Legally Bharat

Supreme Court of India

Pune Municipal Corporation vs Sus Road Baner Vikas Manch on 12 September, 2024

Author: B.R. Gavai

Bench: Prashant Kumar Mishra, B.R. Gavai

2024 INSC 682                                                                        REPORTABLE

                                          IN THE SUPREME COURT OF INDIA
                                           CIVIL APPELLATE JURISDICTION

                                        CIVIL APPEAL NOS. 258-259 OF 2021


                            PUNE MUNICIPAL CORPORATION                           …APPELLANT(S)

                                                            VERSUS

                            SUS ROAD BANER VIKAS MANCH
                            AND OTHERS                                         …RESPONDENT(S)

                                                             WITH


                                        CIVIL APPEAL NOS. 265-266 OF 2021



                                                       JUDGMENT

B.R. GAVAI, J.

1. These Civil Appeals challenge the judgment and order

dated 27th October 2020 passed by the National Green

Tribunal, Principal Bench, New Delhi1 in Original

Application2 No. 210 of 20203 wherein the Tribunal disposed

of the OA preferred by the Sus Road Baner Vikas Manch,

Signature Not Verified

Digitally signed by
Narendra Prasad
Date: 2024.09.12
1
Hereinafter referred to as the ‘Tribunal’.
12:30:06 IST
Reason: 2
Hereinafter referred to as OA
3
Earlier OA No. 34 of 2019 (WZ). Initially the OA was preferred before the
Tribunal, Western Zone, and was subsequently transferred to the Principal
Bench, New Delhi.

1

Respondent No. 1 herein, by directing the Pune Municipal

Corporation4 to close the Garbage Processing Plant5 operated

by Noble Exchange Environment Solution Pune LLP6, at

Baner, Pune and to shift the same to an alternate location in

terms of the guidelines issued by the Central Pollution

Control Board7, within 4 months from the date of the order.

Having directed the closure of the GPP, the Tribunal further

granted liberty to the Maharashtra Pollution Control Board8

to recover environmental compensation on the basis of

‘polluter pays’ principle from the GPP for the entirety of the

period during which the environmental norms were violated

by the GPP. Seeking a review of the aforesaid order, the

respondent-Concessionaire, the operator of the

aforementioned GPP, filed a Review Application being No. 49

of 2020 which came to be dismissed by the Tribunal vide

order dated 22nd December 2020. The said order is also

under challenge in these present appeals.

2. We have two Civil Appeals before us. The first set of

Civil Appeals being CA Nos. 258-259 of 2021 have been filed

4
Hereinafter referred to as the ‘appellant-Corporation’.
5
Hereinafter referred to as the ‘GPP’.

6

Hereinafter referred to as the ‘respondent-Concessionaire’.
7
Hereinafter referred to as the “CPCB”.

8

Hereinafter referred to as the “MPCB”.

2

by the Pune Municipal Corporation. The second set of Civil

Appeals being CA Nos. 265-66 of 2021 have been filed by

Noble Exchange Environment Solution Pune LLP. For the

sake of clarity and to avoid confusion, the parties will be

referred to according to their positions in the first set of civil

appeals.

3. The facts which give rise to the present appeals are as

under:

3.1. Upon the municipal limits of the appellant-Corporation

being extended to include Baner Balewadi, a Development

Plan was drawn up in 2002 wherein land situated at Survey

No. 48/2/1 in Baner Balewadi, Pune was reserved for the

purpose of a GPP. In 2004, a public hearing was conducted

for the purpose of drawing up a new development plan,

subsequent to which, the Planning Committee of the

appellant-Corporation submitted its report on 30th December

2004 to the General Body of the appellant-Corporation

earmarking the aforesaid land for a GPP in the Draft

Development Plan of 2005. The said Plan was submitted to

the Government of Maharashtra on 29th November 2005

3
whereafter the Plan came to be sanctioned by the State

Government vide Notification dated 18th September, 2008.

3.2. In the interregnum, while the aforesaid Plan was

pending approval, in 2005, permission was sought for

constructing a residential building being Tarai Heights at a

site which was approximately 100 metres away from the

earmarked land in Survey No. 48/2/1 and subsequently, in

2008, permission was sought for constructing another

residential building being 52 Green Woods at a site which

was approximately 140 metres away from the aforesaid

earmarked land. In said fashion, over the years, permission

for construction of similar such residential projects were

sought in and around the earmarked portion of land. The

last such permission was sought in 2019 for the construction

of a residential building being Platinum 9.

3.3. Subsequent to the Development Plan of 2005 being

sanctioned, the appellant-Corporation and the respondent-

Concessionaire, Respondent No. 7 in the first appeal, entered

into a Concession Agreement on 30th March 2015 for setting

up an Organic Waste Processing Plant at the land situated at

Survey No. 48/2/1. The purpose of the Concession

4
Agreement was to set up an operational waste-processing

facility where pre-segregated, non-compacted organic waste

received from the appellant-Corporation would be crushed

into a slurry, after removing any non-biodegradable material,

and the said slurry would be transported to a facility in

Talegaon where raw biogas would be generated from the

slurry. The Concession Agreement was for a period of 30

years.

3.4. Subsequently, in compliance of the notification dated

14th August 2006, for the setting up of GPP, the respondent-

Concessionaire sought Environment Clearance from the

State Level Environment Impact Assessment Authority9 on

13th August 2015. Thereafter, pursuant to a public hearing

the SEIAA granted Environment Clearance to the

respondent-Concessionaire for establishment of Organic

Waste Management Plant on 1st February 2016. The

Environment Clearance accorded was to be valid for a period

of 7 years.

3.5. In the meanwhile, on 2nd December 2015, the MPCB,

Respondent No. 2 herein, granted authorization to the

9
Hereinafter referred to as ‘SEIAA’.

5

respondent-Concessionaire to set up and operate a solid

waste processing/disposal plant in accordance with the

Municipal Solid Waste (Management and Handling) Rules,

200010. The said authorization was valid till 31st December

2016.

3.6. The authorization granted by the MPCB was

subsequently renewed on two occasions. On 4th May 2017,

the MPCB further granted authorization to the appellant-

Corporation to set up and operate waste

processing/recycling/treatment/disposal facilities at various

sites, 48 in total, including at the concerned site i.e. Survey

No. 48/2/1, at Baner, Pune. The said authorization was to

be valid till 31st December 2021. The authorization was

renewed once again on 3rd August 2022 and the same is valid

up till 31st July 2027.

3.7. In 2019, Respondent No.1-Sus Road Baner Vikas

Manch, a registered Trust that had been established to

protect the interests of the citizens residing at the Sus Road

and Baner areas in Pune, preferred an OA being No. 34 of

2019 before the National Green Tribunal, Western Zone,

10
Hereinafter referred to as the ‘2000 Rules’.
6
seeking to restrain the respondent-Concessionaire from

operating the aforementioned GPP at Survey No. 48/2/1 at

Baner, Pune since the same had been established without

following the procedure prescribed by law.

3.8. Deeming it appropriate to verify the factual details set

out in the OA, the Tribunal vide its order dated 5th

September 2019 constituted an expert committee comprising

of the CPCB and the MPCB to inspect the GPP and the area

in question, and to submit a report within a month.

3.9. In compliance of the aforesaid order, the CPCB and the

MPCB conducted a joint inspection of the GPP and area in

question. Subsequently, a report was submitted before the

Tribunal wherein the joint inspection team had made several

observations about the operational capacity of the GPP, its

authorization status and certain procedural shortcomings.

3.10. Based on the Joint Inspection Report, the Tribunal

vide the first impugned order dated 27th October 2020 held

that the GPP was in violation of the right to clean

environment of the inhabitants and was against the statutory

norms. In that view of the matter, the Tribunal disposed of

the OA in the aforementioned terms. While directing a shut-
7
down of the plant, the Tribunal further directed that the site

in question might be used for the purpose of developing a

bio-diversity park, for which purpose the site had been

originally designated. The Tribunal further constituted a

Joint Committee comprising of the CPCB, the MPCB, District

Magistrate of Pune and the Municipal Corporation of Pune to

monitor the subsequent course of action in light of the

aforesaid decision.

3.11. Aggrieved thereby, the respondent-Concessionaire

filed a Review Application before the Tribunal being Review

Application No. 49 of 2020 which came to be dismissed vide

second impugned order dated 22nd December 2020.

3.12. Being aggrieved thereby, the present statutory

appeals have been filed under Section 22 of the National

Green Tribunal Act, 201011.

4. We have heard Shri A.N.S. Nadkarni, learned Senior

Counsel appearing on behalf of the appellant in CA Nos. 258-

259 of 2021, Shri K. Parameshwar, learned Senior Counsel

appearing on behalf of the appellant in CA Nos. 265-266 of

2021 and on behalf of respondent No.7 in CA Nos.258-259 of

11
Hereinafter referred to as the “NGT Act”.

8

2021, Shri Ninad Laud, learned counsel appearing on behalf

of respondent No.1 in both the matters and Shri Rahul

Kaushik, learned Senior Counsel appearing on behalf of

respondent No.2-MPCB in both the appeals.

5. Shri Nadkarni submitted that the Draft Development

Plan 2002 for Pune city was sanctioned on 18th September

2008. He submitted that this was done after inviting and

hearing objections under Section 28 of the Maharashtra

Regional and Town Planning Act, 196612. He submitted that,

at that stage, no objection was raised by anyone. He further

submitted that the advertisement inviting Expression of

Interest for setting up Waste Segregation and Processing Unit

was published on 4th March 2014. He submitted that the

Concession Agreement was entered into on 30th March 2015.

It is submitted that the Waste Segregation Unit is set up

within Pune city limits and the Processing Plant is situated at

Talegaon that is outside the city limits. It is further

submitted that the MPCB granted its authorization to set up

and operate on 2nd December 2015 and the Environmental

Clearance was also issued on 1st February 2016.

12

Hereinafter referred to as the “MRTP Act”.
9

6. Shri Nadkarni submitted that the respondent No. 1

herein despite having knowledge of the reservation in the

Development Plan, EC and grant of authorization for the

Waste Segregation and Processing Unit, filed an OA seeking

cancellation and revocation of EC only on 2nd March 2019. It

is therefore submitted that the OA was filed belatedly almost

after a period of three years from the date of grant of EC. It

is therefore submitted that the OA was filed much beyond

the period prescribed under Section 16 of the NGT Act. As

such, the OA ought to be dismissed on the ground of

limitation alone.

7. Shri Nadkarni further submitted that the learned

Tribunal had mixed up the facts. Whereas the GPP

reservation is in Plot No. 48/2/1 under the Development

Plan, the Bio-diversity Park is in Plot No. 49 which is an

adjoining plot. As such, the direction issued by the learned

Tribunal to use Plot No. 48/2/1 for Bio-diversity Park is

unsustainable.

8. Shri Nadkarni further submitted that the reservation for

the GPP in the Draft Development Plan is since 2002 which

was subsequently sanctioned in 2008. The residential

10
buildings had come up at a much later point in time. He

submitted that only one project was commenced on 27th

December 2005 whereas the second project was commenced

on 25th March 2008 and all other projects that is 17 in

number were commenced only from 2010 onwards that is

much after sanction of the Development Plan.

9. Shri Nadkarni further submitted that the

Environmental Clearance for the GPP was received on 1st

February 2016 and the Plant was set up and commenced in

the same year. He submitted that, at the relevant time, the

2000 Rules were in force. It is submitted that the Solid Waste

Management Rules, 201613 granted two years period for the

migration and upgrading of the existing Plant to the 2016

Rules and as such, the provisions pertaining to the waste

disposal came into force on 8th April 2018 i.e. after two years

from the date of notification of the 2016 Rules.

10. Shri Nadkarni further submitted that the provisions as

regards the buffer zones around waste processing and

disposal facility came into force in 2017 and as such, would

not apply to a plant which was conceived, set up and became

13
Hereinafter referred to as the “2016 Rules”.
11
functional in 2016. It is submitted that, even the 2016 Rules

envisage decentralization of the process i.e. segregation at

source. It is submitted that the present location of the GPP

conforms to the requirement of the 2016 Rules inasmuch as

only the waste generated from surrounding areas alone is

segregated and crushed at the Baner Plant.

11. Shri Nadkarni further submitted that in pursuance of

the observations made by this Court, the appellant-

Corporation took steps to look for an alternative site, but it

has not been possible to find out an alternative site on

account of variety of reasons.

12. Shri Nadkarni further submitted that the reasoning

given by the learned Tribunal that there was no consent of

MPCB for establishment of the GPP is also unsustainable. It

is submitted that, at the relevant time, the MPCB was not

issuing a separate “consent to establish” under the Water

Act, 1974 or the Air Act, 1981 but was issuing a composite

authorization to “set up and operate” across the State. It is

submitted that the circular issued by the MPCB dated 6 th

September 2021 would clarify this position. It is further

submitted that the said practice was followed throughout the

12
State. Shri Nadkarni relies on the proceedings of the Minutes

of the Consent Committee Meeting dated 9th November 2015.

13. Shri Nadkarni submitted that, since initially the

authorization granted by MPCB on 2nd December 2015 was

valid till 31st December 2016, the appellant-Corporation and

the respondent-Concessionaire applied for renewal and the

authorization, vide communication of the MPCB dated 4th

May 2017, was renewed for a period of five years i.e. till 31st

December 2021. It is submitted that, before the expiry of five

years period which was to expire on 31st December 2021, the

appellant-Corporation and the respondent-Concessionaire

again applied for renewal of the authorization to set up and

operate on 26th October 2021 and vide communication dated

3rd August 2022, the authorization to set up and operate was

renewed till 31st July 2027. Not only that, but on 1st

November 2022, consent to operate was also obtained as per

notification dated 6th September 2021. The consent to

operate has been further renewed till 30th September 2025.

14. Shri Nadkarni further submitted that the Joint

Inspection Committee appointed by the learned Tribunal

erroneously applied the 2016 Rules which did not apply to

13
the GPP which was conceived and became functional prior to

2016.

15. Insofar as the finding of the learned Tribunal regarding

buffer zone is concerned, Shri Nadkarni submitted that the

said buffer zone of 500 meters is to be maintained from land

fill sites and does not apply to Waste Segregation Plant. Shri

Nadkarni further submitted that the continuation of the

Project was in the larger public interest. It is submitted that

the GPP processes the organic waste generated in the

western part of the city i.e., Aundh, Baner, Kothrud,

Sinhagad road and Katraj. It is submitted that, prior to

commencement of the said Plant, the organic waste

generated in the western part of the city was taken all the

way to Hadapsar which is in the eastern part of the city. It is

submitted that this led to foul odour and nuisance to public.

It is therefore submitted that the impugned order of the

learned Tribunal rather than subserving in public interest,

would be detrimental to the public interest.

16. Shri Nadkarni submitted that, in any case, in order to

address the concern of the respondents, the appellant-

Corporation is in the process of installing portable

14
compactors with hook lifting mechanism to ensure that the

reject waste generated does not touch the ground. It is

submitted that the tenders for the same have already

awarded to one M/s Global Waste Management and the

installation of the machinery would be completed by

December 2024. He further submitted that the construction

of shed to cover the reject area would also be completed by

December 2024. Shri Nadkarni further submitted that the

appellant-Corporation would construct bitumen road to the

Waste Segregation Plant and concrete the Reject Area

immediately. This will in turn enhance the clean transfer of

waste and avoid accumulation of water around the Waste

Segregation Plant. He submitted that though the appellant-

Corporation desired to do it earlier, it could not be done since

the appellant-Corporation was facing objections from

protestors due to pendency of the present proceedings.

17. Shri Parameshwar, learned Senior Counsel appearing

on behalf of the respondent-Concessionaire also supported

the submissions made on behalf of the appellant-

Corporation. He submitted that the respondent-

Concessionaire specializes in processing food waste with

15
cutting edge anaerobic digestion technology – a process in

which microorganisms break down biodegradable waste to

produce biogas and organic manure. He submitted that,

when cleaned and purified to 96% purity, Bio CNG/CBG can

replace fossil fuels such as LPG, diesel, petrol, etc. It is

further submitted that the anaerobic digestion is an efficient

and controlled biological process that productively utilises

waste in an enclosed space, rather than dumping it in a

landfill, which causes environmental harm through leaching,

contamination of groundwater, risk of fires, etc. It is further

submitted that Indian food waste is unique in its

composition, with a high concentration of antibacterial

ingredients like turmeric and spices, and greases such as

ghee that cannot be broken down using conventional

enzymes and cultures. He submitted that the respondent-

Concessionaire, through years of research and experience,

has successfully developed enzymes, cultures, and processes

to biologically break down Indian food. It is submitted that

the Project commissioned by the respondent-Concessionaire,

as a matter of fact, is environment friendly inasmuch as it

16
converts the food waste into biogas which has also been used

to run public transport buses in Pune City.

18. Shri Parameshwar submitted that, in order to carry out

the conversion of food waste into biogas, the respondent-

Concessionaire has established two plants – one in Baner

and one in Talegaon. He submitted that the site at Baner is

a waste processing facility where pre-segregated, non-

compacted organic waste is received from the appellant-

Corporation. The waste is segregated again to remove any

non-biodegradable materials, and the residual organic waste

is crushed to make a slurry. The slurry produced is then

transported to a different site in Talegaon, which is about 34

kms away from Pune City, where raw biogas is generated

from the slurry.

19. Shri Parameshwar submitted that though the

reservation in the Draft Development Plan is of 2002 which

was sanctioned in 2008, no challenge has been made in the

OA challenging the reservation of this Plot as GPP. He

therefore joins Shri Nadkarni in submitting that the

impugned order passed by the learned Tribunal is not

sustainable in law.

17

20. Shri Ninad Laud, learned counsel appearing on behalf

of respondent No.1 in both the matters submitted that the

checklist prescribed by the MPCB in 2003 would also apply

to waste processing facility and the same is not restricted to

landfill sites. He submitted that, as per the said checklist, no

development zone of 500 meters is prescribed for Municipal

Solid Waste Processing Plants and Landfill sites. He further

submitted that a mere reservation in the municipal land will

not absolve the appellant-Corporation of the environmental

obligation. He submitted that the appellant-Corporation itself

has sanctioned the plans of the buildings where the residents

of respondent No.1 reside. Having sanctioned the Plans, the

appellant-Corporation cannot run away from its duty of

preventing pollution in the area on account of GPP.

21. Insofar as the contention that the MPCB was only

granting authorization and not consent, Shri Laud submitted

that merely because the MPCB was following a particular

practice, it cannot absolve the appellant-Corporation of

obtaining consent under the Water Act, 1974 or the Air Act,

1981 which are statutory requirements. Shri Laud submitted

that the 2003 checklist is traceable to 2000 Rules.

18

22. Shri Laud further submitted that, a perusal of the Joint

Inspection Committee Report itself would reveal that the

Joint Inspection officials felt prevalence of odour in and

around the plant premises. He further submitted that the

Joint Inspection Committee also found that the segregation

rejects has been transported in open truck without any

cover. He has submitted that the said Report also suggests

that such open carriage would cause nuisance during

transportation. He therefore submitted that it is clear that

the GPP was causing pollution in the area thereby making

the life of the residents of respondent No. 1 miserable. He

submitted that, not only that even the suggestions which are

given by the National Engineering and Environment Research

Institute14 have also not been implemented.

23. Shri Laud, in the alternative, submitted that, in the

event this Court is inclined to hold that the GPP is entitled to

continue its operations, the Court should issue stringent

directions so that the residents are not compelled to suffer

the pollution.

14

Hereinafter referred to as the “NEERI”.

19

24. Shri Kaushik, learned Senior Counsel appearing on

behalf of the MPCB also accepts the position that, at the

relevant time i.e. when the GPP commenced, the MPCB was

following the practice of only granting authorization and only

after its circular dated 6th September 2021, it has started

granting consent. He therefore submitted that accordingly,

the first consent was granted on 1st November 2022 and the

second consent has been granted on 16th March 2024.

25. We have heard the learned counsel for the parties and

also perused the materials placed on record.

26. A perusal of the proposed Land Use Map for village

Balewadi, Baner which was notified on 31st December 2002

would reveal that in the said Plan, Plot No. 48/2/1 has been

reserved for GPP. Plot Nos. 49/289/50 and 7 have been

shown in Green Belt. The Draft Development Plan was

published under Section 28(4) of the MRTP Act on 30th

November 2005. In the said Plan also, Plot No. 48/2/1 has

been shown as reserved for GPP. Plot Nos. 49/289/50 and 7

have been reserved for Bio-diversity Park (BDP). The

Government of Maharashtra vide notification dated 18th

September 2008 sanctioned the said Draft Development

20
Plan. It could thus clearly be seen that right from 2002, the

Plot in question has been reserved for GPP. As already

observed hereinabove, the first building was granted

commencement certificate on 27th December 2005 whereas

the second was granted commencement certificate on 25th

March 2008 and all other, that is 17 buildings, have been

granted commencement certificate only after 2008. It is thus

clear that the commencement certificate insofar as the first

building is concerned is also after the Draft Development

Plan was statutorily notified. The commencement certificates

insofar as all other buildings are also after the Draft

Development Plan was sanctioned by the State Government.

It is thus clear that the commencement certificates in respect

of all the buildings are after the date on which the Plot was

reserved for GPP.

27. The learned Tribunal while allowing OA of respondent

No.1 has also come to a conclusion that the GPP is also in

violation of Rule 20 of 2016 Rules. For considering the

correctness of the said finding of the learned Tribunal, we

will have to first consider as to which of the Rules are to be

applicable to the said GPP.

21

28. It is the contention of the appellant-Corporation that

the GPP would be covered by the 2000 Rules whereas it is

the contention of the respondent No. 1 that the same would

be covered by the 2016 Rules.

29. As per sub-rule (2) of Rule 1 of the 2016 Rules, the

Rules were to be given effect from the date of their

publication in the Official Gazette. The 2016 Rules were

notified on 8th April 2016. As per Entry No. 7 under Rule 22

of the 2016 Rules, the time frame for establishment of

necessary infrastructure for implementation of these Rules

was to be created by the local bodies and other concerned

authorities within a period of two years from the date of the

said Rules coming into force. It is further to be noted that the

application for authorization as per sub-rule (2) of Rule 4 of

the 2000 Rules was made by the appellant-Corporation on

10th August 2015 in Form-I and the authorization was

granted in Form-III of the 2000 Rules on 2nd December 2015.

The processing plant also became operational on 17th

December 2015. It is also to be noted that the SEIAA granted

Environment Clearance in respect of the Organic Waste

Management Plant at Talegaon, Dabhade after public hearing

22
on 1st February 2016. The GPP and the Organic Waste

Management Plant at Talegoan, Dabhade are part of the

same Concession Agreement which was entered into between

the appellant-Corporation and the respondent-

Concessionaire on 30th March 2015. It could thus clearly be

seen that the application for grant of authorization, grant of

authorization, grant of Environment Clearance by the SEIAA

and the commencement of the project was all prior to 8th

April 2016 i.e. the date on which the 2016 Rules came into

force.

30. It will also be relevant to refer to the Preamble of the

said 2016 Rules, which reads thus:

“Now, therefore, in exercise of the powers conferred
by sections 3, 6 and 25 of the Environment
(Protection) Act, 1986 (29 of 1986) and in
supersession of the Municipal Solid Waste
(Management and Handling) Rules, 2000, except as
respect things done or omitted to be done before
such supersession, the Central Government hereby
makes the following rules for management of Solid
Waste, namely:-”

31. It could thus clearly be seen that the Preamble itself

states that though the 2016 Rules are in supersession of the

2000 Rules, they will apply except as respect things done or

omitted to be done before such supersession.
23

32. It will be relevant to refer to the following observations

of this Court in the case of State of Punjab v. Harnek

Singh15, wherein this Court after considering the earlier

decisions has observed thus:

“16. The words “anything duly done or suffered
thereunder” used in clause (b) of Section 6 are often
used by the legislature in saving clause which is
intended to provide that unless a different intention
appears, the repeal of an Act would not affect
anything duly done or suffered thereunder. This
Court in Hasan Nurani Malak v. S.M. Ismail, Asstt.
Charity Commr., Nagpur [AIR 1967 SC 1742] has
held that the object of such a saving clause is to
save what has been previously done under the
statute repealed. The result of such a saving clause
is that the pre-existing law continues to govern the
things done before a particular date from which the
repeal of such a pre-existing law takes effect.

In Universal Imports Agency v. Chief Controller of
Imports and Exports [AIR 1961 SC 41 : (1961) 1 SCR
305] this Court while construing the words “things
done” held that a proper interpretation of the
expression “things done” was comprehensive
enough to take in not only the things done but also
the effect of the legal consequence flowing
therefrom.”

33. It can thus be seen that this Court has in unequivocal

terms held that the term “things done” was comprehensive

enough to take in not only the things done but also the effect

of the legal consequences flowing therefrom.

15

(2002) 3 SCC 481 : 2002 INSC 84
24

34. In the present case, as already discussed hereinabove,

the application for authorization, the grant of authorization,

the grant of Environment Clearance by the SEIAA and the

commencement of the GPP all have taken place prior to 8th

April 2016 i.e. the date on which the 2016 Rules came into

force. As such, we hold that the learned Tribunal has grossly

erred in observing that the GPP in question was covered by

the 2016 Rules.

35. The next finding of the learned Tribunal is with regard

to the consent under the Water Act or the Air Act. A perusal

of the Minutes of the 11th Consent Committee Meeting of

2015-16 held on 9th November 2015 would clearly reveal that

the MPCB was following the practice of granting

authorization under the 2000 Rules which covers all the

aspects of the consent. As such, MPCB did not find it

necessary to cover such processing plant for the consent

management.

36. It will be relevant to refer to the Circular issued by the

MPCB dated 6th September 2021, which reads thus:

“Board is receiving applications from solid waste
Management Facilities and ULBs for grant of
consent for installation and operation of the facility.

25

As there is no comprehensive categorization of all
Solid waste processing operations/activities in
modified CPCB categorization for Solid Waste
Management, Board is not granting the consent for
Solid Waste Management
Facility/operations/activities.

Presently, Board is granting authorization under
The Solid Waste Management rules, 2016, for
setting up and operation of solid waste management
facilities.

The Board in its 176th meeting held on 25/O2/2O2I
passed resolution on consent management for solid
waste processing plants / facilities and decided to
grant Consent to Establish/Operate for Solid Waste
Management facilities.

The Consent fees is charged as per Env. Dept. GoM
GR dated 25.8.2011 to individual/Integrated Solid
Waste Management facility depending upon type of
ULB. The term of consent for Red, Orange, and
Green category of Industry is one, two and three
years respectively”.

Local Bodies to pay the consent fees to the Board as
per the statement given below.

• Urban Local Bodies-

  Sr.     Urban Local Body               Fees
  No.
    1. Municipal Corporation         Rs.1,00,000/-

2. Municipal Council Class-A Rs.50,000/-

3. Municipal Council Class-B Rs.5,000/-

4. Municipal Council Class-C Rs.2,000/-

• Other than Local Body-

  Individual                    Based   on   gross

                        26
       Operator/Industry           capital investment
       installing   MSW      based as per prevailing
       processing plant.           rules          for
                                   industries.

• Delegation of powers to various authorities for
grant of consent will be as per “revised
delegation of powers for consent Management”

issued vide Office Order No. 12, Dated-
23/12/2O2O.

Therefore, all Ros and SROs are hereby directed to
communicate all local Bodies/Cantonment Boards
of Concern area of jurisdiction for submission of
application to obtain Consent to Establish/Operate
for setting up and operation of existing as well as
proposed solid waste management facilities.”

37. It could thus be seen that prior to 6th September 2021,

the MPCB was not granting Consent for Solid Waste

Management facility/operations/activities. The MPCB was

granting authorization for setting up and operation of solid

waste management facilities. Only in the meeting dated 25th

February 2021, a Resolution was passed on consent

management and it was decided to grant Consent to operate

for Solid Waste Management Facilities. Vide the said

communication, all ROs and SROs were directed to

communicate to all local Bodies/Cantonment Boards of

concerned areas for submission of applications to obtain

Consent to establish/operate for setting up and operation of

27
existing as well as proposed Solid Waste Management

Facilities.

38. Admittedly, after the said date i.e. 6th September 2021,

the Consent to Operate was granted by the MPCB on 1st

November 2022. The said Consent to Operate has been

further renewed till 30th September 2025 and authorization

to set up and operate has been granted till 31st July 2027. It

can thus clearly be seen that the MPCB started granting

Consent only after 6th September 2021 and prior to that, it

was only issuing a composite authorization. We find that the

learned Tribunal has failed to take this into consideration

and as such, the finding in that regard also deserves to be

set aside.

39. The next contention is that the Checklist issued by the

MPCB which was published in 2003 would also apply to the

GPP. The learned counsel for respondent No. 1 submitted

that the said Checklist specifically prescribes that no

development zone of 500 metres was required to be kept from

the boundary of the landfill site. Further relying on the

Checklist, the learned counsel submitted that the buffer zone

of 500 metres was required to be kept from the Solid Waste

28
Processing Plant as well. A perusal of the said Checklist

would reveal that the requirement of no-development zone or

a buffer zone is only with regards to landfill sites. It can

further be seen that the Schedules framed under Rules 6

(1)(3) and 7 (2) of the 2000 Rules prescribe separate

Schedules for landfill sites on one hand and Composting,

Treated Leachates and Incineration by waste processing or

disposal facilities on the other hand. From the said Schedule-

III which is applicable to landfill sites, it can be seen that

under clause 9, a buffer zone of no-development is required

to be maintained around the landfill site and the same shall

be incorporated in the Town Planning Department’s land use

plans. However, insofar as the Standards for Composting,

Treated Leachates and Incineration are concerned, the same

read as under:

“3. In order to prevent pollution problems from
compost plant and other processing facilities, the
following shall be complied with, namely :-

i. The incoming wastes at site shall be
maintained prior to further processing.
To the extent possible, the waste storage
area should be covered. If, such storage
is done in an open area, it shall be
provided with impermeable base with
facility for collection of leachate and
surface water run-off into lined drains

29
leading to a leachate treatment and
disposal facility;

ii. Necessary precautions shall be taken
to minimise nuisance of odour, flies,
rodents, bird menace and fire hazard;
iii. In case of breakdown or maintenance
of plant, waste intake shall be stopped
and arrangements be worked out for
diversion of wastes to the landfill site;
iv. Pre-process and post-process rejects
shall be removed from the processing
facility on regular basis and shall not be
allowed to pile at the site. Recyclables
shall be routed through appropriate
vendors. The non-recyclables shall be
sent for well designed landfill site(s).
v. In case of compost plant, the windrow
area shall be provided with impermeable
base. Such a base shall be made of
concrete or compacted clay, 50 cm thick,
having permeability coefficient less than
10 –7 cm/sec. The base shall be provided
with 1 to 2 per cent slope and circled by
lined drains for collection of leachate or
surface run-off;

vi. Ambient air quality monitoring shall
be regularly carried out particularly for
checking odour nuisance at down-wind
direction on the boundary of processing
plant.”

40. We are therefore of the considered view that the

contention of the learned counsel for respondent No. 1 that

under the 2000 Rules, a buffer zone is required to be

30
maintained insofar as the GPP is concerned is without

substance.

41. We further find that the finding of the learned Tribunal

that initially the plot where GPP was constructed was

reserved for Bio-diversity Park is also erroneous and factually

incorrect. As discussed hereinabove, the plot in question has

been reserved for the GPP since inception and it is only the

adjoining plot which was reserved for the Bio-diversity Park.

42. We are therefore of the considered view that the learned

Tribunal has erred in allowing the OA of the respondent No.

1 and directing closure of the GPP. Apart from that, we find

that the closure of the GPP in question rather than

subserving the public interest, would be detrimental to

public interest. If the GPP in question is closed, the organic

waste generated in the western part of Pune city would be

required to be taken all the way throughout the city to

Hadapsar which is in the eastern part of the city. This will

undoubtedly lead to foul odour and nuisance to the public.

43. It will be relevant to refer to clauses (q) and (v) of Rule

15 of the 2016 Rules, which read thus:

31

“15. Duties and responsibilities of local authorities
and village Panchayats of census towns and urban
agglomerations.- The local authorities and
Panchayats shall,-

…………..

(q) transport segregated bio-degradable waste to the
processing facilities like compost plant, bio-

methanation plant or any such facility. Preference
shall be given for on site processing of such waste;
……………

(v) facilitate construction, operation and
maintenance of solid waste processing facilities and
associated infrastructure on their own or with
private sector participation or through any agency
for optimum utilization or various components of
solid waste adopting suitable technology including
the following technologies and adhering to the
guidelines issued by the Ministry of Urban
Development from time to time and standards
prescribed by the Central Pollution Control Board.
Preference shall be given to decentralized processing
to minimize transportation cost and environmental
impacts such as-

a) bio-methanation, microbial
composting, vermi-composting, anaerobic
digestion or any other appropriate
processing for bio-stabilisation of
biodegradable waste;

b) waste to energy processes including
refused derived fuel for combustible
fraction of waste or supply as feedstock to
solid waste based power plants or cement
kilns;”

44. It can thus be seen that the 2016 Rules also give

preference to the on-site processing of the waste. It also

emphasizes preference to be given to decentralized
32
processing to minimize transportation cost and

environmental impact. It has been submitted on behalf of

the appellant-Corporation that 48 such GPPs have been

commissioned throughout the city of Pune wherein the non-

compacted, organic waste is segregated to remove any non-

biodegradable materials and the residual organic waste is

crushed to make a slurry. The said slurry is then transported

to a site in Talegaon where raw biogas is generated from the

slurry. At the Talegaon plant, biogas is produced which is

used for providing fuel to the public transport buses. As

such, the entire Project is environmentally friendly.

45. The approach of respondent No. 1 appears to be that

such a Facility though could be established in the vicinity of

the other buildings, it should not be established in their

backyard. The Division Bench of the Bombay High Court in

the case of Bhavya Height Co-operative Housing Society

Ltd. v. Mumbai Metropolitan Region Development

Authority and Others16 had an occasion to consider a

similar situation, wherein the High Court observed thus:

“36. …….. To this affidavit there are sketch plans
annexed prepared by the Petitioner’s architects.

16

2019 SCC OnLine Bom 1075
33
These propose that the Monorail Station staircase
be shifted to a point to the south, directly in front of
Rehab Building No. 5. In other words, it would prima
facie seem that this is the classic NIMBY principle
— Not In My Back Yard. For what the Petitioner
seems to be suggesting is that it is perfectly all right
if the lives of the residents of the seven-storey slum
rehab building (all previously slum dwellers) are
endangered by the same staircase, but the
Petitioner’s members’ interest must remain
paramount. We cannot and do not countenance any
such submission.”

46. We agree with the said observations of the High Court.

47. We are therefore of the considered view that the

impugned judgment and order of the learned Tribunal

deserves to be quashed and set aside and the OA of the

respondent No. 1 is to be dismissed.

48. In the result, the appeals are allowed. The impugned

judgments and orders dated 27th October 2020 passed by the

learned Tribunal in OA No. 210 of 2020 and dated 22nd

December 2020 in Review Application being No. 49 of 2020

are quashed and set aside. OA No. 210 of 2020 filed by

respondent No. 1 is also dismissed.

49. However, before we part with the judgment, we find it

necessary to caution the appellant-Corporation as well as the

respondent-Concessionaire that they should take necessary
34
steps so that the residents residing in the nearby buildings

do not have to suffer on account of foul odour. The NEERI, in

its Report, had made the following recommendations:

“Recommendations:

Based on the observations and good engineering
practices, following suggestions are offered:
Plant A:

• The slurry making area needs proper cover in
the hopper area to reduce odour / foul smell,
• A suitable odour control system / misting
system (e.g carbon filters, etc) needs to be
installed immediately,
• Better material of construction and design
could be employed to avoid corrosion problems
and frequent shut downs,
• The space is too congested for capacity
enhancement. PMC may think of
additional/alternative space,
• The food bags need to be stored properly
before using them.

• Slurry sampling and analysis needs to be done
frequently to understand the decomposition of
food waste and control it to the level so that
maximum methane can be produced in the
Talegaon plant.

• The technology provider must also look into
reducing the transporting cost between slurry
making facility at Baner and Talegaon plant by
finding an optimum slurry density.”

50. We direct the appellant-Corporation and the

respondent-Concessionaire to ensure that all the aforesaid

35
suggestions made by NEERI should be strictly complied with.

We further direct the appellant-Corporation to install the

portable compactors with hook mechanisms so as to ensure

that the reject waste does not touch the ground by 31st

December 2024.

51. The appellant-Corporation is further directed to

construct bitumen road to the Waste Segregation Plant and

concrete the reject area which will enhance clean transfer of

waste and avoid accumulation of water around the Waste

Segregation Plant.

52. We further direct the appellant-Corporation as well as

the respondent-Concessionaire to construct a shed so as to

cover the reject area by 31st December 2024.

53. We further direct the appellant-

Corporation/respondent-Concessionaire to carry out

plantation with thick density so that there would be a green

cover on all the sides of the GPP.

54. A perusal of the sanctioned plan would reveal that, on

one side, there is a reservation for the Bio-diversity Park. As

such, the plantation would be required to be done to cover

the three sides.

36

55. Insofar as the Bio-diversity Park is concerned, we direct

the State Government to consider the possibility of growing

Miyawaki forests so as to provide green lungs to the nearby

areas.

56. We further direct the NEERI to conduct an

environmental audit of the GPP every six months and in

turn, the appellant-Corporation and the respondent-

Concessionaire are directed to ensure that the suggestions

made in the said audit are strictly complied with.

57. Pending application(s), if any, shall stand disposed of.

…………………………J.
(B.R. GAVAI)

……………………………………..J.
(PRASHANT KUMAR MISHRA)

…………………………J.
(K.V. VISWANATHAN)
NEW DELHI;

SEPTEMBER 12, 2024.

37

Source link

Leave a Reply

Your email address will not be published. Required fields are marked *