Legally Bharat

Supreme Court of India

Kali Charan vs The State Of Uttar Pradesh on 26 November, 2024

Author: B.R. Gavai

Bench: B.R. Gavai

2024 INSC 898
                                                                   REPORTABLE

                                     IN THE SUPREME COURT OF INDIA
                                      CIVIL APPELLATE JURISDICTION

                                   CIVIL APPEAL NO(S).               OF 2024
                                (Arising out of SLP(Civil) No(s). 15782 of 2023)

             KALI CHARAN AND OTHERS                                …APPELLANT(S)


                                     VERSUS


             STATE OF U.P. AND OTHERS                             …RESPONDENT(S)

                                                    WITH

                                   CIVIL APPEAL NO(S).               OF 2024
                                (Arising out of SLP(Civil) No(s). 15535 of 2023)

                                    CIVIL APPEAL NO(S).              OF 2024
                            (Arising out of SLP(Civil) No(s). 19512-19513 of 2023)

                                    CIVIL APPEAL NO(S).              OF 2024
                            (Arising out of SLP(Civil) No(s). 19510-19511 of 2023)

                                   CIVIL APPEAL NO(S).               OF 2024
                                (Arising out of SLP(Civil) No(s). 24970 of 2023)

                                   CIVIL APPEAL NO(S).               OF 2024
                                (Arising out of SLP(Civil) No(s). 20314 of 2023)

                                    CIVIL APPEAL NO(S).              OF 2024
                                (Arising out of SLP(Civil) No(s).     of 2024)
                                                          (D. No. 34908/2023)
   Signature Not Verified

   Digitally signed by
   DEEPAK SINGH
                                    CIVIL APPEAL NO(S).              OF 2024
   Date: 2024.11.26
   16:42:29 IST
   Reason:
                                (Arising out of SLP(Civil) No(s).    of 2024)
                                                          (D.No. 35223/2023)


                                                                                     1
       CIVIL APPEAL NO(S).               OF 2024
    (Arising out of SLP(Civil) No(s). 24969 of 2023)

       CIVIL APPEAL NO(S).               OF 2024
    (Arising out of SLP(Civil) No(s). 24971 of 2023)

        CIVIL APPEAL NO(S).               OF 2024
     (Arising out of SLP(Civil) No(s). 23732 of 2023)

        CIVIL APPEAL NO(S).               OF 2024
     (Arising out of SLP(Civil) No(s). 23727 of 2023)

        CIVIL APPEAL NO(S).               OF 2024
     (Arising out of SLP(Civil) No(s). 25000 of 2023)

       CIVIL APPEAL NO(S).               OF 2024
    (Arising out of SLP(Civil) No(s). 16057 of 2023)

       CIVIL APPEAL NO(S).               OF 2024
    (Arising out of SLP(Civil) No(s). 17876 of 2023)

        CIVIL APPEAL NO(S).               OF 2024
     (Arising out of SLP(Civil) No(s). 17015 of 2023)

        CIVIL APPEAL NO(S).               OF 2024
     (Arising out of SLP(Civil) No(s). 21488 of 2023)

        CIVIL APPEAL NO(S).               OF 2024
(Arising out of SLP(Civil) No(s). 17888-17889 of 2023)

        CIVIL APPEAL NO(S).              OF 2024
(Arising out of SLP(Civil) No(s). 18703-18704 of 2023)

        CIVIL APPEAL NO(S).              OF 2024
(Arising out of SLP(Civil) No(s). 19514-19515 of 2023)

        CIVIL APPEAL NO(S).              OF 2024
(Arising out of SLP(Civil) No(s). 18705-18718 of 2023)

        CIVIL APPEAL NO(S).              OF 2024
(Arising out of SLP(Civil) No(s). 19222-19226 of 2023)


                                                         2
   CIVIL APPEAL NO(S).               OF 2024
(Arising out of SLP(Civil) No(s). 18885 of 2023)

   CIVIL APPEAL NO(S).               OF 2024
(Arising out of SLP(Civil) No(s). 19904 of 2023)

   CIVIL APPEAL NO(S).               OF 2024
(Arising out of SLP(Civil) No(s). 21354 of 2023)

   CIVIL APPEAL NO(S).               OF 2024
(Arising out of SLP(Civil) No(s). 20605 of 2023)

   CIVIL APPEAL NO(S).               OF 2024
(Arising out of SLP(Civil) No(s). 20486 of 2023)

   CIVIL APPEAL NO(S).               OF 2024
(Arising out of SLP(Civil) No(s). 20634 of 2023)

   CIVIL APPEAL NO(S).               OF 2024
(Arising out of SLP(Civil) No(s). 21500 of 2023)

   CIVIL APPEAL NO(S).               OF 2024
(Arising out of SLP(Civil) No(s). 21330 of 2023)

   CIVIL APPEAL NO(S).               OF 2024
(Arising out of SLP(Civil) No(s). 20541 of 2023)

   CIVIL APPEAL NO(S).               OF 2024
(Arising out of SLP(Civil) No(s). 21446 of 2023)

   CIVIL APPEAL NO(S).               OF 2024
(Arising out of SLP(Civil) No(s). 22041 of 2023)

   CIVIL APPEAL NO(S).               OF 2024
(Arising out of SLP(Civil) No(s). 21495 of 2023)

   CIVIL APPEAL NO(S).               OF 2024
(Arising out of SLP(Civil) No(s). 7247 of 2024)




                                                   3
                                                    JUDGMENT

 Mehta, J.

Table of Contents

INTRODUCTION ………………………………………………………………………………………………… 4
BATCH NO. 1- LANDOWNERS’ APPEALS @ SPECIAL LEAVE PETITIONS ……………….. 5
BATCH NO. 2- YEIDA APPEALS @ SPECIAL LEAVE PETITIONS ……………………………. 6
BRIEF FACTS …………………………………………………………………………………………………… 6
SUBMISSIONS ON BEHALF OF LANDOWNERS (APPELLANTS IN BATCH NO. 1): ……… 15
SUBMISSIONS ON BEHALF OF YEIDA (RESPONDENT NO.3 IN BATCH NO. 1): – ………. 26
DISCUSSION AND FINDINGS: – ………………………………………………………………………….. 38
CONCLUSION ………………………………………………………………………………………………….. 44

1. Delay in filing application(s) for setting aside of abatement is

condoned.

2. Abatement is set aside.

3. Delay in filing the application(s) for substitution is condoned.

4. Application(s) for substitution is allowed.

5. Application(s) for transposition is allowed.

6. Application(s) for intervention/impleadment is allowed.

7. Leave granted.

INTRODUCTION

8. The present batch of civil appeals @ special leave petitions arise

out of the land acquisition proceedings initiated by respondent No.1-

4
State of Uttar Pradesh1 for planned development in the District

Gautam Budh Nagar, Uttar Pradesh, through respondent No.3-

Yamuna Expressway Industrial Development Authority2 by invoking

‘urgency provisions’ incorporated in Sections 17(1) and 17(4) of the

Land Acquisition Act, 18943.

9. Arguments on all the appeals @ special leave petitions have

been heard analogously and are being disposed of vide this common

judgment.

10. In total, 35 civil appeals @ special leave petitions are preferred

both by landowners and YEIDA which can be categorized into two

batches as mentioned below:

BATCH NO. 1- LANDOWNERS’ APPEALS @ SPECIAL LEAVE
PETITIONS

11. A total of 29 civil appeals @ special leave petitions have been

filed by the landowners challenging the decision of the Division Bench

of the Allahabad High Court in “Kamal Sharma v. State of U.P. thru

Special Secretary Industrial Development and Ors4”. The appeal

1 hereinafter being referred to as ‘State’
2 hereinafter being referred to as ‘YEIDA’
3 hereinafter being referred to as “the Act”
4 Writ-C No. 26767 of 2010; hereinafter referred to as ‘Kamal Sharma’

5
@ special leave petition titled “Kalicharan v. State of U.P. and

others5” is being treated as the lead matter in this batch.

BATCH NO. 2- YEIDA APPEALS @ SPECIAL LEAVE PETITIONS

12. The YEIDA has filed 6 appeals @ special leave petitions

challenging various decisions of the Division Bench of the Allahabad

High Court invalidating the self-same land acquisition proceedings for

integrated development of notified areas including the decision in

“Shyoraj Singh and Others v. State of U.P.6”. The appeal @ special

leave petition titled “YEIDA v. Shyoraj Singh and Ors.7” is being

treated as the lead matter in this batch.

BRIEF FACTS

13. The chronology of events leading to the filing of these civil

appeals are as follows.

14. For the sake of convenience, we shall refer to the factual context

as noticed in Writ-C No. 26767 of 2010 titled as “Kamal Sharma v.

State of U.P. thru Special Secretary Industrial Development and

Ors.8(lead matter in Batch No.1) filed before the Allahabad High Court.

5 SLP(C) No. 15782 of 2023
6 Writ-C No. 30747 of 2010; hereinafter referred to as ‘Shyoraj Singh’
7 SLP(C) Nos. 19512-19513 of 2023
8 Supra, Note 4

6

15. Upon receipt of a proposal from the Director, Land Acquisition

Directorate, Rajswa, Uttar Pradesh, with prior approval of the State

Government, a notification dated 26th February, 2009 was issued

under Section 4(1)9 read with Sections 17(1)10 and 17(4)11 of the Act

for the acquisition of the tracts of lands in question for planned

development in the District Gautam Budh Nagar, Uttar Pradesh. The

relevant portion of the aforesaid notification is extracted below: –

“Under sub-section (1) of section 4 of the Land Acquisition Act,
1894 (Act No. 1 of 1894), the Governor hereby notifies for the
information of the general public that the land mentioned in the
Schedule below shall be earmarked for public purposes,
namely, the Yamuna Expressway Industrial Development
Authority in District Gautam Budh Nagar for Planned
Development.

Because the Governor is of the opinion that the provisions
or sub-section (1) of section 17 of the said Act apply to the
said land, because the said land is urgently needed for
planned development in district Gautam Buddha Nagar
through Yamuna Expressway Industrial Development
Authority and in view of this urgency, it is also necessary
that the possible delay in conducting the Investigation

9 4. Publication of preliminary notification and power of officers thereupon. –

(1) Whenever it appears to the [appropriate Government] the land in any locality [is needed
or] is likely to be needed for any public purpose [or for a company], a notification to that effect
shall be published in the Official Gazette [and in two daily newspapers circulating in that
locality of which at least one shall be in the regional language], and the Collector shall cause
public notice of the substance of such notification to be given at convenient places in the said
locality [(the last of the dates of such publication and the giving of such public notice , being
hereinafter referred to as the date of the publication of the notification)].
10 17. Special powers in case of urgency. –

(1) In cases of urgency, whenever the [appropriate Government], so directs, the Collector,
though no such award has been made, may, on the expiration of fifteen days from the
publication of the notice mentioned in section 9, sub-section (1). [take possession of any land
needed for a public purpose]. Such land shall thereupon vest absolutely in the [Government],
free from all encumbrances.

11 17. Special powers in case of urgency. –

(4) In the case of any land to which, in the opinion of the [appropriate Government], the
provisions of sub-section (1) or sub-section (2) are applicable, the [appropriate Government]
may direct that the provisions of section 5A shall not apply, and, if it does so direct, a
declaration may be made under section 6 in respect of the land at any time [after the date of
the publication of the notification] under section 4, sub-section (1).

7

under Section 5-A of the said Act should be avoided.

Therefore, the Governor also directs under sub-section (4)
of Section 17 of the said Act that the provisions of Section
5-A of the said Act shall not apply.”
(emphasis supplied)

16. Since the land was sought to be acquired by invoking urgency

provisions under Sections 17(1) and 17(4) of the Act, the landowners

made representations to the Chief Executive Officer(‘CEO’) of YEIDA

requesting that their land may not be acquired because the status of

the land was ‘Abadi Bhoomi’ which was being used by the landowners

as dwelling units and for rearing their cattle. The

functionaries/authorities concerned did not accede to the request of

the landowners and the State Government issued the notification

dated 19th February, 2010 under Section 6 of the Act.

17. The landowners challenged the acquisition of their lands by

filing numerous writ petitions before the Allahabad High Court,

primarily seeking the relief of quashing the acquisition proceedings

undertaken by invoking Sections 4 and 6 read with Sections 17(1) and

17(4) of the Act on several grounds which may be broadly categorized

as below: –

(i) That the State Government arbitrarily invoked Section

17(1) and Section 17(4) of the Act and deprived the

8
landowners of their valuable right to raise objections

under Section 5-A of the Act.

(ii) That a bare reading of the notification issued under

Section 4 would reflect that there was no material with

the State Government for invoking the urgency clause

in the matter of acquisition of land for planned

development.

(iii) That there was no genuine public purpose behind the

acquisition and thus, the impugned action was illegal,

arbitrary and unjustified.

18. These writ petitions were decided by the Allahabad High Court

taking divergent views which are assailed in these appeals by special

leave.

19. The Division Bench of the Allahabad High Court vide judgment

dated 24th April, 2017 allowed the Writ-C No. 30747 of 2010 titled

Shyoraj Singh and quashed the land acquisition notifications in

question holding that the grounds being taken in the impugned

notifications for invocation of the urgency clause were arbitrary and

bad in law. The learned Division Bench in Shyoraj Singh summoned

the original records from the State Government and perused the same

to arrive at the following conclusions: –

9

(i) The Division Bench referred to two letters issued by the

authorities of the District Gautam Budh Nagar, the details of

which are as follows:

(a) A letter justifying the invocation of the urgency clause

signed by the Additional Chief Executive Officer of

Yamuna Expressway, Tehsildar, Naib Tehsildar, and

Lekhpal. The relevant extract from the said letter is as

below: –

“Yamuna expressway urgently needs the proposed land
for planned industrial development. In the event of delay
in the acquisition, there is a strong possibility of
increasing encroachment on the proposed land, due to
which public interest project of planned industrial
development will adversely be affected.”
“Hearing and disposal of written/oral objections will
definitely take years and there will be unexpected delays
which will stall the planned development.”

(b) A letter issued in 2010 by the District Magistrate,

recording a satisfaction that the prevailing facts and

circumstances justified the invocation of the powers

under Section 17 of the Act for dispensing with the

hearing of objections under Section 5-A of the Act. The

relevant extract from the said letter is as below:

“Due to the need to complete the project without delay
in the acquisition of the said land, it is necessary to take
possession of the proposed land with immediate effect.
In the case of using Section 17 of LAA, the provisions of
10
Section 5-A of the Act become extinct and I fully agree
with the justification of ending the opportunity of
hearing to the land owners.”

With reference to the aforesaid letters, the Division Bench

observed that the two grounds mentioned for invoking urgency

clause were: (1) That there are chances of unauthorized

construction/encroachment on the said land. (2) Large number of

landowners would be affected by the acquisition and hearing such

large number of landowners would delay the project.

The Division Bench in Shyoraj Singh held that the above-

noted factors did not furnish legally acceptable justification for the

exercise of power under Section 17(1) of the Act by the State

Government because the acquisition was primarily meant to cater

to private interests in the name of industrial development of the

District and no material was produced on record to show that the

State Government and/or agencies/instrumentalities of the State

were intending to establish industrial units on the acquired tracts

of land. Further, the justification for invoking urgency provisions,

that the land will be encroached on, had no substance as the land

was already in possession of the recorded tenure holders.

(ii) The Division Bench also observed that the notification under

Section 4 of the Act was published on 26th February, 2009 but

11
thereafter, the State Government took nearly one year to publish

the notification under Section 612 of the Act. The time of one year

consumed by the State Government in publishing the notification

under Section 6 of the Act was by itself sufficient to infer that there

was absolutely no urgency that could have justified the invocation

of the urgency clause, thereby depriving the landowners of an

opportunity of hearing under Section 5-A of the Act.

20. However, another Division Bench of the Allahabad High Court

while dealing with a batch of 73 writ petitions challenging the very

same land acquisition proceedings took a different view from Shyoraj

Singh and dismissed the writ petitions filed by the landowners, the

lead matter being Writ-C No. 26767 of 2010 titled “Kamal Sharma v.

State of U.P.”. The Division Bench while upholding the acquisition

proceedings held that it could not be accepted that the entire exercise

for invocation of urgency clause was mechanical or there was no

material with the State for recording the subjective satisfaction to this

effect. The reasons assigned by the Division Bench in Kamal Sharma

were as follows: –

(i) A perusal of the Master plan and the facts established

that the land required for development of Yamuna

12 Published on 19th Feb, 2010.

12

Expressway [‘Planned development through Yamuna

Expressway’] was for an integrated project. The land

was initially acquired for the Yamuna Expressway

and, thereafter, for developing land parcels alongside

the Expressway as townships.

(ii) The original record of the State contains a categorical

statement that the State Government, after

scrutinizing the record had accepted the proposal

applying mind to the fact that, in case the objections

under Section 5-A of the Act were invited, it would

adversely affect and cause delay in execution of the

project of public importance. The said decision was

made looking at the enormity of the project which

required the acquisition of the lands spread over a

large area of 18,000 hundred acres (approx.)

comprising 16 villages. The development of the village

‘Abadi Bhoomi’s by YEIDA was also linked to the

development of the land alongside the Expressway. It

was not the case of non-application of mind and no

fault in the decision-making process could be

demonstrated.

13

(iii) There was no post-notification delay, inasmuch as, in

two or three acquisition notifications, which were the

subject matter of challenge in the present writ

petitions, wherein one year time has been consumed

in the issuance of the Section 6 notification, the delay

has been duly explained by the State.

21. In Kamal Sharma, the Division Bench distinguished Shyoraj

Singh noting that the said judgment failed to consider the fact that

the acquisition was proposed for an integrated project and that the

Division Bench did not deal with the argument that looking at the large

number of tenure holders, the hearings would have resulted into the

project of tremendous importance being delayed. Further, it was noted

that the reasons given for justifying the invocation of the urgency

clause had not been examined in the context in which they were made,

and also the decision of this Court in the case of Nand Kishore Gupta

and Others v. State of Uttar Pradesh and Others.13 was not

considered.

22. The Division Bench of the Allahabad High Court while delivering

the judgment in Kamal Sharma, validated the acquisition proceeding

13 (2010) 10 SCC 282; hereinafter referred to as ‘Nand Kishore’

14
in question and granted an enhanced compensation of 64.7% to the

landowners.

23. During the course of arguments, this Court was apprised of the

fact that out of total 410 writ petitioners(landowners) before the High

Court, only 96 have challenged the judgment in Kamal Sharma by

filing civil appeals @ special leave petitions in Batch No. 1.

24. It is in this backdrop of the conflicting decisions rendered by

the Division Benches of the Allahabad High Court, that the two

batches of civil appeals @ special leave petitions i.e. Batch No.1 and

Batch No.2, have been preferred by the landowners and YEIDA before

this Court.

SUBMISSIONS ON BEHALF OF LANDOWNERS (APPELLANTS IN
BATCH NO. 1): –

25. Learned counsel representing the landowners implored the

Court to grant relief in favour of the appellants as prayed for in Batch

No.1 wherein lead matter is “Kalicharan and others v. The State of

Uttar Pradesh and others14” and negate the challenge to the

judgment in Shyoraj Singh. They advanced the following pertinent

14 supra

15
submissions for assailing the questioned land acquisition

proceedings:-

(i) That the Division Bench of Allahabad High Court, while

rendering the judgment dated 26th May, 2023 in Kamal

Sharma, in effect sat in appeal over the judgment dated 24th

April, 2017 in Shyoraj Singh rendered by a coordinate bench

of the same High Court which dealt with an identical

controversy both in facts and law. It was fervently contended

that the Division Bench of Allahabad High Court, while

dealing with the subsequent batch of writ petitions in Kamal

Sharma should have followed the judgment passed in

Shyoraj Singh as a matter of judicial discipline.

(ii) That if at all the Division Bench in Kamal Sharma was of a

view that Shyoraj Singh did not lay down the correct

position of law, then the question of law should have been

referred to a larger Bench rather than taking a divergent view

in a Bench with a composition of same number of Judges.

(iii) That the land acquisition notifications under Sections 4 and

6 of the Act were dated 26th February, 2009 and 19th February

2010, respectively. The above-mentioned dates demonstrate

that about one years’ time was taken by the State

16
Government for issuance of the final declaration notification

under Section 6 after the proposal under Section 4 of the Act

was issued and thus, there was pre and post notification

delay which could not have been ignored and had to be taken

into account. In this background there could not have been

any justification for the dispensation of few weeks’ time to the

landowners to file objections under Section 5-A of the Act, on

the ground of urgency. On this aspect, reliance was placed

upon Radhy Shyam(dead) through LRs. and Others v.

State of Uttar Pradesh and Others15, wherein this Court

observed as follows: –

“82. In this case, the Development Authority sent the
proposal sometime in 2006. The authorities up to the level of
the Commissioner completed the exercise of survey and
preparation of documents by the end of December 2006 but
it took one year and almost three months for the State
Government to issue notification under Section 4 read with
Sections 17(1) and 17(4). If this much time was consumed
between the receipt of proposal for the acquisition of land and
issue of notification, it is not possible to accept the argument
that four to five weeks within which the objections could be
filed under sub-section (1) of Section 5-A and the time spent
by the Collector in making enquiry under sub-section (2) of
Section 5-A would have defeated the object of the
acquisition.”

15 (2011) 5 SCC 553; hereinafter referred to as ‘Radhy Shyam’

17
Reliance in this regard was also placed on Dev Sharan and

Others v. State of Uttar Pradesh and Others16, wherein

this Court observed as below: –

“37 [Ed.: Para 37 corrected vide Official Corrigendum No.
F.3/Ed.B.J./16/2011 dated 16-3-2011.]. Thus the time
which elapsed between publication of Section 4(1) and
Section 17 notifications, and Section 6 declaration in the
local newspapers is 11 months and 23 days i.e. almost one
year. This slow pace at which the government machinery had
functioned in processing the acquisition, clearly evinces that
there was no urgency for acquiring the land so as to warrant
invoking Section 17(4) of the Act.

38. In Para 15 of the writ petition, it has been clearly stated
that there was a time gap of more than 11 months between
Section 4 and Section 6 notifications, which demonstrates
that there was no urgency in the State action which could
deny the petitioners their right under Section 5-A. In the
counter which was filed in this case by the State before the
High Court, it was not disputed that the time gap between
Section 4 notification read with Section 17, and Section 6
notification was about 11 months.”

Learned counsel for the appellants also placed reliance on

Devender Kumar Tyagi and Others v. State of Uttar

Pradesh and Others17, wherein, this Court, while dealing

with a post-notification delay of almost two years, held as

follows:

“28. In the facts and circumstances of the present case,
it is clear that this Court, vide its order dated 17-8-2004
[(2011) 12 SCC 572], has issued a direction to the
respondents to relocate the bone mills and allied industries
causing environment pollution and health hazards as per the
recommendations of CPCB and, inter alia, the respondents

16 (2011) 4 SCC 769
17 (2011) 9 SCC 164

18
were also directed to identify the area for relocation.

Pursuant to this, the respondents have filed an affidavit in
the month of December 2004 specifying the construction of
the Leather City Project at Hapur in Ghaziabad.
Subsequently, it was only after the lapse of two years, the
State Government had issued a Notification under Section 4
on 3-7-2006 and the same was published on 4-7-2006.
Thereafter, the State Government took more than 17 months
in order to make a declaration of the notification under
Section 6 from the date of publication of the notification
under Section 4 of the LA Act. In view of the above
circumstances, it is crystal clear that the government
functionary has proceeded at very slow pace at two levels,
that is, prior to the issuance of the notification under Section
4 and post the issuance of the notification under Section 4,
for acquisition of the land for construction of the Leather City
Project, which undoubtedly is a public purpose. Therefore,
the above series of the events amply exhibit the lethargical
and lackadaisical attitude of the State Government. In the
light of the above circumstances, the respondents are not
justified in invoking the urgency provisions under Section 17
of the LA Act, thereby, depriving the appellants of their
valuable right to raise objections and opportunity of hearing
before the authorities in order to persuade them that their
property may not be acquired.

Further reliance was placed on the case of Darshan Lal

Nagpal(Dead) by LRs. v. Government of NCT of Delhi and

Others18, wherein, this Court observed as below:

“36. It needs no emphasis that majority of the projects
undertaken by the State and its agencies/instrumentalities,
the implementation of which requires public money, are
meant to benefit the people at large or substantially a large
segment of the society. If what the High Court has observed
is treated as a correct statement of law, then in all such cases
the acquiring authority will be justified in invoking Section
17 of the Act and dispense with the inquiry contemplated
under Section 5-A, which would necessarily result in
depriving the owner of his property without any opportunity
to raise legitimate objection. However, as has been repeatedly
held by this Court, the invoking of the urgency provisions can
be justified only if there exists real emergency which cannot
18 (2012) 2 SCC 327

19
brook delay of even few weeks or months. In other words, the
urgency provisions can be invoked only if even small delay of
few weeks or months may frustrate the public purpose for
which the land is sought to be acquired. Nobody can contest
that the purpose for which the appellants’ land and land
belonging to others was sought to be acquired was a public
purpose but it is one thing to say that the State and its
instrumentality wants to execute a project of public
importance without loss of time and it is an altogether
different thing to say that for execution of such project,
private individuals should be deprived of their property
without even being heard.”

(iv) That one of the grounds taken by the State for invoking the

urgency clause was that there were chances of unauthorized

construction/encroachments on the land subject to

acquisition. This stand was questioned by placing reliance on

Radhy Shyam, wherein this Court observed that it is highly

unlikely that the recorded tenure holders would encroach or

allow encroachments on their own land when they are

admittedly in the possession of the same. The relevant extract

as relied upon is quoted hereinbelow: –

“83. The apprehension of the respondents that delay in the
acquisition of land will lead to enormous encroachment is
totally unfounded. It is beyond the comprehension of any
person of ordinary prudence to think that the landowners
would encroach their own land with a view to frustrate the
concept of planned industrial development of the district.”

(v) That there was no material before the State Government to

show the existence of any unforeseeable emergency

20
warranting invocation of the urgency clause under Sections

17(1) and 17(4) of the Act, thereby denying the landowners of

their right to file objections against acquisition of their lands.

(vi) That the lands under acquisition were to be utilized for

commercial and residential purposes and such development

work, would take ample time in planning and execution, thus

there could have been no justification for the invocation of

urgency clause. Reliance in this regard was placed on the

following observations in Radhy Shyam:-

“80……Even if planned industrial development of the district
is treated as public purpose within the meaning of Section 4,
there was no urgency which could justify the exercise of
power by the State Government under Section 17(1) and
17(4). The objective of industrial development of an area
cannot be achieved by pressing some buttons on the
computer screen. It needs a lot of deliberations and planning
keeping in view various scientific and technical parameters
and environmental concerns. The private entrepreneurs, who
are desirous of making investments in the State, take their
own time in setting up the industrial units. Usually, the State
Government and its agencies/instrumentalities would give
them two to three years to put up their factories,
establishments, etc. Therefore, time required to ensure
compliance with the provisions contained in Section 5A
cannot, by any stretch of imagination, be portrayed as delay
that will frustrate the purpose of acquisition.”

21
Reliance was also placed upon the decision of Anand Singh

and Another v. State of Uttar Pradesh and Others19,

wherein this Court observed as follows: –

“46. As to in what circumstances the power of emergency
can be invoked are specified in Section 17(2) but
circumstances necessitating invocation of urgency under
Section 17(1) are not stated in the provision itself. Generally
speaking, the development of an area (for residential
purposes) or a planned development of city, takes many years
if not decades and, therefore, there is no reason why
summary enquiry as contemplated under Section 5-A may
not be held and objections of landowners/persons interested
may not be considered. In many cases, on general
assumption likely delay in completion of enquiry under
Section 5-A is set up as a reason for invocation of
extraordinary power in dispensing with the enquiry little
realising that an important and valuable right of the person
interested in the land is being taken away and with some
effort enquiry could always be completed expeditiously.”

(vii) That the judgment of this Court in Radhy Shyam holds the

field on the issue of invocation of urgency clause in

acquisition proceedings for planned development for

commercial, residential, industrial purposes and the decision

in Kamal Sharma has been rendered while glossing over the

law settled in Radhy Shyam.

(viii) That the right to be heard as provided under Section 5-A of

the Act is in the nature of a fundamental right and the same

cannot be dispensed with, so as to justify the lackadaisical

19 (2010) 11 SCC 242

22
approach of the State Government. It was also contended

that Section 5-A is not to be superseded ipso facto even if the

provisions of Sections 17(1) and 17(2) of the Act are being

invoked. Reliance in support of this contention was placed

upon the decision of this Court in the case of Dev Sharan v.

State of Uttar Pradesh and Others20, wherein it was held

that even in cases of ‘urgency’ or ‘unforeseen emergency’,

enquiry contemplated by Section 5-A cannot ipso facto be

dispensed with and even if the case is covered under sub-

sections (1) or (2) of Section 17, sub-Section (4) of Section 17

would not necessarily apply. The relevant extracts relied

upon are as below:-

“32. In a recent judgment of this Court in Essco Fabs,
(2009) 2 SCC 377, this Court, after considering previous
judgments as also the provisions of Section 17 of the Act
held: (SCC P. 839, para 41)

“41. Whereas sub-section (1) of Section 17 deals with
cases of ‘urgency’, sub-section (2) of the said section
covers cases of ‘sudden change in the channel of any
navigable river or other unforeseen emergency’. But
even in such cases i.e. cases of ‘urgency’ or
‘unforeseen emergency’, enquiry contemplated by
Section 5-A cannot ipso facto be dispensed with
which is clear from sub-section (4) of Section 17 of the
Act.”

This Court, therefore, held that once a case is covered
under sub-section (1) or (2) of Section 17, sub-section (4) of

20 (2011) 4 SCC 769

23
Section 17 would not necessarily apply: (SCC P. 395, para

54)

“54. In our opinion, therefore, the contention of the
learned counsel for the respondent authorities is not
well founded and cannot be upheld that once a case
is covered by sub-sections (1) or (2) of Section 17 of
the Act, sub-section (4) of Section 17 would
necessarily apply and there is no question of holding
inquiry or hearing objections under Section 5-A of the
Act. Acceptance of such contention or upholding of
this argument will make sub-section (4) of Section 17
totally otiose, redundant and nugatory.”

(ix) That the Division Bench of the Allahabad High Court

committed grave error in law while placing reliance upon the

judgment of Nand Kishore, for denying relief to the

landowners. That on a conjoint reading of paras 3 and 96 of

Nand Kishore, it would become evident that the land in

question therein admeasured 1604 Hectares, which was to be

acquired for the construction of the Yamuna Expressway

itself and it is in that background that the invocation of the

urgency clause was upheld, whereas the question as to the

invocation of urgency clause to acquire land for commercial,

residential or industrial purpose was not posed for

adjudication in Nand Kishore, although it held the

acquisition to be for public purpose. Paras 3 and 96 of Nand

Kishore read as follows: –

24

“3. The High Court, in the judgment dated 30-11-2009
passed in Nand Kishore Gupta v. State of U.P. [ CMWP No.
31314 of 2009 decided on 30-11-2009 (All)] , basically
pointed out that out of 12,282 landowners, 11,397 had
already received their compensation under the agreement
and the challenge related only to 21.03 ha out of 1604 ha of
land. The High Court also took the view that the scales of
justice must tilt towards the right to development of the
millions who will be benefited from the road and the
development of the area, as against the human rights of 35
petitioners therein, whose main complaint was that they
were not heard before the declaration under Section 6 of the
Act. The High Court also declined to give any direction to the
State Government to consider to exempt 21.03 ha of land
relating to the 35 petitioners therein on account of the fact
that the construction of the road had to be made in an
alignment and that alignment could not be changed.
Identical view was taken in another writ petition filed by one
Balbir Singh. The High Court also expressed its concern that
any direction to exempt the land covered by the construction
might seriously jeopardise the Project. The High Court also
reiterated that the acquisition of the land for interchange of
the road was the essential part of the Project, as also the
construction of bridges, culverts and interchanges, which
were essential for the fast-moving six-lane Expressway.

96. We are not impressed by the argument that the
encroachment issue was not a relevant factor. This argument
was based on the reported decision in Om Prakash v. State
of U.P. [(1998) 6 SCC 1] It must be said that the actual
scenario in that case was different. In that case, the Court
was considering the acquisition of area of about 500 acres
comprising of 437 plots, whereas, in the present case, the
area to be acquired for the Expressway alone was more than
1600 ha. This is apart from the 25 million sq m of land which
was liable to be acquired for the purposes of development of
five land parcels. There was interlinking between the
acquisition of land for the highway and the acquisition of
land for establishing the five townships.”

(x) That the judgment in Radhy Shyam carves out a clear

distinction by observing that the judgment in Nand Kishore

related to the lands proposed to be acquired for construction

of the expressway itself and not to the lands acquired for

25
commercial, residential, and industrial purposes, for which

the invocation of urgency clause was held to be untenable

and bad in law.

(xi) That neither the appellants have received any amount

towards compensation for acquisition of the lands nor have

they parted with the possession of the subject lands, and

thus, quashing of the land acquisition notification would not

have any adverse impact as no development has taken place

on the lands in question.

(xii) That the mere ploy of the grant of adequate compensation to

the landowners with an escalation of 64.7% could not justify

the grave illegalities committed by the authorities under the

garb of urgent acquisition because the same cannot obviate

or supersede the substantive fundamental right of the

landowners to file objections against the acquisition of the

privately owned lands.

SUBMISSIONS ON BEHALF OF YEIDA (RESPONDENT NO.3 IN
BATCH NO. 1):-

26. Shri Tushar Mehta, learned Solicitor General of India, Shri

Ranjit Kumar, Shri Gopal Jain, learned senior counsel appearing on

behalf of YEIDA implored the Court to uphold the judgment passed in

26
Kamal Sharma and to reverse the judgment passed in Shyoraj

Singh as being unsustainable in the eyes of law. They advanced the

following pertinent submissions seeking the above relief:-

(i) YEIDA is a statutory authority formed under Section 3 of the

U.P. Industrial Area Development Act, 1976, which has been

established to ensure planned development of the ‘industrial

development area’. In furtherance of this objective, YEIDA

prepared the Master Plan of 2021 and the Master Plan of

2031 with the intent to develop the eastern side of river

Yamuna by construction of a six-lane Expressway joining

Noida to Agra and also for integrated development of five

distinct regions along the said Expressway for residential,

industrial, institutional and recreational purposes. The

construction of the Jewar Airport is also a part and parcel of

the very same integrated project.

(ii) That a bare perusal of the Master Plan(Phase-1-2031) clearly

establishes that the land acquired for development across

Yamuna Expressway, is an integrated project. The land was

initially acquired for the Yamuna Expressway and thereafter,

for developing land parcels alongside the Yamuna

Expressway as residential townships, industrial areas,

27
amusement zones, etc. The development is strictly being

carried out in accordance with the Master Plan prepared by

YEIDA.

(iii) The Yamuna Expressway is a vital project of seminal

importance providing access to millions of commuters by

connecting the National Capital to Agra and nearby areas.

The Yamuna Expressway is poised to become even more

important with the upcoming Jewar Airport. A project of this

magnitude would require the involvement of the adjoining

areas which would lead to an overall development of the

State.

(iv) That the legality of the acquisition of the lands in question by

YEIDA for integrated and complementary planned

development is no longer res integra as the same has been

consistently upheld by this Court vide various judicial

pronouncements over time, the landmark case being Nand

Kishore.

(v) That the judgment in Nand Kishore squarely covers the

controversy at hand, wherein it was observed that the

planned development of 25 million square meter of land (2500

Hectares) being acquired for creation of the five zones for
28
industry, residence, amusement zones, etc. would be

complementary to the creation of the Expressway and is a

part of an integrated project and it was urged that similarly

in the present case, land has been acquired for the planned

development of the region.

(vi) That it is settled law that the decision on invocation of

urgency clause is an administrative decision requiring

subjective satisfaction of the State Government and scope of

judicial review in the matters of invocation of the urgency

clause under Sections 17(1) and 17(4) of the Act is limited to

the decision-making procedure and not to the decision itself.

The Court is required to examine the record just to arrive at

a satisfaction regarding existence of material to form an

opinion about invoking the urgency clause.

(vii) That the controversy involved in the present case is ad idem

to the facts of the case in Nand Kishore and the factors that

weighed with this Court in upholding the invocation of the

urgency clause in Nand Kishore, also exist in the present

case, and therefore, the invocation of the urgency clause in

the present case was fully justified. The Court’s attention was

drawn to the following factors: –

29

(a) Enormity of the project: The acquisition therein in

‘Nand Kishore’ case, involved 1604 Hectares of

land affecting 12,283 farmers. Similarly, in the

present case, the acquisition involves approximately

2,979 Hectares of land affecting 12,868

farmers/landowners. Thus, the present acquisition

is of greater magnitude than the one considered in

Nand Kishore.

(b) Likelihood of encroachments: The area for the

expressway alone exceeded 1600 Hectares, not

including the 25 million square meter parcel of land

required for developing the five additional zones. In

the present case, out of the 2,979 Hectares of land

acquired, only 456.74 Hectares of land is under

litigation. Therefore, there is an imminent likelihood

of encroachment on 2,522.26 Hectares of land

where landowners have already received

compensation and YEIDA has taken the possession.

(c) Number of Landowners to be heard: The total

number of landowners to be heard could delay the

project further. In the present case, 12,868

30
landowners would need to be heard, significantly

delaying the project. Only 140 landowners are

before this Court (inclusive of both batches of civil

appeals @ special leave petitions), claiming they

were not heard before the issuance of notification

under Section 6 of the Act, whereas, the others have

accepted the escalated compensation of 64.7%

directed to be paid by the High Court in Kamal

Sharma. Thus, hearing all the landowners was

bound to unnecessarily delay the developmental

works of great importance without causing any real

prejudice to the large number of landowners and

would also lead to escalation of cost of development.

(viii) That there was sufficient material before the State

Government to justify the invocation of urgency clause, and

there was no malice on part of the State Government in

invoking the same. Stress was laid upon the observations

made in Nand Kishore, wherein it was held that the

executive’s subjective satisfaction in dispensing with the

enquiry under Section 5-A can be subjected to judicial review

only on the grounds of insufficient material to justify

31
dispensing with the enquiry or malice in the impugned action,

neither of these elements exist in the present case.

(ix) That the Division Bench of Allahabad High Court in the case

of Shyoraj Singh clearly erred while relying upon the case of

Radhy Shyam to hold that the acquisition notifications are

bad in law and that the urgency clause was wrongly invoked.

That Radhy Shyam is not applicable to the lands acquired

for integrated planned development project at hand and is

clearly distinguishable on facts as the said judgment was

passed in the context of an acquisition for private purposes,

serving private interests and the chunk of land was acquired

in a standalone exercise for development of residential,

commercial and industrial projects, unlike the present case

where the acquisition is being done in the national interest

for a project meant to create public infrastructure of huge

magnitude. In this regard, it was submitted that Nand

Kishore was distinguished in Radhy Shyam in the following

terms: –

“76. In Nand Kishore Gupta v. State of U.P. [(2010) 10 SCC
282] the acquisition was upheld because the land was
urgently needed for construction of Yamuna Expressway and
by the time the matter was decided by this Court, huge
amount had been spent on the project.
As against this, the
exercise of power under Sections 17(1) and/or 17(4) for the

32
acquisition of land for residential, industrial and commercial
purposes, construction of sewage treatment plant and
district jails was held to be legally impermissible in Raja
Anand Brahma Shah v. State of U.P. [AIR 1967 SC 1081 :

(1967) 1 SCR 373] , Narayan Govind Gavate v. State of
Maharashtra [(1977) 1 SCC 133 : 1977 SCC (Cri) 49] , Om
Prakash v. State of U.P. [(1998) 6 SCC 1] , Union of India v.

Krishan Lal Arneja [(2004) 8 SCC 453] , Essco Fabs (P) Ltd.
v. State of Haryana [(2009) 2 SCC 377 : (2009) 1 SCC (Civ)
537] , Babu Ram v. State of Haryana [(2009) 10 SCC 115 :

(2009) 4 SCC (Civ) 69] and Anand Singh v. State of U.P.
[(2010) 11 SCC 242 : (2010) 4 SCC (Civ) 423].”

(x) That this Court in Natthi v. State of U.P. & Ors.21 and

Narendra Road Lines Pvt. Ltd. v. State of UP and

Others22, has dismissed the SLPs preferred against the

judgments passed by the Allahabad High Court in the self-

same acquisition while relying on the law laid down in Nand

Kishore, wherein it was held that the acquisition in question

in District Gautam Budh Nagar through YEIDA is for planned

development and the subject lands are contiguous to the land

parcels, which were acquired for the purpose of residential,

industrial, amusement, etc. along with Yamuna Expressway.

(xi) The attention of the Court was also drawn to the fact that the

SLP in Natthi v. State of U.P. & Ors.23 was dismissed on 9th

21 SLP(C) No. 014705-014710 of 2011
22 SLP(C) No. 17808 of 2010
23
(Supra, Note 22)

33
May, 2011, just a month after the decision of Radhy Shyam

which was delivered on 15th April, 2011.

(xii) That another Division Bench of the Allahabad High Court in

the case of Yogesh Kumar v. State of U.P.24 considered the

applicability of Radhy Shyam on invocation of urgency

clause for planned development through YEIDA, and vide

judgment dated 1st March, 2013, it was held that in view of

judgment in Natthi v. State of U.P. Thru. Secr. Industrial

Devp. & Ors.25, the decision in Radhy Shyam will have no

application on the present acquisition. The decision of

Allahabad High Court in Yogesh Kumar was also affirmed by

this Court while dismissing the SLP26 by a Bench presided

over by Hon’ble Mr. Justice G.S. Singhvi (who authored

Radhy Shyam) vide order dated 23rd September, 2013.

(xiii) That it was correctly held by the Division Bench of Allahabad

High Court in Kamal Sharma that the right of the tenure

holders to object against the acquisition provided under

Section 5-A of the Act cannot be said to be a fundamental

24 CMWP No.10782/2013, hereinafter referred to as ‘Yogesh Kumar’
25 Writ-C No. 20585 of 2010, hereinafter referred to as ‘Natthi’
26
Special Leave to Appeal (Civil) No. CC 16505/2013

34
right or a right akin to fundamental right protected by the

Constitution of India.

(xiv) That the Division Bench of the Allahabad High Court in

Kamal Sharma has meticulously reviewed the material on

record, and held that the same justified the invocation of the

urgency clause, recording its conclusions as follows:

(a) The lands of nine villages were acquired through

different notifications issued over a span of two years

between 26th February, 2009 to 22nd March, 2011.

(b) Majority of the declaration notifications were issued

in a gap of 3 to 4 months.

(c) It was specifically mentioned in the Certificate of the

Collector that the acquisition of different parcels of

land was being proposed as contiguous part of the

project. If an opportunity of hearing under Section 5-A

of the Act was granted, the same would have resulted

in legal proceedings and eventual non-availability of

contiguous land which would have hampered the

execution of the integrated project in a time bound

manner. The original record of the State provides

categorical statements to this effect.

35

(d) The aforesaid decision was taken on account of the

enormousness of the project in question and the area

of the land sought to be acquired.

He thus urged that the Division Bench of the Allahabad High

Court, therefore, rightly held that the invocation of the

urgency clause was not a mechanical exercise and was

undertaken pursuant to the subjective satisfaction of the

State Government being arrived at after due application of

mind to material available on record.

(xv) That the judgment in Shyoraj Singh does not lay down good

law and is liable to be set aside, since it failed to take note of

the earlier Division Bench decisions of the Allahabad High

Court in the cases of Natthi27, Narendra Road Lines Pvt.

Ltd. v. State of U.P. & Others28 and Yogesh Kumar29,

wherein the validity of self-same land acquisition for

integrated planned development by YEIDA was upheld.

Ignoring an earlier judicial precedent rendered by a Bench

presided by co-equal number of judges and taking a totally

27 Writ-C No. 20585 of 2010
28 Civil Misc. Writ Petition No. 29682 of 2009, hereinafter referred to as ‘Narendra Road

Lines’
29 supra

36
contrary view itself amounts to a fundamental error rendering

the subsequent view per incuriam as held in case of Karnail

Singh v. State of Haryana30.

(xvi) That there is no pre or post notification delay in the present

acquisition inasmuch as there are only three notifications,

where a period of nearly one year has been consumed in

issuing the Section 6 notification. For other seven

notifications, Section 6 notification was issued within two to

four months.

Learned Solicitor General concluded his submissions urging

that it is now futile to oppose the acquisition, particularly when the

same is unequivocally accepted by all except a few, inasmuch as the

majority of the landowners have accepted the enhanced

compensation without raising any further challenge to the

acquisition. Learned Solicitor General urged that the entire process

was wholly transparent and that there was pressing necessity for

acquisition of lands, considering the public purpose involved. He

thus implored the Court to accept the appeals filed by the YEIDA

and dismiss the appeals filed by the landowners.

30 (2009) 8 SCC 539

37

27. We have given our thoughtful consideration to the submissions

advanced at bar and have gone through the impugned judgments and

the material placed on record.

DISCUSSION AND FINDINGS: –

28. The issues which arises for our consideration in the present

batches of appeal are as follows: –

(i) Whether the present acquisition is a part of the

integrated development plan of ‘Yamuna Expressway”

undertaken by respondent No.3-YEIDA?

(ii) Whether the application of Sections 17(1) and 17(4) of

the Act was legal and justified in the instant case,

thereby justifying the decision of the State

Government to dispense with the enquiry under

Section 5-A of the Act?

(iii) Whether the view taken by the Division Bench of the

Allahabad High Court in Kamal Sharma validating

the questioned acquisition while relying upon Nand

Kishore lays down the correct proposition of law or

whether the Division Bench in the case of Shyoraj

Singh was justified in applying the principles laid

38
down in Radhy Shyam and quashing the acquisition

proceedings in question?

29. Before adverting to the above issues, we may take note of the

fact that the State Government had formulated a “Policy for Planned

Development along the Taj Expressway31” and the notification to this

effect was issued by the Infrastructure & Industrial Development

Commissioner, Government of Uttar Pradesh on 29th December, 2007.

The Policy dealt with the formation of Special Development Zone32 and

the development thereof. As per clause 3.2 of the said Policy, the land

use of SDZ is divided in the following terms: –

“3.2. Land use of SDZ (special development zone)

The permissible break-up of the total land area under SDZ for
different activities shall be as under:

%age of total area of SDZ
A. Core Activity Sports Not less than 35%
(including road & open spaces)

B. Other activities

(i) Commercial Not more than 20%

(ii) Institutional & amenities Not less than 5%

(iii)Roads, open and Not less than 25%
Circulation areas

(iv) Residential including Not less than 15%
Group Housing and
Plotted Development
Area ”

31
In short, ‘Policy’
32 In short ‘SDZ’.

39

30. A bare perusal of the aforesaid clause makes it clear that while

the development of roads and open spaces which was to constitute

35% of the land area was considered to be the core activity, the allied

activities such as commercial, institutional & amenities, roads, open

and circulation areas, residential including group housing and plotted

development areas were to constitute the remaining 65% of the land

under the SDZ. Hence, undeniably, the authorities were required to

develop the entire SDZ in an integrated manner. This aspect was

precisely taken note of by this Court in the case of Nand Kishore. The

relevant extracts from the judgment of Nand Kishore are reproduced

hereinbelow for the sake of ready reference: –

“57. The Expressway is a work of immense public importance.
The State gains advantages from the construction of an
expressway and so does the general public. Creation of a
corridor for fast-moving traffic resulting into curtailing the
travelling time, as also the transport of the goods, would be
some factors which speak in favour of the Project being for the
public purpose. Much was stated about the 25 million sq m of
land being acquired for the five parcels of land. In fact, in our
opinion, as has rightly been commented upon by the High
Court, the creation of the five zones for industry, residence,
amusement, etc. would be complementary to the creation of the
Expressway.

58. It cannot be forgotten that the creation of land parcels
would give impetus to the industrial development of the State
creating more jobs and helping the economy and thereby
helping the general public. There can be no doubt that the
implementation of the Project would result in coming into
existence of five developed parcels/centres in the State for the
use of the citizens. There shall, thus, be the planned
development of this otherwise industrially backward area. The
creation of these five parcels will certainly help the maximum
utilisation of the Expressway and the existence of an

40
Expressway for the fast-moving traffic would help the industrial
culture created in the five parcels. Thus, both will be
complimentary to each other and can be viewed as parts of an
integral scheme. Therefore, it cannot be said that it is not a
public purpose.”

31. Learned counsel for the landowners sought to draw a

distinction, urging that Nand Kishore only dealt with the issue as to

whether the acquisition was for public purpose and not with the issue

as to whether the invocation of the urgency clause for commercial,

residential, industrial purpose was justified. However, we are of the

view that this contention is bereft of merit as no such distinction is

permissible.

32. The core question which requires this Court’s consideration is

whether the Division Bench of the Allahabad High Court in the case of

Shyoraj Singh was justified in relying upon Radhy Shyam, so as to

quash the acquisition notification pertaining to the development of the

land adjoining the Yamuna Expressway. The relevant extracts from

Radhy Shyam which are reproduced supra would make it clear that

in the said case, this Court was considering a controversy relating to

the land acquisition for the purpose of planned industrial development

in District Gautam Budh Nagar through Greater Noida Industrial

Development Authority. Hence, the project did not contemplate a

planned and integrated development of an Expressway and the

41
adjoining areas. It was a standalone project pertaining to the

development in industrial Gautam Budh Nagar. However, it cannot

be gainsaid that Yamuna Expressway is a vital heartline providing

access to millions of commuters from National Capital Delhi to Agra.

The Expressway also connects the prestigious upcoming Jewar Airport

to adjoining areas. To assume that the Yamuna Expressway is a

simple highway without any scope for simultaneous development of

the adjoining lands for commercial, residential and other such

activities would be unconceivable. A project of such magnitude and

enormity would definitely require the involvement of the adjoining

areas which would lead to an overall development of the State of Uttar

Pradesh at large.

33. As observed above, the purpose behind the acquisition was

unquestionably the integrated development of lands abutting the

Yamuna Expressway. The acquisition of the lands for the Expressway

could not be isolated or separated from the acquisition of the abutting

lands. This was precisely held in the case of Nand Kishore.

34. It may be noted that the entire edifice of Shyoraj Singh is based

on Radhy Shyam, wherein a two-Judge Bench of this Court decided

the controversy arising from land acquisition pertaining to the planned

industrial development in the District Gautam Budh Nagar. Another

42
Division Bench of this Court considered the acquisition pertaining to

the Yamuna Expressway in the case of Natthi. Placing reliance on

Nand Kishore, the Division Bench of the same composition as in

Radhy Shyam vide order dated 9th May, 2011 rejected the special

leave petition(s) laying challenge to the invocation of the urgency

clause in the self-same acquisition proceedings.

35. Much stress was laid by the learned counsel for the landowners

on the issue that the Division Bench while deciding the impugned

judgment in the case of Kamal Sharma could not have taken a

different view from Shyoraj Singh and if at all, there was any doubt

on the correctness of the view taken in Shyoraj Singh, then, the

question of law was mandatorily required to be referred to a larger

Bench. We feel that the said argument is fallacious on the fact of it.

Much prior to Shyoraj Singh’s decision, three different Division

Benches of the Allahabad High Court by detailed judgments in the

cases of Natthi, Narendra Road Lines and Yogesh Kumar had

already affirmed the validity of invocation of the urgency clause in the

land acquisition notifications for the integrated development plan of

‘Yamuna Expressway’ by respondent No.3-YEIDA. It is trite to mention

that in Shyoraj Singh, the Division Bench failed to consider the

earlier Division Bench judgments in the cases of Natthi, Narendra

43
Road Lines and Yogesh Kumar. In this background, the view taken

by the Division Bench in the case of Shyoraj Singh is per incuriam,

rather than that in Kamal Sharma.

36. At the cost of repetition, it may be mentioned that the Division

Bench judgments rendered by the Allahabad High Court in the cases

of Natthi, Narendra Road Lines and Yogesh Kumar have been

affirmed by this Court with the dismissal of SLPs assailing the

impugned judgments in those cases.

CONCLUSION

37. In the wake of the above discussion, we have no hesitation in

holding that the Division Bench of the Allahabad High Court correctly

interpreted the legal position while deciding the batch of writ petitions

in the case of Kamal Sharma and the judgment in the case of

Shyoraj Singh does not lay down the correct proposition of law.

38. The issues framed above are answered in the following terms:

(i) Whether the present acquisition is part of the integrated

development plan of the ‘Yamuna Expressway’ undertaken by

respondent No. 3-YEIDA?

• Yes, the present acquisition forms part of the integrated

development plan for the Yamuna Expressway initiated by
44
YEIDA. As observed in the case of Nand Kishore, the

development of land parcels for industrial, residential, and

recreational purposes is complementary to the construction

of the Yamuna Expressway. The objective of the acquisition

is to integrate land development with the Yamuna

Expressway’s construction, thereby promoting overall

growth serving the public interest. Consequently, the

Expressway and the development of adjoining lands are

considered to be inseparable components of the overall

project.

(ii) Whether the application of Sections 17(1) and 17(4) of the Act

was legal and warranted in the instant case, thereby justifying the

Government’s decision to dispense with the inquiry under Section

5-A of the Act?

• Yes, the invocation of Sections 17(1) and 17(4) of the Land

Acquisition Act, 1894, was legal and justified in this case.

The urgency clause was applied in accordance with the

planned development of the Yamuna Expressway, as held in

Nand Kishore.

(iii) Whether the view taken by the Division Bench of the Allahabad

High Court in Kamal Sharma while relying on Nand Kishore lays

45
down the correct proposition of law, or whether the Division Bench

in Shyoraj Singh was justified in applying the principles laid

down in Radhy Shyam and quashing the acquisition proceedings

in question?

• The view expounded by the Division Bench in Kamal

Sharma, which relied upon Nand Kishore, sets forth the

correct proposition of law, and the judgment of the High

Court in Shyoraj Singh, which relied on Radhy Shyam, did

not present a correct legal interpretation. The judgment in

Shyoraj Singh is set aside as it does not lay down good law

and was passed while overlooking at the earlier precedents,

rendering it per incuriam.

39. The High Court while deciding Kamal Sharma extensively

considered the factual matrix and also examined the original records

of the State Government to arrive at the satisfaction that the

invocation of the urgency clause was absolutely justified with regard

to the acquisition in question. The High Court also exhaustively

considered the entire sequence of judicial pronouncements in respect

of the acquisition in question before arriving at the aforesaid

conclusion and acted in an equitable manner while affirming the

acquisition proceedings and directing the grant of additional

46
compensation. We appreciate the endeavour made by the High Court

to resolve the controversy objectively and equitably and grant our full

imprimatur to the judgment in Kamal Sharma.

40. Now, we are called upon to consider as to whether the escalated

compensation formula as arrived at by the Division Bench of the High

Court in the case of Kamal Sharma would subserve the ends of

justice or the landowners whose lands have been acquired would be

entitled to better compensation.

41. It is pertinent to note that the overwhelming majority of

landowners have refrained from seeking judicial intervention in this

matter, as manifested by the fact that only 140 out of 12,868

landowners(covered in both batches of civil appeals @ special leave

petitions) have opted to challenge the acquisition by approaching this

Court. This indicates that the majority of the landowners have

accepted the escalated compensation granted by the High Court in

Kamal Sharma.

42. This Court, in the cases of Savitri Devi v. State of Uttar

Pradesh and Others33, Sahara India Commercial Corporation

Limited and Others v. State of Uttar Pradesh34, and Noida

33 (2015) 7 SCC 21
34 (2017) 11 SCC 339

47
Industrial Development Authority v. Ravindra Kumar and

Others35, despite holding the invocation of the urgency clause under

Sections 17(1) and 17(4) of the Act to be illegal, nonetheless upheld

the acquisition proceedings and directed enhancement of

compensation so as to compensate the land owners. However, in the

present case, we have concluded that the action of the State in

invocation of the urgency clause is in consonance with the law.

43. The Division Bench of the Allahabad High Court, while

delivering its decision in Kamal Sharma has already granted

additional compensation of 64.7% to the landowners, to be offered as

‘No Litigation Bonus’ in consonance with the Government order dated

4th November, 2015, thus there is no scope to direct further

enhancement in compensation.

44. In light of the Government order dated 4th November, 2015 and

the precedents set in Savitri Devi v. State of Uttar Pradesh36 and

Yamuna Expressway Industrial Authority v. Shakuntla

Education and Welfare Society37, it is directed that 64.7%

enhancement in compensation shall apply in rem, ensuring uniform

benefits to all affected landowners under the present land acquisition.

35 (2022) 13 SCC 468
36 supra
37(2022) SCC OnLine SC 655

48

45. The question of non-issuance of the final award and its effect

on the acquisition is left open ensuring that any affected party would

retain the right to challenge or seek appropriate remedy on this

specific issue independently, in accordance with law.

46. As a result of the above discussion, the appeals filed by the

landowners i.e. Batch No. 1, are dismissed, and the appeals filed by

YEIDA i.e. Batch No. 2, are hereby allowed.

47. No order as to costs.

48. Pending application(s), if any, shall stand disposed of.

………………….……….J.
(B.R. GAVAI)

………………………….J.
(SANDEEP MEHTA)
New Delhi;

November 26, 2024.

49

Source link

Leave a Reply

Your email address will not be published. Required fields are marked *