Supreme Court of India
M/S Siddamsetty Infra Projects Pvt. Ltd vs Katta Sujatha Reddy on 8 November, 2024
Author: Dhananjaya Y Chandrachud
Bench: Dhananjaya Y Chandrachud
Reportable 2024 INSC 861 IN THE SUPREME COURT OF INDIA INHERENT JURISDICTION Review Petition (C) No. 1565 of 2022 in C.A. No. 5822 of 2022 M/s Siddamsetty Infra Projects Pvt. Ltd. …Petitioner Versus Katta Sujatha Reddy & Ors. …Respondents
And With
Review Petition (C) No. 1839 of 2024 in C.A. No. 5823 of 2022
Signature Not Verified
Digitally signed by
SANJAY KUMAR
Date: 2024.11.08
17:08:33 IST
Reason:
Page 1 of 38
JUDGMENT
Dr Dhananjaya Y Chandrachud, CJI
Table of Contents
A. Background ……………………………………………………………………………………….. 3
B. Judgments of the Trial Court, High Court and this Court ………………………….. 7
C. Submissions…………………………………………………………………………………….. 16
D. Grounds for exercising review jurisdiction ……………………………………………. 17
E. Limitation…………………………………………………………………………………………. 19
F. Specific performance ………………………………………………………………………… 25
G. Lis pendens ………………………………………………………………………………….. 32
H. Relief …………………………………………………………………………………………… 36
1. The petitioner has instituted proceedings under Article 137 of the
Constitution read with Order XLVII Rule 1 of the Supreme Court Rules 2013
seeking a review of the judgment of a three-Judge Bench of this Court dated 25
August 2022. By the judgment, this Court allowed the appeal against the judgment
of the High Court of Telangana dated 23 April 2021 by which the suit for specific
performance was partially decreed by directing the registration of the suit property
in favour of the petitioner proportionate to the extent of the consideration paid. The
issue for the consideration of this Court is whether the judgment of this Court dated
25 August 2022 suffers from an error apparent on the face of the record which
warrants the exercise of the review jurisdiction.
Page 2 of 38
PART A
A. Background
2. On 19 March 1994, Shri Debbad Narayana, Shri Vishweswara Rao
(represented by the tenth to twelfth respondents who are his legal representatives),
the third respondent, fourth respondent and fifth respondent (“original owners”)
entered into an agreement to sell a land admeasuring 127.29 acs to the first,
second, sixth, seventh and eight respondents (“vendors”). On the date of the
agreement, possession to the extent of 65.23 acs was delivered to the vendors.
Upon the payment of the balance sale consideration, the possession of the entire
property was delivered. A sale deed was not executed, though the full sale
consideration was paid. However, on 28 March 1994, an irrevocable power of
attorney was executed in favour of the vendors.
3. On 26 March 1997, the vendors executed an agreement to sell in favour of
the petitioner. This agreement will be referred to as the “first agreement to sell”. By
the agreement, the first and the second respondents offered to alienate the
scheduled property of 38.15 acs1 for a sale consideration of Rs 38,37,500. The
agreement notes that the petitioner paid a sum of Rs 5,30,000 in cash and Rs
6,00,000 in cheque as advance and earnest money. The relevant clauses of the
agreement to sell are extracted below:
“3. The purchaser shall pay a sum of Rs. 27,07,200/-
(Rupees Twenty Seven Lakhs seven thousand five1 “All that the agriculture land bearing Sy. Nos. 301 part, 302, 303, 304 part totally admeasuring Ac. 38-
15 guntas situated at Budwel village, the then Hyderabad West Tq., now Rajendernagar Mandar, R.R.
District, which is bounded by as under:-
East: Sy. No. 381, 380 and 326
West: Sy. No. 54 Village boundary of Irsalgandi
North: Sy. No. 381, 380 and 326
South: Sy. No. 300 and 306”Page 3 of 38
PART Ahundred only) towards the balance sale
consideration within three months from this date to
the parties of the second part herein and if the
purchaser does not honour to pay the balance sale
consideration of Rs. 27,07,500/- (Rupees Twenty
Seven Lakhs Seven Thousand and Five Hundred
Only) within a period of three months from the date
of this date, the advance amount paid will be
forfeited and this agreement of sale will be cancelled
if the vendors fail to furnish the non-encumbrance
certificate, income tax exemption certificate,
agricultural certificates to the purchaser within three
months.
[…]
6. The parties of the first part and the parties of the
second part herein undertake that they will execute
a registered sale deed or deeds or any other nature
of documents as desired by the purchaser in favour
of the purchaser or its nominee or nominees, after
receiving the balance sale consideration.
[…]
20. The parties of the first part and the second part
herein undertake to execute the documents either
registered or un-registered as desired by the
purchaser after receiving the balance sale
consideration to the extent to the schedule property.
[…]
21. The parties of the first part are not at all
concerned to the sale consideration agreed by the
parties of the second part herein with the purchaser
as already they received the agreed sale
consideration from the parties of the second part
herein as per the agreement dated 19th March 1994.
[…]
23. The parties of the second part herein undertake
on any pretext they will not make any claim for
enhancing the agreed sale consideration.”
(emphasis supplied)
Page 4 of 38
PART A
4. The first agreement to sell refers to the “original owners” as the “parties of
the first part”. The agreement refers to the “vendors” as the “parties to the second
part”. The petitioner is referred to as the “purchaser”. It must also be noted that the
recital to the first sale agreement states that the “parties of the first part and parties
1,3,5 and 6 of the parties of the second part” have been made a party to the
agreement only to ensure that there is no “cloud over the title”.
5. On 27 March 1997, an agreement to sell was executed by the first and
second respondents in favour of the petitioner to sell the scheduled property of
1.33 Acs2 for a consideration of Rs 1,82,500. This agreement will be referred to as
the second agreement to sell.
6. On 8 February 2000, the petitioner issued a legal notice (“first legal notice”)
to the first and second respondents calling upon them to receive the balance sale
consideration and execute the sale deed. On 14 April 2000, the second respondent
responded to the legal notice claiming to not have received the part-payment and
refusing to execute a sale deed in the petitioner’s favour. On 6 July 2002, the
petitioner issued another legal notice (“second legal notice”) to all the
respondents calling upon them to execute the sale deed upon the receipt of the
balance consideration. The first and second respondents replied to the legal notice
by a letter dated 22 July 2002 claiming that (a) the execution is barred by limitation;
(b) they were ready with the documents required under Clause 3 of the first
2 “All that the agricultural land bearing Sy. Nos. 304 part totally admeasuring Ac. 1.33 guntas situated
at Budwel village, the then Hyderabad West Tq. Now Rajendernagar mandal, R.R. District, which is
bounded by as under:-
East: Sy. No. 308
West: Sy. No. 3030
North: Sy. No. 326
South: Sy. No. 305”.
Page 5 of 38
PART A
agreement to sell but the petitioner was not willing to pay the balance
consideration; and (c) the first legal notice dated 8 February 2000 was ante-dated
to overcome limitation. The first legal notice was posted on 30 March 2000 by
registered post.
7. On 9 August 2002, the petitioner instituted a suit seeking a decree for
specific performance of the first and the second agreements to sell. The case of
the petitioner in the suit was:
a. Rs.34,70,000 towards the sale consideration for the first agreement and Rs
10,850 as advance for the second agreement was paid. Thus, of the
aggregate sale consideration of Rs. 40,20,000, Rs, 34,80,850 was paid and
only a balance of Rs 5,39,150 remained outstanding;
b. The possession of the suit land was delivered under the agreement; and
c. The petitioner has always been ready and willing to perform his part of the
agreements. Both the agreements required the respondents to furnish the
petitioner with necessary permissions and certificates, which they failed to do.
8. The petitioner prayed for a decree for specific performance upon the receipt
of the balance sale consideration of Rs 5,39,150. The petitioner sought alternative
reliefs of (a) delivery of possession of the suit land; or (b) a direction to refund the
consideration of Rs. 34,80,850 paid with interest of 36% per annum.
Page 6 of 38
PART B
B. Judgments of the Trial Court, High Court and this Court
9. By a judgment dated 12 December 2010, the Additional District Judge
dismissed the suit instituted by the petitioner. The Trial Court held that the petitioner
is not entitled to a decree or specific performance for the following reasons:
a. The respondents did not dispute the execution of the two agreements to sell.
There is also no dispute over the identity of the property. The petitioner is only
required to prove that he was always willing to perform his part of the
agreement;
b. It can be inferred from the evidence on record that the petitioner does not
have possession of the suit property and that a false plea that possession has
been delivered has been made because:
i. The alternative prayer of the petitioner in the suit was to put him in
possession of the property if, for any reason, the Court concludes that
the possession of the suit property was not delivered. The petitioner
would not have sought the alternative prayer if he were confident about
being in possession of the suit property;
ii.The petitioner did not plead when he was put in possession of the
property. PW-1 (the petitioner) was not able to respond to a question
during cross-examination on when he was put in possession of property;
iii.Though PW-2 (the owner of the land adjacent to the suit property)
deposed that the petitioner developed the suit property by fencing it and
constructing internal roads, these aspects did not find a mention in either
Page 7 of 38
PART Bthe deposition of PW-1 or the plaint. Further, the photographs of the suit
property also did not reflect these developments;
iv.The sale agreements also did not conclusively indicate that the petitioner
was put in possession of the suit property;
v.The first legal notice issued by the petitioner does not mention that
possession was delivered. The claim is only made in the second legal
notice; and
vi.The draft sale deed that the petitioner allegedly prepared and sent to the
respondents also does not mention that possession was delivered.
c. A cheque of Rs 5,40,000 issued by the petitioner towards
consideration was dishonoured. So, the petitioner paid Rs 29,30,000 towards
the sale consideration and not Rs 34,70,000, as claimed by him. The
petitioner made a false plea that he had paid Rs 34,70,000. The table
indicating the payments made by the petitioner is below:
26.3.1997 Rs. 5,40,000 (cheque dated
2.4.1997 which was
dishonoured)26.3.1997 Rs. 11,30,000 (Rs. 5,30,00 by
cash and Rs. 6,00,00 by cheque)26.3.1997 Rs, 13,00,000 by cheque
9.4.1997 Rs. 5,00,000 by cheque
Page 8 of 38
PART Bd. Clause 3 of the sale agreements states that the petitioner is required to pay
the balance consideration and the respondents must furnish certificates within
three months. The clause prescribes a consequence for non-payment, that
the agreement would be cancelled. However, the clause does not prescribe
any consequence if the respondents fail to furnish the necessary certificates
within three months. It cannot be concluded that time is of the essence only
because the agreement requires the petitioner to pay the balance
consideration within three months. The respondents had not obtained the
permissions and certifications required under Clause 3 and they did not inform
the petitioner about any steps taken to obtain them. The cross-examination of
DW-1 (first respondent) indicates this. Thus, time is not of essence in the
agreement;
e. The petitioner claims that he issued the first legal notice on 8 February 2000.
However, the postal cover and postal certificate indicate that it was registered
on 31 March 2000. Thus, the petitioner ante-dated the legal notice to
overcome limitation ;
f. The petitioner is not entitled to the discretionary relief of specific performance
if a false plea is made. In this case, the petitioner made three false pleas;
g. The petitioner has been unable to prove that he was willing to perform his part
of the contract within three years from the sale agreements and specifically,
within three months according to the agreement. If the petitioner was able to
perform his part, a notice would have been issued earlier or the balance would
have been deposited in the bank;
Page 9 of 38
PART B
h. The first part of Article 54 of the Schedule to the Limitation Act 1963 applies
to the facts of the case. The petitioner was required to pay the balance
consideration within three months from the date of the sale agreement. The
suit should have been filed on or before 26 June 2000 (three years from the
date fixed for the performance). However, the suit was filed on 9 August 2002,
nearly two years after the limitation expired. Thus, the suit was time barred;
and
i. The suit was barred by time for recovery of the advance amount in terms of
Article 47 of Schedule to the Limitation Act.
10. The petitioner preferred an appeal before the High Court against the
judgment of the Additional District Judge. By a judgment dated 23 April 2021, the
High Court partly allowed the appeal for the following reasons:
a. The Trial Court did not distinguish between the time fixed for payment of sale
consideration and the time for the performance of the contract. The first part
of Clause 3 of the agreements only fixes the time for the payment of sale
consideration. The performance of the contract hinges on the respondents
furnishing the documents. The agreements do not fix a time for the
performance of the contract. Thus, the second part of Article 54 of the
schedule to the Limitation Act applies. The limitation begins from the date of
refusal of performance. The suit was filed on 30 July 2002, which is within
three months of 14 April 2000 (the date when the respondents’ responded to
the first legal notice). Even if the first legal notice issued by the petitioner was
ante-dated, it would not affect the merits of the issue since limitation ought to
Page 10 of 38
PART Bbe calculated from the date of refusal. Further, the conclusion that the
petitioner did not file a suit immediately after the issuance of the second legal
notice is erroneous. The second legal notice was issued on 6 July 2002. The
suit was filed on 30 July 2002. The suit was numbered on 9 August 2002;
b. It cannot be concluded that possession was not delivered merely because
there was no mention of it in the sale agreements or the first legal notice. The
finding of the Trial Court on the aspect of possession and that the petitioner
made a false plea in this regard is erroneous. Even otherwise, the issue of
whether the petitioner has possession of the suit property is immaterial for the
relief of specific performance. The delivery of possession is inherent and
ancillary to the relief of specific performance under Section 55 of the Transfer
of Property Act 1882. (Relied on Babulal v. Hajarilal Kishorilal3);
c. The respondents received a substantial amount of the sale consideration of
Rs. 38,80,850 out of the total sale consideration of Rs. 40,20,000. The
respondents failed to provide the certificates. The first respondent admitted
that she received the amount in her cross-examination though she had denied
the same earlier in her written statement and chief examination. The sale
deed could not be executed because of the fault of the respondents. It cannot
be concluded that the petitioner did not approach the respondents for the
payment of the balance consideration merely because he could not depose
the particulars of when he approached them. Further, though the first and the
second respondents pleaded that they had obtained the necessary
3 1982 (1) SCC 525
Page 11 of 38
PART Bdocumentation as required by Clause 3 of the sale agreement in both the
written statement and evidence, this version was denied during the cross-
examination of DW-1 and DW-2 (husband of DW-1). The Trial Court
concluded that the respondents were not ready with the certifications. This
finding was not assailed by the counsel for the respondents;
d. The petitioner would not benefit from not performing the remainder of the
contract when he already paid 90 percent of the sale consideration. The
petitioner filed an Interlocutory Application to deposit the balance sale
consideration of Rs. 5,39,150 which was allowed. The petitioner has shown
bona fides by depositing the balance consideration. Thus, the oral evidence
of the petitioner (PW-1) that he approached the respondents to fulfil the
contract cannot be disbelieved. The petitioner has proven his readiness and
willingness to perform the contract;
e. The conclusion of the Trial Court that the petitioner made a false plea that he
paid Rs. 34,70,000 when he has only paid Rs, 29,30,000 is erroneous. DW-1
in her deposition admitted the payments of the petitioner and admitted that
the balance amount of Rs.5,39,150 was deposited in the Court in her cross-
examination. Upon the dishonour of the cheque dated 2 April 1997, the
plaintiff issued a Demand Draft of Rs. 5,00,000 on 9 April 1997;
f. Merely because the plaintiff did not institute a suit immediately after the reply
to the first legal notice in 2000, it cannot be inferred that he was not willing to
perform his part of the contract. The suit was filed within limitation (relied on
Page 12 of 38
PART B
R Lakshmi Kantham v. Devaraji (2019) 8 SCC 62; Mademsetty
Satyanarayana v. G. Yelloji Rao (AIR 1965 SC 1405));
g. Time is not of essence to the contract for the reasons recorded in the Trial
Court’s judgment; and
h. Section 10 of the Specific Relief Act 1963 was amended in 2018, by which
the relief of specific performance is no longer a discretionary power. Section
10 is a procedural provision. All procedural laws are retrospective. The
amended provision applies to all pending proceedings.
The High Court directed that since the petitioner had paid 90 percent of the sale
consideration, the suit for specific performance can be decreed in favour of the
petitioner to the extent proportionate to the consideration paid. The High Court
further directed that the amount of Rs, 5,39,150 deposited by the petitioner
pursuant to the Interlocutory Application must be refunded along with any interest
that is accrued.
11. Proceedings under Article 136 were instituted against the judgment of the
High Court. By a judgment dated 25 August 2022, a three-Judge Bench consisting
of Chief Justice NV Ramana, Justice Krishna Murari and Justice Hima Kohli
allowed the appeal. This Court referred to the judgment in Chand Rani v. Kamal
Rani4, in which it was held that there is no presumption that time is of essence in
a contract for a sale of immovable property and the Court may infer if it was of
essence based on (a) the express terms of the contract; (b) the nature of the
4 (1993) 1 SCC 519
Page 13 of 38
PART B
property; and (c) surrounding circumstances such as the object of the contract.
Relying on the judgment, this Court held that in the facts of the present case, time
is of essence for the following reasons:
a. Both the vendors’ and the purchaser’s obligations in Clause 3 of the sale
agreements were required to be completed within the stipulated time period
of three months. The consequences of (in)actions are different. There are no
consequences if the vendors do not produce the certificates and permissions.
However, the clause spells out a consequence of forfeiture of the advance
amount if the purchaser does not pay the balance consideration; and
b. According to Clause 21 of the sale agreements, the parties had entered into
an earlier agreement to sell dated 19 March 1994. This agreement did not
materialize and the agreed price was no longer applicable. Fresh agreements
were entered into “to provide a last opportunity to successfully enter into a
sale-purchase agreement.” This intention of the parties is also clear from
Clause 23 of the agreement.
12. This Court held that the suit was barred by limitation since the suit had to
be instituted within three years of the time fixed for completing the performance
(which was three months from the sale agreements). The three years ended in
June 2000 and the suit ought to have been instituted within that period to not be
barred by limitation.
Page 14 of 38
PART B
13. This Court also held the following on merits:
a. Section 10 of the Specific Relief Act is not procedural but substantive. Thus,
the 2018 amendment to the provision does not apply retrospectively to
pending proceedings;
b. Under the unamended provision, the Court’s power to grant specific
performance was discretionary. This discretion ought not to be exercised
arbitrarily5. The purchaser must be vigilant to enforce his right. Clause 3 of
the agreements was drafted to provide “one last opportunity for the purchaser
to make good their lapse which had happened on the earlier occasion.” The
time for performance of the contract, including payment lasted till June 1997;
c. The plaintiff was not ready and willing to perform the contract. The purchaser
did not voluntarily adhere to the time stipulated under the contract. However,
the vendors fulfilled their obligation to provide documentation. DW-1 averred
that all documents were available and that the petitioner entered into an
agreement only after he was satisfied with the title. Specific performance
cannot be enforced in favour of a party who has not proven that he was always
ready and willing to perform his part of the contract;
d. The Trial Court’s reasoning on the question of whether the petitioner has
possession of the suit property is correct; and
5 Saradamani kandappan v. S. Rajalakshmi (2011) 12 SCC 18
Page 15 of 38
PART Ce. Section 12 of the Specific Relief Act does not apply to situations where the
inability to perform the contract arises out of the party’s own conduct.6 In the
instant case, there was no inability on the part of the parties to perform the
contract. The petitioner was not willing to perform the contract after entering
into a “time-sensitive agreement”.
14. This Court directed the respondents/vendors to repay the sale consideration
received with an interest of 7.5 percent from the date on which the payment was
made till the time the entire amount is paid back. The payment was directed to be
made within six months.
15. The petitioner filed a review petition against the judgment of this Court.
C. Submissions
16. Mr Neeraj Kishan Kaul, senior counsel submitted that the judgment of this
Court suffers from the following apparent errors that warrants the exercise of the
review jurisdiction:
a. Clause 21 of the agreements to sell refers to the sale agreement executed by
the original owners in favour of the vendors in 1994. Though petitioner was
not a party to that agreement, this court has proceeded on the incorrect
premise that the 1994 agreement was between the parties;
b. The Trial Court, after analysing the evidence on record, concluded that the
vendors did not produce certificates and permissions as required by Clause
6 Jaswinder Kaur v. Gurmeet Singh, (2017) 12 SCC 810
Page 16 of 38
PART D3 of the sale agreements. This finding was not challenged before the High
Court. This Court wrongly records that the vendors produced the certificates
without referring to the direct evidence on record to the contrary; and
c. Clause 3 does not state that the agreement will be cancelled if the petitioner
does not pay the balance amount within three months.
17. Mr Rakesh Dwivedi and Mr. Mukul Rohatgi, senior counsel for the
respondents argued that this is not a fit case for the exercise of review jurisdiction.
It was submitted that the judgment of this Court was sound, independent of the
(mis)reference to the 1994 agreement. The learned counsel further submitted that
the suit property was alienated after the judgment of this Court and before the
review petition was registered. It was argued that the doctrine of lis pendens does
not apply when the petition was in the registry in a defective state.
D. Grounds for exercising review jurisdiction
18. Before proceeding with the analysis, we will refer to the grounds for
exercising review jurisdiction. Order XLVII of the Supreme Court Rules 2013 states
that an application for review must be filed on the grounds mentioned in Order
XLVII Rule 1 of the Code of Civil Procedure 1908 (“CPC”). Order XLVII Rule 1 of
CPC lays down the following grounds for review:
a. Discovery of new and important matter or evidence, which after the exercise
of due diligence was not within their knowledge or could not be produced by
them at the time the decree was passed;
b. Mistake or error apparent on the face of the record; and
Page 17 of 38
PART D
c. Any other sufficient reason.
19. This Court has laid down the following principles on the exercise of review
jurisdiction7:
a. Review proceedings are not by way of appeal and have to be strictly confined
to the scope and ambit of Order 47 Rule 1 CPC;
b. Error on the face of record must be an error which must strike one on a mere
perusal and must not on a long drawn process;
c. The power of review must not be exercised on the ground that the decision
was erroneous on merits;
d. The phrase “any other sufficient reason” means a reason that is analogous to
the grounds specified in Order 47 Rule 1 CPC; and
e. The mere possibility of two views on the subject cannot be a ground for
review.
20. Let us proceed to analyse if the judgment of this Court satisfies the grounds
for review. The issues which arose for the consideration of this Court were two-
fold: first, whether the suit instituted by the petitioner was barred by limitation; and
second, whether the suit for specific performance must be decreed. The finding
that time was of essence to the contract was central to the Court’s reasoning on
both the issues.
7See Murali Sundaram v. Jothibai Kannan, 2023 SCC OnLine SC 185; Karnail Singh v. State of
Haryana, 2021 SCC OnLine SC 961; Kamlesh Verma v. Mayawati, (2013) 8 SCC 320; Sanjay Kumar
Agarwal v. State Tax Officer, (2024) 2 SCC 362
Page 18 of 38
PART E
E. Limitation
21. The Schedule to the Limitation Act 1963 prescribes the period of limitation.
Article 54 of the Schedule prescribes the period of limitation for a suit for specific
performance of a contract:
Description of suit Period of limitation Time from which period
begins to run
54. For specific Three years The date fixed for the
performance of a contract performance, or, if no such
date is fixed, when the
plaintiff has notice that
performance is refused.
22. The provision has two parts. The first part deals with situations where the
contract fixes a date for performance. The period of limitation of three years runs
from the date fixed for completion of performance. The second part deals with
situations where the contract does not fix a date for the performance of the contract.
In such situations, the period of limitation runs from the date when the plaintiff has
notice that the defendant has refused performance.
23. The issue for consideration was whether the sale agreements fix a date for
the performance of the agreement. This Court referred to Clauses 3, 21, and 23 to
hold that the agreement fixes a date of three months for performance. This Court
interpreted Clause 3 as follows:
“31. At the outset, this Court has perused Clause 3
of the agreements, which is in two parts. The first
part provides for the purchaser’s obligations, while
the second part details the obligation of the vendors
to provide the requisite certificates. Although both
the obligations were required to be completed withinPage 19 of 38
PART Ethe stipulated period of three months, there is a
substantive difference between these two sets of
obligations. The obligation upon the vendors
concerned was production of certain certificates,
such as income tax exemption certificate and
agriculture certificate. No consequences were
spelt out for non-performance of such
obligations. Whereas the obligation on the
purchaser, was to make the complete payment of the
sale consideration within three months. The clause
further mandates forfeiture of the advance
amount if the payment obligation is not met
within the time period stipulated therein.”(emphasis supplied)
24. This Court observed that Clause 3 casts two obligations: one on the
petitioner/purchaser and the other on the respondents/vendors. To this extent, we
find no error. However, the conclusion that the Clause only provides consequences
for the non-payment of the balance consideration by the purchaser and not for the
non-production of certificates by the vendors is an error apparent on the face of
the record. The judgment correctly notes that Clause 3 prescribes that the advance
amount paid will be forfeited if the balance is not paid by the petitioner in three
months. However, this Court missed that the Clause also provides a consequence
for not producing the documents within three months, which is the cancellation of
the sale agreements. This Court seems to have missed the phrase “and this
agreement of sale will be cancelled..”. If this Court had read “and this agreement
of sale will be cancelled” as a consequence of the non-fulfilment of the obligation
cast on the purchaser, it could still be argued that it was a probable (though in our
opinion, erroneous) view and not an error apparent on the face of the record.
However, the judgment completely disregards the phrase “and this agreement of
sale will be cancelled” in Clause 3. In paragraph 32 of the judgement, this Court
Page 20 of 38
PART E
further notes that non-payment of the balance consideration would lead to a severe
consequence of “forfeiture”:
“33. Coming to the aforesaid indicators, the
language of the agreements makes it clear that
severe consequences of forfeiture would ensue if the
payment is not made within three months of the date
of the agreements.”
25. Clause 3 has two parts. The first part casts an obligation on the
purchaser/petitioner and prescribes consequences for it, that is, the forfeiture of
the advance paid. The word “and” disjuncts this part from the second part which
casts an obligation on the vendors. The second part prescribes the consequence
if the vendors do not furnish the documents.
26. This Court further noted that the “language of the agreements” ensures
severe consequences of forfeiture if the balance consideration is not paid within
three months. This Court further referred to Clauses 21 and 23 to substantiate this
interpretation:
“32. […] It may be noted that as per Clause 21, the
parties had entered into an earlier agreement to sell
dated 10.03.1994, which did not materialize and
accordingly the agreed price therein was no longer
applicable. It is in this context that the fresh
agreements were entered into between the parties,
so as to provide a last opportunity for them to
successfully enter into a sale-purchase agreement.
The aforesaid intention of the parties is also made
clear through Clause 23 of the agreement to sell,
which reads as under:
[…]
33. The aforesaid clause clearly freezes any
enhancement of the agreed sale consideration,
which cannot be independent of a fixed time period.
A contrary interpretation would render the contract
commercially unreasonable and unworkable. The
Page 21 of 38
PART E
moratorium on the enhancement of rates prescribed
under Clause 23 should be interpreted to be
predicated on a fixed time and be executable within
a reasonable period. The same should not be utilized
to render the commercial wisdom between the
parties otiose, which is inherent in drafting such
clauses.”
27. To recall, Clause 21 stipulates that the parties of the “first part” are not
concerned with the sale consideration as they have already received the agreed
sale consideration from the parties of the “second part” by an agreement dated 19
March 1994. This Court has interpreted the reference to the agreement dated 19
March 1994 as the agreement between the petitioner and the respondents which
did not materialise. This is an obvious and apparent error on the face of the record.
The agreements refer to the original owners from whom the vendors purchased
the suit property as parties of the “first part”. The vendors are referred to as parties
to the “second part”. The agreement dated 19 March 1994 is the agreement to sell
that was executed by the original owners in favour of the vendors. The petitioner
was not a party to this agreement. The 1997 agreements in favour of the petitioner
were executed by the original owners in addition to the vendors because though
the vendors were put in possession of the suit property after the sale agreement,
a sale deed was not executed. Instead, an irrevocable power of attorney was
executed in favour of the vendors. Though only the first and the second
respondents offered to alienate the suit property to the petitioner, the agreement is
executed by the original owners and vendors other than the first and the second
respondent as well to prevent any litigation in the future. The relevant clauses of
the recital to the agreement dated 26 March 1997 are extracted below:
Page 22 of 38
PART E
“4. Whereas parties of the Second part herein
have entered into an agreement of sale with the
parties of the first part herein dated 19 March 1994.
5. Whereas the parties of the second part herein
have purchased from the parties of the first part to
an extent of Articles 127-129 guntas only in lad
bearing Sy.No. 301 part 302, 303, 304, 305, 306,
307, 308 and 309 for a valuable consideration and
on the date of the agreement possession was
delivered to an extent of Articles 65-23 guntas and it
was specifically agreed that an irrevocable general
power of attorney will be executed through a
registered document in the names nominated by the
parties of the second part herein, as such parties of
the first part herein have executed and irrevocable
power of attorney on 28 March 1994 which was
registered on 30th day of April 1994.
6. Whereas parties of the second part herein
have paid the full sale consideration to the parties of
the first part and the parties of the first part herein
have also delivered the possession of the remaining
extent of Ac. 50-00 gts and to that effect admitting
and acknowledging the same the parties of the first
part herein have passed receipts and also got
executed another regd. Irrevocable power of
attorney in favour of the parties of the second part
herein, as such the parties of the second part herein
become the possessors of the total extent of Ac. 115-
29 guntas.
7. Whereas parties 2 and 4 of the second part
herein have offered to alienate and extent of Ac. 38-
15 guntas in land bearing Sy. No. 301 part, 302,303
and 304 part out of the total extent of Ac. 127-29
guntas @ Rs 1, 00, 000/- per acre which comes to a
total sum of Rs. 38, 37, 500/- (Rupees Thirty Eight
Lakhs Thirty Seven Thousand give hundred only)
and infact, parties of the first part as well parties
1,3,5 and 6 of the parties of the second part herein
have no concern either for the agreed sale
consideration or for the extent under alienation but
they have been made as parties to this agreement
not to have a cloud over the title and also to get
convey the title in a better way along with the rights
for not to give any scope for the litigation in future on
any pretext and the parties 1,3,5, and 6 of the parties
of the second part herein shall be at liberty either to
enjoy or to alienate to their choice of the extent of
their share of land situated at Budwel village,
Rajendernagar mandal, Ranga Reddy District.”Page 23 of 38
PART E
28. Thus, the conclusion that Clause 21 indicates that an agreement was
executed in 1994 with the petitioner which did not materialise is an error apparent
on the face of the record. The argument of the respondent that the Court concluded
that time is of essence independent of the interpretation of Clause 21, in our
opinion, does not hold merit. This Court placed considerable weightage on Clause
21. This Court referred to Clauses 3, 21 and 23 to interpret if time was of essence
in the backdrop of the principles laid down in Chand Rani (supra). To recall, in
Chand Rani (supra), this Court held there is no presumption that time is of essence
in a contract for a sale of immovable property and the Court may infer if it was of
essence based on (a) express terms of the contract; (b) nature of the property; and
(c) surrounding circumstances such as the object of the contract. Clause 21 was
interpreted to cast light upon the surrounding circumstances/the object of the
contract and was crucial to its decision.
29. Having concluded that the interpretation of Clauses 3 and 21 of the Sale
Agreements was erroneous, there is nothing in Clause 23 alone that could be
interpreted to prescribe a time for the performance of the contract. Further, the
judgment also does not take note of Clause 6 of the agreements to sell which
provides that a sale deed will be executed after receiving the balance sale
consideration. This clause does not prescribe any time period within which the sale
deed must be executed. Another question is whether Clause 3 can be
independently interpreted to prescribe a date for the performance of contract. The
consequence of the non-payment of the balance consideration in terms of Clause
3 is the forfeiture of the advance amount paid by the purchaser and not all the
Page 24 of 38
PART F
consideration paid by the end of three months. The consequence is not that the
sale deed shall not be executed.
30. For the above reasons, Clauses 3, 21 and 23 cannot be interpreted to mean
that a time is fixed for the execution of the sale agreements. Thus, the limitation is
governed by the second part of Article 54. The limitation of three years prescribed
by the second part of Article 54 runs from the date when the plaintiff has notice that
performance has been refused. The petitioner/plaintiff had notice that performance
is refused only by the reply dated 14 April 2000 to the first legal notice of the
petitioner. A portion of the reply is extracted below:
“That our client along with Smt. Kotta Sujatha Reddy
have not received the alleged amount of Rs.
34,80,850/- as part sale consideration of the alleged
agreement.
That our client has no any liability to execute the sale
deed in your clients favour on any account under the
alleged agreement of sale deed 26.3.1997 or
27.3.1997. As such the execution of any sale deed
in your client’s favour does not arise.”
31. Thus, the limitation prescribed by Article 54 sets in from the date when the
petitioner received the above reply refusing performance. Irrespective of whether
the suit was instituted on 9 August 2002 (as concluded by the Trial Court) or 30
July 2002 (as concluded by the High Court), it was within limitation.
F. Specific performance
32. The next issue is whether the petitioner is entitled to a decree for specific
performance. This Court held that the 2008 amendment to Section 10 of the
Specific Relief Act does not apply retrospectively and decided the matter based on
Page 25 of 38
PART F
Section 10 before the amendment. Section 10, before the amendment, conferred
courts with the discretion to provide a decree for specific performance. In exercise
of review jurisdiction, we must not disturb a finding unless there is an error apparent
on the face of record. Even assuming that the grant of relief of specific
performance continued to be discretionary to a suit instituted before the date of the
amendment, we are of the opinion that this Court committed a grave error in its
analysis of whether the Court ought to use its discretionary power in this matter.
Section 10 of the Specific Relief Act before the 2018 amendment read as follows:
“10. Cases in which specific performance of contract
enforceable.- Except as otherwise provided in this
Chapter, the specific performance of any contract
may, in the discretion of the court, be enforced-
(a) when there exists no standard for ascertaining
actual damage caused by the non-performance of
the act agreed to be done; or
(b) when the act agreed to be done is such that
compensation in money for its non-performance
would not afford adequate relief.
Explanation.- Unless and until the contrary is proved,
the court shall presume
(i) that the breach of a contract to transfer immovable
property cannot be adequately relieved by
compensation in money; and
(ii) that the breach of a contract to transfer movable
property can be so relieved except in the following
cases:
(a) where the property is not an ordinary article of
commerce, or is of special value of interest to the
plaintiff, or consists of goods which are not easily
obtainable in the market;
(b) where the property is held by the defendant as
the agent or trustee of the plaintiff.”Page 26 of 38
PART F
33. This Court referred to the judgment in Saradamani Kandappan v.
Rajalakshmi8, which laid down the factors that the Courts must consider while
deciding whether to exercise the discretion of decreeing specific performance of a
contract:
“43. Till the issue is considered in an appropriate
case, we can only reiterate what has been
suggested in K.S. Vidyanadam [(1997) 3 SCC 1] :
(i) The courts, while exercising discretion in suits for
specific performance, should bear in mind that when
the parties prescribe a time/period, for taking certain
steps or for completion of the transaction, that must
have some significance and therefore
time/period prescribed cannot be ignored.
(ii) The courts will apply greater scrutiny and
strictness when considering whether the purchaser
was “ready and willing” to perform his part of the
contract.
(iii) Every suit for specific performance need not be
decreed merely because it is filed within the period
of limitation by ignoring the time-limits stipulated in
the agreement. The courts will also “frown” upon
suits which are not filed immediately after the
breach/refusal. The fact that limitation is three years
does not mean that a purchaser can wait for 1 or 2
years to file a suit and obtain specific performance.
The three-year period is intended to assist the
purchasers in special cases, as for example, where
the major part of the consideration has been paid to
the vendor and possession has been delivered in
part-performance, where equity shifts in favour of the
purchaser.”
(emphasis supplied)
34. Section 16(c) of the Specific Relief Act states that specific performance of
a contract cannot be enforced in favour of the person who fails to prove that he is
ready and willing to perform the essential terms of the contract which are to be
performed by him, other than the terms which are prevented or waived by the
8 (2011) 12 SCC 18
Page 27 of 38
PART F
defendant. The explanation to clause (c) states that it is not essential for the plaintiff
to tender money to the defendant where the contract involves the payment of
money, unless directed by court. Section 16(c) reads as follows:
“16. Personal bars to relief.- Specific performance of
a contract cannot be enforced in favour of a person-
[…]
(c) who fails to prove that he has performed or has
always been ready and willing to perform the
essential terms of the contract which are to be
performed by him, other than terms the performance
of which has been prevented or waived by the
defendant.
Explanation.- For the purposes of clause (c),-
(i) where a contract involved the payment of money,
it is not essential for the plaintiff to actually tender to
the defendant or to deposit in court any money
except when so directed by the court;”
35. This Court concluded that the petitioner was not ready and willing to perform
his part (as required by Section 16(c)) because the balance sale consideration was
not paid within three months as required by Clause 3:
“58. From the aforesaid, it is clear that the purchaser
ought to have been vigilant in the case at hand to enforce
his right and could not have been lackadaisical in his
approach. From the facts, it is clear that the purchaser
had entered into an agreement way back on
26/27/.03.1997, which had a clause mandating
completion of the contract by payment of the remaining
consideration within three months. The aforesaid clause
was drafted, as alluded to earlier, for providing one
last opportunity for the purchaser to make good their
lapse which had happened on the earlier occasion. In
this context, the time for performance of the contract
including the payment lasted till the month of June 1997.”(emphasis supplied)
Page 28 of 38
PART F
36. It is clear from the above extract that this Court held that the petitioner was
not ready and willing to perform the contract in which time was of essence. The
conclusion that time was of essence was derived based on an interpretation of
Clause 3 read with Clause 21. The reasoning based on which this Court held that
the petitioner was not ready and willing to perform the contract falls in view of the
conclusion that the interpretation of Clause 21 and Clause 3 by this Court is
erroneous because of the factual misconception and omission, respectively.
37. In paragraph 67 of the judgment, this Court also held that the first and the
second respondents were ready and willing to perform their obligation of providing
the documents:
“67. On the aspect of the vendor’s obligation to
provide requisite and necessary documents, DW1
(Smt. Katta Sujatha Reddy), has averred that all the
documents were available. It is only after the
purchaser was satisfied about the sound title that he
entered into the agreement to sell.”
38. There is an error apparent on the face of the record in the factual finding
recorded above. The Trial Court recorded that the respondents did not produce the
records. The Trial Court expressly noted that DW-1 initially stated that they
produced the certificates. However, during the cross-examination, DWs 1-3
deposed that they had not obtained and produced these documents. The
observations of the Trial Court in this regard are extracted below:
“70. […] It is in the written statement and as well as
in the reply lawyers notice as if the defendants got
secured these documents. But, the fact remains and
undisputed is, the defendant have not obtained such
certificates and they have not furnished them to the
plaintiff and they have not even informed to the
plaintiff what are the steps taken by them in obtainingPage 29 of 38
PART Fthese documents and the proceedings taken by
them in that context. But it is in the pleading and
in the evidence of DW-1 at the earliest part of
time that they have obtained these documents.
But from the later part of evidence of DW-1 by
filing further chief examination affidavit and from
the cross-examination of DW-1 to 3 it is made out
the defendants have not obtained and they are
not informed to the plaintiff and that they have
secured such certificates.”(emphasis supplied)
39. In the appeal, the High Court categorically noted that the above finding of
the trial court was not challenged:
“40. It is also pertinent to note about categorical
admission by the defendants 6 & 8 that they have
not obtained certificates and documents for
completing the sale transaction. But the defendants
6 & 8 pleaded that they have obtained necessary
documents both in the written statements and also
in the evidence. In the cross-examination that
version of D.W.1 is dismantled and trial Court
also comes to the conclusion that the
defendants without obtaining documents and
certificates simply pleaded that they are ready
with the certificates. However, that finding is not
attacked in this appeal, which goes to show that
the defendants are at fault in not obtaining
certificates for fulfilling their part of the contract,
though, the plaintiff paid 90% of the sale
consideration requesting the defendants 6 & 8 to
receive balance sale consideration.”(emphasis supplied)
40. The judgment of this Court in paragraph 67 only refers to the deposition of
DW-1 without referring to her cross-examination or the fact that the respondents
did not challenge the finding of the Trial Court on this aspect. This is another error
apparent on the face of the record.
Page 30 of 38
PART F
41. Having held that the basis of the reasoning of this Court on whether the
petitioner was willing to perform the contract has an error apparent on the face of
the record, we are required to decide the issue of whether the petitioner was ready
and willing to perform the contract. We are of the considered opinion that the
petitioner was ready and willing to perform the contract in terms of Section 16(c) of
the Specific Relief Act. The first agreement to sell noted that the purchaser paid a
sum of Rs.11,30,00 as earnest money. Subsequently, the petitioner paid Rs.
13,00,000 on the same day by cheque and paid another Rs. 5,00,000 by Demand
Draft on 9 April 1997. If the petitioner was unwilling to perform the contract, he
would not have paid nearly 75 percent of the sale consideration. Thus, the
petitioner with the payment of the additional sum above the earnest money, has
proved his readiness and willingness to perform the contract. Further, this aspect
must be analysed in the backdrop of the explanation to Section 16(c) of the Specific
Relief Act which states that if the contract involves the payment of money, it is not
necessary that the plaintiff actually tenders the money. It cannot be concluded that
the petitioner was not ready or willing to perform his part of the contract merely
because the balance sale consideration was due to be paid.
42. Section 10, before the amendment in 2018 stated that the Court can
exercise its discretion to award specific performance of contract where (a) there
exists no standard for ascertaining the actual damage caused by the non-
performance of the act agreed to be done; or (b) when the act agreed to be done
is such that compensation in money for its non-performance would not afford
adequate relief. The Explanation provided that unless there is anything to the
contrary, the court shall presume that the compensation in money is not an
Page 31 of 38
PART G
adequate relief for the breach of a contract to transfer immovable property. There
is nothing in the agreements to sell to rebut this statutory presumption. On an
application of the facts to the principles in Sections 10 and 16 of the Specific Relief
Act, we are of the considered opinion that this is a fit case for this Court to exercise
its discretion to direct specific performance.
G. Lis pendens
43. The respondents submitted that a sale of the suit property was executed
after the judgment of this Court (25 August 2022) and before the review petition
was registered (13 December 2022). It was submitted that the third party is in
possession and enjoyment of the suit property.
44. On 23 September 2022, the petitioner filed a review petition against the
judgment of this Court dated 25 August 2022. The review was filed within thirty
days, the prescribed period of limitation in terms of Order XLVII Rule 2 of the
Supreme Court Rules 2013. On 14 October 2022, the Registry sent a letter to the
petitioner asking him to cure defects. On 11 November 2022, the petitioner cured
the defects. On 13 December 2022, the review petition was registered. On 27
January 2023, the counsel for the petitioner sought six weeks to bring some
documents on record. On 1 March 2023, the matter was listed before a three-Judge
Bench of Justice Krishna Murari, Justice Hima Kohli and one of us (Justice DY
Chandrachud). The matter was not taken up. By an order dated 31 August 2023,
Justice D Y Chandrachud allowed the application for listing the review petition in
open court and issued notice, returnable in six weeks. Justice Hima Kohli did not
agree and was of the view that the review petition be dismissed. Justice Narasimha
Page 32 of 38
PART G
who was the third member of the Bench recused from the matter for personal
reasons. Subsequently, Justice Manoj Misra was nominated as the third member
of the Bench. By an order dated 26 September 2024, notice was issued in the
review petition.
45. Section 52 of the Transfer of Property Act 1882 states that during the
pendency in any court of any suit in which any right to immovable property is
directly and specifically in question, the property cannot be transferred or otherwise
dealt with by any party to the suit or proceedings. The explanation to the provision
states that for the purposes of the Section, the pendency of a suit or proceedings
shall be deemed to commence from the date of the presentation of the plaint or
institution of the proceeding in a Court, and shall continue until the suit or
proceeding is disposed by a “final decree or order” and complete satisfaction of the
order is obtained, unless it has become unobtainable by reason of the expiry of
any period of limitation. Section 52 of the Transfer of Property Act reads as follows:
“52. During the pendency in any Court having
authority within the limits of India excluding the State
of Jammu and Kashmir or established beyond such
limits by the Central Government of any suit or
proceeding which is not collusive and in which
any right to immovable property is directly and
specifically in question, the property cannot be
transferred or otherwise dealt with by any party to
the suit or proceeding so as to affect the rights of
any other party thereto under any decree or order
which may be made therein, except under the
authority of the Court and on such terms as it
may impose.
Explanation.– For the purposes of this section, the
pendency of a suit or proceeding shall be deemed to
commence from the date of the presentation of the
plaint or the institution of the proceeding in a Court
of competent jurisdiction, and to continue until thePage 33 of 38
PART Gsuit or proceeding has been disposed of by a
final decree or order and complete satisfaction
or discharge of such decree or order has been
obtained, or has become unobtainable by reason of
the expiration of any period of limitation prescribed
for the execution thereof by any law for the time
being in force.”(emphasis supplied)
46. The following conditions ought to be fulfilled for the doctrine of lis pendens
to apply:
a. There must be a pending suit or proceeding; b. The suit or proceeding must be pending in a competent court; c. The suit or proceeding must not be collusive9; d. The right to immovable property must be directly and specifically in question in the suit or proceeding; e. The property must be transferred by a party to the litigation; and f. The alienation must affect the rights of any other party to the dispute.10
47. In short, the doctrine of lis pendens that Section 52 of the Transfer of
Property Act encapsulates, bars the transfer of a suit property during the pendency
of litigation. The only exception to the principle is when it is transferred under the
authority of the court and on terms imposed by it. Where one of the parties to the
suit transfers the suit property (or a part of it) to a third-party, the latter is bound by
9 A collusive suit is not a real suit but a sham where the claim that is put forward if fictitious. See Nagubai
Ammal v. B Shama Rao, 1956 SCC 321
10 See Amit Kumar Shaw v. Farida Khatoon, (2005) 11 SCC 403
Page 34 of 38
PART G
the result of the proceedings even if he did not have notice of the suit or proceeding.
The principle on which this doctrine rests was explained by Lord Turner in Bellamy
v. Sabine11 as follows:
“It is, as I think, a doctrine common to the courts both
of Law and Equity and rests, as I apprehend, upon
this foundation that it would plainly be impossible
that any action or suit could be brought to a
successful termination, if alienations pendente lite
were permitted to prevail. The plaintiff would be
liable in every case to be defeated by the defendants
alienating before the judgment or decree, and would
be driven to commence his proceedings de novo,
subject again to be defeated by the same course of
proceedings.”
48. Justice M H Beg in Jayaram Mudaliar v. Ayyaswami12 set out the content
of the doctrine of lis pendens as follows:
“14. The background of the provision set out above
was indicated by one of us (Beg, J.,) in Jayaram
Mudaliar v. Ayyaswami [(1972) 2 SCC 200, 217 :
AIR 1973 SC 569] . There, the following definition of
the lis pendens from Corpus Juris Secundum (Vol.
LIV, p. 570) was cited:
“Lis pendens literally means a pending suit, and the
doctrine of lis pendens has been defined as the
jurisdiction, power, or control which a court acquires
over property involved in a suit pending the
continuance of the action, and until final judgment
therein.”
It was observed there:
“Expositions of the doctrine indicate that the need for
it arises from the very nature of the jurisdiction of
Courts and their control over the subject-matter of
litigation so that parties litigating before it may not
remove any part of the subject-matter outside the
power of the Court to deal with it and thus make the
proceedings infructuous.”
11 (1857) 1 De G&J 566
12 AIR 1973 SC 569
Page 35 of 38
PART H
49. The purpose of lis pendens is to ensure that the process of the court is not
subverted and rendered infructuous. In the absence of the doctrine of lis pendens,
a defendant could defeat the purpose of the suit by alienating the suit property.
This purpose of the provision is clearly elucidated in the explanation clause to
Section 52 which defines “pendency”. Amending Act 20 of 1929 substituted the
word “pendency” in place of “active prosecution”. The Amending Act also included
the Explanation defining the expression “pendency of suit or proceeding”.
“Pendency” is defined to commence from the “date of institution” until the
“disposal”. The argument of the respondents that the doctrine of lis pendens does
not apply because the petition for review was lying in the registry in a defective
state cannot be accepted. The review proceedings were “instituted” within the
period of limitation of thirty days. The doctrine of lis pendens kicks in at the stage
of “institution” and not at the stage when notice is issued by this Court. Thus,
Section 52 of the Transfer of Property Act would apply to the third-party purchaser
once the sale was executed after the review petition was instituted before this
Court. Any transfer that is made during the pendency is subject to the final result
of the litigation.13
H. Relief
50. The High Court relied on Section 12 of the Specific Relief Act to decree
specific performance only to the extent of the consideration paid by the petitioner.
The directions of the High Court are extracted below:
“89. […], this court is of the considered opinion that
by exercising power under Section 12, in order to13 See GT Girish v. Y Subba Raju, 2022 8 SCR 991
Page 36 of 38
PART Hmeet the ends of justice, suit can be decreed for
specific performance only to the extent of 90% of the
amount paid by the plaintiff to the defendants 6 & 8
towards sale consideration.
90. In the result, Appeal Suit is allowed in part
directing the defendants 6 & 8 to register the suit
schedule property in favour of the plaintiff
proportionate to the extent of amount paid by the
plaintiff i.e., 90% of the total sale consideration[…].
91. It is needless to state that the Suit Schedule Land
is required to be divided by metes and bounds in the
execution proceedings by the Execution Court, as
indicating above i.e., 90% and 10% with the
assistance of an advocate commissioner and the
90% of the part of the Suit Schedule Land, so
determined, shall be registered in favour of the
Appellant in accordance with the law.”
51. On appeal, this Court held that it was not a fit case to exercise discretion to
grant relief in terms of Section 12 because the purchaser breached an essential
condition of the agreements to sell and the suit was filed beyond limitation:
“77. […] In this case, the petitioner breached the
essential condition of the contract, which altogether
disentitles him to claim specific performance. There
is no doubt that the claim of purchaser is hit by delay
and laches on their part as they did not take
appropriate measures within the stipulated time and
filing of the suit was delayed by almost five years […]
78. Therefore, we do not think that it is an
appropriate case for granting relief to the purchaser
in terms of Section 12 of the Specific Relief Act 1963
as the claim of the purchaser is barred by delay,
laches and limitation.”
52. Having concluded that the errors apparent on the face of the record
identified above go to the root of the reasoning on both the issues of limitation and
specific performance, we recall the judgment of this Court dated 25 August 2022.
The judgment of the High Court dated 23 April 2021 is restored.
Page 37 of 38
PART H
53. The review petitions are allowed in the above terms.
54. Pending application(s), if any, is disposed of.
…….……………………………………CJI
[Dr Dhananjaya Y Chandrachud]
….….………………………………………J
[J. B. Pardiwala]
….….………………………………………J
[Manoj Misra]
New Delhi;
November 08, 2024
Page 38 of 38