent huge amount of money for

R.S.A. No.174 of 2024 Page 45 of 53
obtaining necessary NOCs and permissions from

different authorities as also paid Rs.3.20 crores to the

Plaintiff. As such, a substantial and subsisting interest

was created in its favour for which no action

prejudicial to its interest can be taken under Sections

202 to 205 of the Contract Act. In this regard, Mr.

Mishra has relied upon a judgment of Supreme Court

rendered in the case of T. Seshareddy (D) Rep. by his

LR.-cum-Irrevocable GPA holder and Assignee

Kotamreddy Kodandarami v. State of Karnataka

and others (S.L.P (C) Nos.6354 and 6356 of 2020

decided on 9.11.2022).

34. Per contra, Mr. Baug would argue that the

judgment of the trial Court having merged with the

judgment of confirmation passed by the 1st Appellate

Court, the findings in question of the trial Court under

Paragraph-13 have lost its importance. Since the

Second Appeal has been filed challenging the

R.S.A. No.174 of 2024 Page 46 of 53
confirming judgment, the finding of the trial Court

rendered under Paragraph-13 of the judgment cannot

be considered as a substantial question of law.

35. After considering the rival submissions as above,

this Court finds that the findings rendered by the trial

Court have in fact merged in the judgment passed by

1st Appellate Court and the decree has been drawn up

accordingly. Nevertheless, this Court having already

held that the Plaintiff was justified to step out of the

contract because of its breach, the said question

automatically pales into insignificance not warranting

any further attention of this Court much less as a

substantial question of law.

The question so formulated is therefore,

answered accordingly against the Defendant.

Substantial Question No.(vi).

36. It has been argued by Mr. Mishra, learned

Senior counsel that the finding of the 1st Appellate

Court that the Defendant-Appellant had not proved

R.S.A. No.174 of 2024 Page 47 of 53
any material to show that it had made due diligence for

obtaining and presenting the evidence before the trial

Court even though the same are of prior to the

institution of the suit cannot be sustained because the

documents in question could not be marked as

exhibits as their presence could not be known at the

relevant time which is a plausible plea having regard to

the fact that the Managing Partner late Bibhuti

Bhusan Patra was dealing with the records and had

kept the same in his custody.

37. Per contra, Mr. Baug contends that the

Defendant has not been able to prove that the

documents in question were not within its possession

during pendency of the suit being kept under lock and

key. When it is the case of the Defendant that the same

firm was reconstituted with one of the earlier Partners

becoming the Managing Partner of the new firm, it is

hardly believable that she would not have had access

R.S.A. No.174 of 2024 Page 48 of 53
to all documents particularly when she has made all

correspondence relating to the agreement repeatedly

with the Plaintiff. Even otherwise, according to

Mr. Baug, these documents would not improve the

case of the Defendant in any manner nor are of such

nature as are essentially required by the Court to give

judgment in the case.

38. After considering the rival submissions as noted

above, this Court holds that even if the requirement of

exhibiting due diligence as contemplated under Order

41, Rule 27 of C.P.C. can be dispensed with, it is still

necessary for the Defendant to prove that the

documents in question are germane to the case and

are essentially required for a just decision of the case.

Even before this Court, the Defendant-Appellant has

not been able to demonstrate that but for the

documents sought to be adduced as additional

evidence, the judgment would have been otherwise.

R.S.A. No.174 of 2024 Page 49 of 53
This Court therefore, finds nothing wrong in the

impugned judgment in so far as it relates to rejection

of the application for adducing additional evidence.

The substantial question of law is answered

accordingly.

39. Apart from the aforementioned substantial

questions of law, an additional question was raised by

the Appellant, i.e. valuation of the suit. According to

the Defendant, the suit was grossly undervalued being

valued at Rs.1,00,000/- only. The suit was filed on the

pleading that the Plaintiff had received Rs.3.20 crores

out of total consideration of Rs.15.15 crores. The trial

Court brushed aside the objection relating to under

valuation on the ground that no objection had been

raised by the office and the 1st Appellate Court also

erroneously held that there was no irregularity in this

regard.

R.S.A. No.174 of 2024 Page 50 of 53

40. Per contra, Mr. Baug would argue that the

question of valuation of a suit is a matter between the

State and the Plaintiff over which the Defendant has

no say. Even otherwise, the Plaintiff has valued the

suit at Rs.1,00,000/- as per Section 7(iv) (c) of the

Court Fees Act and accordingly paid ad valorem court

fee of Rs.4185/-. Mr. Baug further argues that if the

arguments of the Defendant were to be accepted then

in order to prove its bonafides, the Second Appeal

should have been valued accordingly on the valuation

of Rs.15.15 crores and appropriate court fee should

have been paid.

41. Without entering into the merits of the rival

contentions as noted above, this Court finds that the

suit was one for declaration. As such, the Plaintiff was

within his right to value the suit as provided under

Section 7 (iv) (c) of the Court Fees Act. This Court

therefore, rejects the plea of undervaluation of the suit.

R.S.A. No.174 of 2024 Page 51 of 53

Conclusion.

42. Thus, from a conspectus of the analysis of facts,

evidence and law as discussed before, this Court finds

that none of the questions raised in the appeal can be

treated as substantial questions of law requiring

adjudication by this Court as the 2nd Appellate Court.

Moreover, the appeal being against a confirming

judgment, it is the settled position of law that the 2nd

Appellate Court would be slow to interfere unless it can

be demonstrated that there was any patent illegality or

perversity or finding against the weight of evidence on

record so as to be persuaded to interfere. Reference in

this regard may be had to the judgment of the

Supreme Court in the case of S. Appadurai Nadar &

another v. A. Chokalinga Nadar and another3;

43. For the foregoing reasons therefore, this Court

finds no justified reason to interfere with the

3
(2007) 12 SCC 774

R.S.A. No.174 of 2024 Page 52 of 53
concurrent findings of facts rendered by both the

courts below.

44. Resultantly, the appeal is found to be devoid of

merit and is therefore, dismissed, but in the

circumstances, without any cost.

…………………………….
Sashikanta Mishra,
Judge

Ashok Kumar Behera

Signature Not Verified
Digitally Signed
Signed by: ASHOK KUMAR BEHERA
Reason: Authentication
Location: High Court of Orissa, Cuttack
Date: 30-Sep-2024 11:02:04

R.S.A. No.174 of 2024 Page 53 of 53

Source link

Leave a Reply

Your email address will not be published. Required fields are marked *