Legally Bharat

Supreme Court of India

Kukreja Construction Company vs The State Of Maharashtra on 13 September, 2024

Author: B.V. Nagarathna

Bench: B.V. Nagarathna

2024 INSC 692
                                                        REPORTABLE

                            IN THE SUPREME COURT OF INDIA

                             CIVIL APPELLATE JURISDICTION

                             CIVIL APPEAL NO.9702 OF 2024

                   KUKREJA CONSTRUCTION COMPANY
                   & OTHERS                           … APPELLANTS

                             VERSUS

                   STATE OF MAHARASHTRA & OTHERS      … RESPONDENTS


                                        WITH

                             CIVIL APPEAL NO.9703 OF 2024

                             CIVIL APPEAL NO.9704 OF 2024

                             CIVIL APPEAL NO.9705 OF 2024

                             CIVIL APPEAL NO.9706 OF 2024

                             CIVIL APPEAL NO.9707 OF 2024

                             CIVIL APPEAL NO.9708 OF 2024

                             CIVIL APPEAL NO.9709 OF 2024

                             CIVIL APPEAL NO.9710 OF 2024

                             CIVIL APPEAL NO.9711 OF 2024

                             CIVIL APPEAL NO.9712 OF 2024
   Signature Not Verified

   Digitally signed by
   RADHA SHARMA
   Date: 2024.09.13
   15:47:44 IST
   Reason:




                                                            Page 1 of 86
                       JUDGMENT



NAGARATHNA, J.

     These appeals have been filed against three impugned

judgments and orders of the High Court of Judicature at

Bombay, namely,

i)   Judgment dated 18.12.2018 whereby Writ Petition Nos.

     1898/2009,      1823/2012,      839/2015,      2871/2015,

     2107/2016, 2170/2016, 384/2017 and 541/2017 were

     rejected on the ground of delay and laches and the writ

     petitioners therein/appellants herein have filed an appeal.

     Writ Petition Nos. 203/2014 and 2262/2010 were allowed

     and Writ Petition No.1860/2017 was partly allowed.


         As against Writ Petition No.203/2014, Municipal

     Corporation of Greater Mumbai (hereinafter referred as

     “Mumbai Municipal Corporation”) has filed Civil Appeal

     No.9708/2024 arising out of Special Leave Petition (Civil)

     No.13365/2019. However, as against orders in Writ Petition




                                                     Page 2 of 86
      No.2262/2010 and 1860/2017, there are no Special Leave

      Petitions filed by the Mumbai Municipal Corporation;


ii)   Judgment     and     Order   dated   18.10.2019/08.11.2019

      whereby Writ Petition No.2531/2009 was allowed and the

      Mumbai Municipal Corporation has filed Civil Appeal

      No.9711/2024 arising out of Special Leave Petition (Civil)

      No.10430 of 2020;


iii) Judgment      dated    20.10.2022     whereby   Writ     Petition

      No.411/2013 was allowed and the Mumbai Municipal

      Corporation has filed Civil Appeal No.9712/2024 arising

      out of Special Leave Petition (Civil) No.606 of 2023.


1.1    Thus, there are sets of judgments and orders of the

Bombay High Court which have been considered together owing

to their similarity.

1.2    The High Court considered the writ petitions on the issue

concerning the implementation of the decision of this Court in

Godrej & Boyce Manufacturing Company Limited vs. State

of Maharashtra, (2009) 5 SCC 24 (“Godrej & Boyce I”). The




                                                         Page 3 of 86
said decision dealt with Regulation 34 read with Para 6 of

Appendix-VII to the Development Control Regulations for

Greater Bombay, 1991 (“the DCR” for short).

Relevant facts:

2.   With regard to the order dated 18.12.2018, the writ

petitioners before the High Court (appellants herein) were

holding plots of land shown as reserved in the sanctioned

development plan under the provisions of the Maharashtra

Regional and Town Planning Act, 1966 (“MRTP Act” for short)

which were reserved for Development Plan Road (“DP Road” for

short). According to the writ petitioners, they constructed DP

Roads at their own cost and voluntarily surrendered the

reserved lands to the Mumbai Municipal Corporation. In lieu

thereof, in terms of clause (b) of sub-section (1) of Section 126

of the MRTP Act read with Regulations 33 and 34 as well as

Para 5 of Appendix-VII of DCR, the writ petitioners were

granted Floor Space Index (“FSI” for short) and/or Transferrable

Development    Rights   (“TDR”   for   short)   in   the     form   of

Development Rights Certificates (“DRC” for short) equal to the




                                                           Page 4 of 86
gross area of the plots surrendered by them.        Para 6 of

Appendix-VII (as it stood prior to its amendment) provided that

when an owner or a lessee also develops or constructs the

amenities on the surrendered plot at his own cost and hands

over the developed/constructed amenity to the Municipal

Commissioner, he is entitled to DRC in the form of FSI or TDR

equivalent to the area of construction/development done by

him. The expression “amenity” has been defined in sub-section

(2) of Section 2 of the MRTP Act as well as clause (7) of

Regulation 3 of DCR.

2.1    For the purpose of implementation of the DCR, two

Circulars were issued on 09.04.1996 and 05.04.2003.          By

Circular dated 09.04.1996, the DRC equivalent to 15% area of

the DP Road constructed by the owner or lessee on the

surrendered plot was to be provided when the owner or lessee

surrendered the developed amenity together with the reserved

plot. By Circular dated 05.04.2003, the figure was enhanced to

25%.




                                                    Page 5 of 86
2.2   In Godrej & Boyce I, this Court held that the expression

“equivalent” in Para 6 of Appendix-VII would entitle the owner

or lessee to 100% FSI or TDR for the construction of an amenity

at his cost.   Therefore, FSI or TDR for construction of an

amenity would not be confined to 15% or 25% of DP Road area

and it would be equivalent to 100% of the area of the road

constructed by the owner or the lessee.

2.3   The grievance of the writ petitioners before the High Court

was that the Mumbai Municipal Corporation had declined to

grant 100% additional TDR equivalent to the area of the

amenity developed.       By a notification issued on 16.11.2016,

Regulation 34 of the DCR was amended. As a result, Appendix-

VII was virtually obliterated from the DCR. The notification

dated 16.11.2016 was assailed and question arose as to

whether the modifications made by the notification amending

Regulation 34 of the DCR would have retrospective or

retroactive operation.

2.4   The High Court made a brief reference to the facts of each

of the writ petitions and considered the detailed submissions



                                                      Page 6 of 86
made on behalf of the writ petitioners, the Mumbai Municipal

Corporation and the State Government.

Contentions before the High Court:

3.   It was contended on behalf of the writ petitioners before

the High Court that the unamended Regulation 33(1) of the

DCR enabled the owner of the land to seek benefit of FSI of the

land reserved for DP Road and utilize the same on the

remaining land. Till 17.06.2010, there was no entitlement to

seek FSI under Regulation 33 for construction of an amenity

and the amenity TDR was available only under Regulation 34

read with Para 6 of Appendix-VII. The amendment made on

17.06.2010 to Regulation 33 resulted in the owner, who had

constructed the road, instead of TDR, to opt for FSI to be

utilized on the remainder of the land. He would then be entitled

to an extent of 25% of the FSI. But if the owner constructed an

amenity but did not avail FSI benefit on the remainder land, the

benefit was separated from the land and given in the form of

TDR under Regulation 34 read with Para 6 of Appendix-VII.

That Para 6 of Appendix-VII was not amended as such on




                                                     Page 7 of 86
17.06.2010 after the decision of this Court in Godrej & Boyce I

as no amendment was carried out as such. However, by the

notification dated 16.11.2016, the entire Regulation 34 and

Appendix-VII were substituted. As per the amended provision,

the owner was eligible to obtain TDR for the land at the rate

mentioned in Para 4.1 of the amended Regulations as the owner

who developed the amenity thereon became eligible to receive

TDR in terms of Para 4.2 but by this, Regulation 33(1) did not

undergo any amendment.

3.1   It was contended that the aforesaid amendment should be

construed to be prospective as otherwise it would apply to cases

where amenity was developed and surrendered earlier, and

hence would be unconstitutional. It was pointed out that

subsequent to the judgment of this Court in Godrej & Boyce I,

in the case of Municipal Corporation of Greater Bombay vs.

Natwar Parikh & Co. Pvt. Ltd., Civil Appeal No.1748 of

2015, (“Natwar Parikh”) this Court had rejected the prayer of

the Mumbai Municipal Corporation to revisit the decision in the

case of Godrej & Boyce I and had also rejected the prayer for




                                                     Page 8 of 86
declaring that the said judgment would have only a prospective

effect. In the said case, this Court had also rejected an

argument of delay and laches.

3.2   It was further contended that the notification dated

16.11.2016 could not have a retrospective effect as the decision

of this Court in Godrej & Boyce I could not have been nullified

by taking away the vested right conferred, without altering the

basis of the judgment.

3.3   It was next contended that clause (b) of sub-section (1) of

Section 126 of the MRTP Act, which was incorporated into the

statute book with retrospective effect from 25.03.1991, would

imply that prior to the said date, there was no provision for

FSI/TDR for construction of a road by the owner. That for the

first time w.e.f. 17.06.2010, provision was made for an

additional 25% FSI for construction of DP Road. Since a road

falls within the definition of amenity under the DCR as well as

MRTP Act, compensation in the form of FSI/TDR for the

construction of an amenity as provided by the relevant DCR

ought to have been granted to the petitioners. This was having



                                                      Page 9 of 86
regard to Regulation 34 read with Appendix-VII which is a

complete code for grant of TDR.      It was submitted that the

scheme of an additional 100% TDR on account of construction

of an amenity was in lieu of payment of compensation in an

acquisition proceeding.

3.4   The contention of the Mumbai Municipal Corporation, on

the other hand, was that the decision of this Court in Godrej &

Boyce I, was per incuriam as it ignored the effects of Regulation

33 of the DCR. It was contended that if the compensation had

been paid partly or fully by any means, TDR could not be

granted. That in the case of the writ petitioners, the

compensation in the form of 10% or 25% additional TDR had

already been granted and the notification dated 16.11.2016 had

removed the basis of the decision of this Court in Godrej &

Boyce I and there was now a prohibition for issuance of TDR in

favour of the persons who had already been compensated. They

further contended that the impugned notification would apply

even to cases pending before the High Court and the Mumbai

Municipal Corporation as the judgment in Godrej & Boyce I




                                                     Page 10 of 86
had been nullified by the said notification.      Further, there

cannot be 100% TDR in respect of the area of the amenity

developed, and therefore, to cure the defect, the notification

dated 16.11.2016 was enforced and that the DCR applicable on

the date of deciding an application for grant of development

permission would govern the decision on the application.

3.5   By way of reply, the writ petitioners contended before the

High Court that the notification dated 16.11.2016 was not a

validating Act. It was merely a delegated legislation which could

not nullify the judgment of the Apex Court. The right to claim

TDR on the development of the amenity vests in the owner the

moment     the   permission   is   granted   by   the     Municipal

Corporation to construct the road/amenity. The judgment in

Godrej & Boyce I is not per incuriam and had been applied in

other subsequent cases. The object of giving a benefit under

Regulation 34 is owing to lack of financial capacity of the

Municipal Corporation to construct amenities by itself. Hence,

the writ petitioners sought relief under Regulation 34 of the

DCR.




                                                        Page 11 of 86
Consideration by the High Court:

4.     On a consideration of the rival submissions and taking

note of the fact that the contention of the Mumbai Municipal

Corporation was that the decision of this Court in Godrej &

Boyce I was per incuriam, the High Court considered the

provisions of the Act and the Regulations in extenso. The High

Court noted that in almost all the cases the action of

surrendering the land and developing the amenities had been

completed by 17.06.2010 when Regulation 33 underwent an

amendment.      Therefore, on a consideration of the erstwhile

Regulation 33, the High Court observed that the same was

applicable to a case where the owner, including a lessee, had

surrendered the land or area required for road widening or for

construction of a new road proposed under the development

plan    or   those   proposed   under   the   Mumbai    Municipal

Corporation Act, 1888 (“the Act of 1888” for short).       Thus, it

would apply to the lands reserved in the development plan for

construction of new roads or for road widening and also to the

lands which were within the road-line as fixed under the Act of




                                                       Page 12 of 86
1888 on which a road had not yet been constructed. The said

provision was not applicable to any other amenity.        It was

further observed that a part of FSI could be used on the plot

remaining after such surrender and the balance FSI was to be

permitted to be utilised as TDR by issuing DRC. Such TDR was

to be governed by Regulation 34 as that is the provision for

grant of TDR.    Thereafter, the road and land would stand

transferred in the city survey record in the name of the Mumbai

Municipal Corporation and vest in the Corporation.

4.1   Reference was then made to Regulation 34 and Appendix-

VII, which deals with TDR.     The concept of TDR is that FSI

available in respect of one plot of land could be permitted to be

utilised on another plot of land. Para 6 of Appendix-VII dealt

with a case where the owner or lessee developed or constructed

the amenity on the surrendered land. In such a case, it was

relatable to clause (b) of sub-section (1) of Section 126 of the

MRTP Act. The said Act defines “amenity” under sub-section (2)

of Section 2 of the MRTP Act, as also in clause (7) of Regulation

3 of the DCR. The High Court observed that Regulation 33(1)




                                                     Page 13 of 86
gave effect to clause (b) of sub-section (1) of Section 126 of the

MRTP Act. That Para 5 of Appendix-VII pertains to the extent of

TDR to be granted against the surrender of a reserved land.

Para 5 of Appendix-VII is significant inasmuch as it deals with a

case where the owner or lessee develops or constructs an

amenity on the surrendered plot at his own cost subject to such

stipulation   as   may    be   prescribed   by   the     Municipal

Commissioner. That the expression ‘amenity’ would include a

road and the construction or development of the road would

have to be at the cost of the owner. In such an event, under

Para 6 of Appendix-VII, the grant of additional FSI in the form

DRC is equivalent to the area of construction/development

done by the owner as per the stipulations prescribed by the

Commissioner.      This is like a compensation granted for

construction of an amenity as provided in clause (b) of sub-

section (1) of Section 126 of the Act.

4.2   The High Court again considered the argument of the

Mumbai Municipal Corporation made before this Court to the

effect that the value of the amenity developed or constructed by




                                                       Page 14 of 86
the owner for which an additional TDR was sought must be

commensurate to the value of the amenity and not the area of

the amenity, which argument had been repelled by this Court

in Godrej & Boyce I. Thus, the High Court on considering the

judgment of this Court in Godrej & Boyce I observed that the

additional TDR was required to be granted as per DCR and in

particular Para 6 of Appendix-VII equivalent to the area

constructed or developed and not on the basis of the value of

the development of the amenity.        Hence, the High Court

observed   that   when   a   land   which   is   reserved   in   the

development plan under the MRTP Act for a public purpose is

surrendered by the owner or lessee free of cost and the amenity

is developed thereon, on its surrender, the owner or lessee will

be entitled to FSI/TDR equivalent to the area of the

surrendered land and an additional TDR equivalent to the area

of the amenity developed or constructed by him.

4.3   While considering the arguments on behalf of the Mumbai

Municipal Corporation with regard to Regulation 33, the High

Court observed that the said Regulation provided that only a




                                                      Page 15 of 86
part of the land FSI can be used on the remaining portion of the

land and the balance FSI had to be provided in the form of

TDR, as per Appendix-VII. That Appendix-VII read with

Regulation 34 dealt only with grant of TDR and the conditions

on which TDR can be granted. Even the TDR available in terms

of the Regulation 33(1) will be governed by Regulation 34 read

with Appendix-VII.   This is particularly so, as per Para 5 of

Appendix-VII which applied to the grant of TDR in respect of

land covered by Regulation 33(1). That Para 6 of Appendix-VII

dealt with both situations, i.e., where the entire land held by

the owner or lessee was reserved or a part thereof was reserved

and the land was surrendered to the Corporation. Para 6 also

dealt with grant of an additional TDR for construction of an

amenity in terms of clause (b) of sub-section (1) of Section 126

of the MRTP Act. Regulation 33(1) dealt with FSI or TDR in lieu

of surrender of land required for roads whereas Para 6 of

Appendix-VII dealt with the grant of FSI or TDR in respect of

the road developed at the cost of the owner or the lessee. That




                                                    Page 16 of 86
this Court in Godrej & Boyce I had considered Regulation 33

also.

4.4     Considering Regulation 33 which had undergone an

amendment on 17.06.2010, the High Court observed that prior

to the amendment, the said Regulation did not deal with FSI or

TDR in lieu of the construction of road. It dealt with only FSI or

TDR against the surrender of land reserved for road. However,

after amendment, when a road constructed as per the

stipulation of the Commissioner was handed over to the

Commissioner free of cost, an initial FSI equivalent to 25% of

the area of construction of road can be granted. A part of the

FSI can be consumed on the remaining land and the remaining

part of the FSI will be provided in the form of TDR. Therefore,

the     amendment   to   Regulation   33(1)   was   applicable   to

reservation of road and not for any other amenity. It was also

clarified that the amendment will not apply where the FSI

granted in lieu of road had been utilized and full occupation

certificate had been granted prior to 17.06.2010.       Therefore,

after 17.06.2010, in case of a land reserved for road or road




                                                      Page 17 of 86
widening which was surrendered, if the amenity being a road

had been constructed by the owner on the land surrendered,

the additional FSI as provided in clause (b) of sub-section (1) of

Section 126 of the MRTP Act will be 25% of the area of the

construction of road. Hence, Para 6 of Appendix-VII to

Regulation 34 would apply and the owner or the lessee will not

get TDR equivalent to entire area of the road constructed by

him but it will be confined to 25% of the area.

4.5   It was clarified that pursuant to notification dated

16.11.2016, Para 4.2 of the Schedule to the notification would

be the only clause applicable to the grant of TDR against

construction of amenity and that from 16.11.2016, Para 6 of

Appendix-VII would not apply to the lands with amenity

surrendered after that date. In other words, Regulation 34

stands substituted by the Schedule to the said notification. It

was further observed by the High Court that the said

notification dated 16.11.2016 did not have a retrospective

operation and it also did not take away the basis of the decision

in Godrej & Boyce I.




                                                     Page 18 of 86
4.6   It was further clarified by the High Court that in the case

of Natwar Parikh & Co. Pvt. Ltd. vs. State of Maharashtra,

2014 SCC Online Bom 495 (“Natwar Parikh & Co. Pvt.

Ltd.”), 25% TDR was granted to the petitioner therein in the

year 2006-2007. Subsequent to the decision of this Court in

Godrej & Boyce I, the petitioner therein had filed a petition.

On the facts of the case in Natwar Parikh & Co. Pvt. Ltd., it

was observed that there was no delay or laches. The said

decision of the High Court was sustained by this Court in Civil

Appeal No.1748 of 2015.      This Court had also rejected the

argument that the judgment in Godrej & Boyce I should apply

prospectively.

4.7   Finally, it was held that additional FSI or TDR in terms of

Para 6 of Appendix-VII as well as in terms of clause (1) of

Regulation 33 becomes available on surrender of the land

reserved with or without amenity, as the case may be. After

17.06.2010, if there is surrender of land reserved for road or

road widening on which road is constructed by the owner or

lessee, the FSI or TDR will be available in respect of amenity of




                                                     Page 19 of 86
road as per Regulation 33(1) as amended. Therefore, the right

to get FSI or TDR accrues at the time of surrender.

4.8    Thereafter, the High Court went into the facts of each of

the writ petitions. Accordingly, the High Court passed the

following order:

      i)     We hold that the notification dated 16th November
             2016 is legal and valid. However, the said
             notification will not have retrospective or
             retroactive application to a land reserved under the
             development plan which is surrendered and
             amenity is developed on the said land by the owner
             or lessee thereof at his own cost prior to 16 th
             November 2016. Such cases will be governed by
             the Regulation 33(1) and clauses (5) and 6 of
             Appendix VII. In case of a land reserved for a road,
             either in development plan under the MRTP Act or
             under the provisions of the said Act of 1888 and
             surrender is made and road is developed on or
             after 17th June 2010 but before 16th November
             2016, the FSI or TDR in lieu of amenity will be
             governed by the Regulation 33(1) as amended on
             17th June 2010.

      ii)    We reject the argument that the decision of the
             Apex Court in the case of Godrej & Boyce
             Manufacturing Company Limited (supra) is per
             incuriam.

      iii)    We hold that whether the writ jurisdiction of this
             Court under Article 226 of the Constitution of India
             can be allowed to be invoked on the basis of the
             said decision or not depends upon the facts of each



                                                         Page 20 of 86
     case and the conduct of the petitioners especially
     the delay and laches on their part;

iv) Writ Petition No.203 of 2014 is allowed. We direct
    the    third    respondent-MMRDA        to    make
    recommendation to the Mumbai Municipal
    Corporation for grant of 75% additional FSI/TDR in
    terms of the aforesaid decision of the Apex Court
    within a period of two months from today. The
    Municipal Corporation shall examine the said
    recommendation and if the petitioners are
    otherwise entitled to TDR for amenity in terms of
    the aforesaid decision of the Apex Court, necessary
    DRC shall be issued within a period of two months
    from the date on which recommendation of
    MMRDA is received.

v)   Writ Petition No.1898 of 2009 is rejected;

vi) In Writ Petition No.2262 of 2010, the petitioners
    will be entitled to additional 100% amenity FSI in
    terms of the aforesaid decision of the Apex Court
    provided by producing the documents, they satisfy
    the Mumbai Municipal Corporation that work was
    actually carried out by them for developing the
    recreation grounds and the ground;

vii) Writ Petition No.1823 of 2012 is rejected.

viii) Writ Petition No.839 of 2015 is rejected.

ix) Writ Petition No.2871 of 2015 is rejected.

x)   Writ Petition No.2107 of 2016 is rejected.

xi) Writ Petition No.2170 of 2016 is rejected.

xii) Writ Petition No.384 of 2017 is rejected.



                                                  Page 21 of 86
      xiii) Writ Petition No.541 of 2017 is rejected.

      xiv) Writ Petition No.1860 of 2017 is partly allowed. We
           direct the Mumbai Municipal Corporation to grant
           additional FSI in respect of amenity of road as
           provided by Regulation 33(1) as amended with
           effect from 17th June 2010.

      xv) We make it clear that wherever we have held that
          the petitioners are entitled to 100% amenity TDR in
          accordance with clause 6 of Appendix VII in terms
          of the aforesaid decision of the Apex Court, the
          Mumbai Municipal Corporation will have to
          examine whether the petitioners are otherwise
          eligible for grant of TDR.”


4.9    Out of all the writ petitions disposed of, Writ Petition

No.203 of 2014 was allowed and a direction was issued to the

MMRDA to make recommendations to Mumbai Municipal

Corporation for grant of 75% additional FSI/TDR in terms of

the decision of this Court in Godrej & Boyce I within two

months from the said date of disposal. A further direction was

issued to Mumbai Municipal Corporation to consider the said

recommendation and to pass orders for issuance of DRC within

a     period   of   two   months     from   the   date   on    which

recommendation of MMRDA was received, provided the writ




                                                         Page 22 of 86
petitioner was otherwise entitled to TDR for amenity in terms of

the judgment of this Court in Godrej & Boyce I.

4.10   Similarly, in Writ Petition No.2262 of 2010, additional

FSI to the extent of 100% on amenity was granted in terms of

the decision of this Court in Godrej & Boyce I provided the

writ petitioner therein produced the documents and satisfied

the Mumbai Municipal Corporation that work was actually

carried out for developing the recreation grounds and ground.

4.11   Writ Petition No.1860 of 2017 was partly allowed to the

effect that Mumbai Municipal Corporation ought to grant

additional FSI in respect of amenity of road as provided by

Regulation 33(1) as amended with effect from 17.06.2010. It

was also observed that the petitioners therein are entitled to

100% amenity TDR in accordance with Para 6 of Appendix-VII

in terms of the aforesaid decision of this Court in Godrej &

Boyce I and Mumbai Municipal Corporation was to examine

whether the petitioners therein were otherwise eligible for grant

of TDR.




                                                     Page 23 of 86
4.12    With regard to those cases which were dismissed on the

ground of delay and laches, appeals have been filed by the

private petitioners therein. Appeal has been filed by Mumbai

Municipal Corporation against the order in writ petition No.203

of 2014 but no appeal has been filed against the order in Writ

Petition Nos.2262/2010 and 1860/2017.

       There are two more impugned judgments in Writ Petition

Nos.2531/2009 and 411/2013 against which the Mumbai

Municipal Corporation has filed its appeals.

4.13    At this stage, it may be mentioned that where the writ

petitions were dismissed by the High Court on the ground of

delay and laches, there is no observation in those writ petitions

denying the benefit on merits. Insofar as in three cases where

the writ petitions were allowed, there is only one appeal filed by

the Mumbai Municipal Corporation as the orders in Writ

Petition No.2262 of 2010 and Writ Petition No.1860/2017 have

been accepted by it.




                                                     Page 24 of 86
4.14 The details of the three cases in which appeals have been

filed by the Mumbai Municipal Corporation are noted as

under:-

     (i)   WP No.2531 of 2009 –             Starwing Developers

           Private Limited     vs. Municipal Corporation of

           Greater Mumbai - disposed of on 18.10.2019

     (ii) WP No.203 of 2014 – Apurva Natvar Parikh

           and Co. Private Ltd. vs. State of Maharashtra

           and Others - disposed of on 18.12.2018

     (iii) WP   No.411   of    2013     –    Arvind   Kashinath

           Dadarkar      and     Others         vs.   Municipal

           Corporation of Greater Mumbai and Others –

           disposed of on 20.10.2022.

Starwing Developers Private Limited:

5.    In Starwing Developers Private Limited vs. State of

Maharashtra (“Starwing Developers Private Limited”), Writ

Petition No.2531 of 2009 disposed by the High Court on

18.10.2019, unamended Regulation 33 and Regulation 34 as




                                                        Page 25 of 86
they stood prior to 2010 were considered in depth. It was

observed that Regulation 34 as it stood at the relevant time

provided that in certain circumstances, the development

potential of a plot of land could be separated from the land

itself and could be made available to the owner of the land in

the form of TDR which would be subjected to Regulation 34 and

Appendix-VII.   It   was   observed   that   Appendix-VII   titled

“Regulations for the grant of Transferable Development Rights

(TDRs) to owners/developers and conditions for grant of such

rights” had a scheme for the award of TDR to the owner of the

plot of land which was reserved for public purpose and for

additional amenities in the form of FSI. As per the conditions

set out therein, such award would entitle the owner of the land

to FSI in the form of DRC which he could use for himself or

transfer to any other person. Para 5 of the Appendix provided

that the built-up area for the purposes of FSI credited in the

form of DRC shall be equal to the gross area of the reserved plot

to be surrendered and will proportionately increase or decrease

according to the permissible FSI of the zone where the TDR has




                                                     Page 26 of 86
originated. Para 6 provided that when an owner or a lessee also

developed or constructed an amenity on the surrendered plot at

his own cost, subject to such stipulations which may be

prescribed and to the satisfaction thereof and hands over the

developed or constructed amenity to the Commissioner or the

appropriate authority free of cost, he would be granted further

DR    in   the   form    of   FSI   equivalent   to   the   area    of

construction/development done by him, utilisation of which

would be subject to the regulations contained in the said

Appendix.

5.1   Contrasting Regulation 34 with Regulation 33, it was

observed that the latter pertained to additional FSI which may

be allowed to certain categories. Sub-regulation (1) as it stood

at the relevant time, provided that the Commissioner could

permit the additional FSI on 100% of the area required for road

widening    or   for   construction   of   new   roads   under     the

development plan. Such FSI so surrendered would be utilisable

on the remainder of the land up to a limit of 40% in respect of

the plots situated in Mumbai city and 80% in respect of the




                                                         Page 27 of 86
plots situated in suburbs and extended suburbs. The balance

FSI remaining thereafter was allowed to be utilised as a

development right in accordance with the regulations governing

TDRs. In the said case, it was again contended on behalf of the

Mumbai Municipal Corporation that the petitioner therein

having utilised 100% FSI for surrender of land without cost on

the same layout, was governed by Regulation 33 and therefore,

could not claim any additional FSI/TDR for having constructed

the amenities. This contention, in fact, was squarely identical

to those in the case of Apurva Natwar Parikh & Co. Pvt. Ltd

which case is discussed later.

5.2   It was pointed out that till the amendment on 17.06.2010,

there was no provision in Regulation 33 for claiming FSI for

construction of amenities and the same could be claimed only

in terms of Regulation 34 read with Para 6 of Appendix-VII. On

the other hand, it was contended by the Municipal Corporation

that Regulation 33 was not brought to the notice of this Court

in Godrej & Boyce I and that by notification dated 16.11.2016

the Regulation was amended to restrict the benefit of additional




                                                    Page 28 of 86
TDR for development of amenities which was to cure a defect in

the legislation. The said contention was considered in light of

the amendment to Regulation 33 with effect from 17.06.2010,

by which a clause was added to sub-regulation (1) and it was

observed   that   the   amendment    to   Regulation   33(1)   was

applicable to roads and not to any other amenity. Moreover,

this portion of the amendment would not apply where the FSI

granted in lieu of road is utilised and full occupation certificate

was granted prior to 17.06.2010. Therefore, from 17.06.2010 in

case of a land reserved for road or road widening which was

surrendered, if the amenity of the road was constructed by the

owner of the land surrendered, the additional FSI as provided

in clause (b) of sub-section (1) of Section 126 will be 25% from

the area of the construction of the road. Therefore, for such

amenity, in terms of Para 6 of Appendix-VII, the owner or a

lessee will not get TDR equivalent to entire area of the road

constructed by him. It will remain confined to 25% of the area.

It was observed that Regulation 33(1) as amended on




                                                       Page 29 of 86
17.06.2010 was not modified by the impugned notification

dated 16.11.2016.

Apurva Natwar Parikh & Co. Pvt. Ltd.:

6.   In the case of Apurva Natwar Parikh & Co. Pvt. Ltd. vs.

State of Maharashtra, Writ Petition No.203 of 2014 filed

before the High Court, the surrender of land was in the form of

deed of conveyance and handing over of possession was in

February, 2007 and within three years from the surrender i.e.

February, 2010, the writ petitioner/appellant herein requested

an officer of MMRDA to recommend to the Mumbai Municipal

Corporation to issue 100% additional TDR in respect of

construction of amenity. In December, 2010, DRC of 25% of the

amenity was granted. The balance 75% had not been paid.

Hence, the writ petition was filed in October, 2013. Actually,

within one month from the date of decision in the case of

Godrej and Boyce I, the petitioner applied to the respondent-

MMRDA     for   recommending    to   the   Mumbai    Municipal

Corporation for grant of 100% TDR in respect of the amenity

and the said application was acted upon and 25% FSI was




                                                    Page 30 of 86
granted in December, 2010. Therefore, the High Court held that

conduct of the petitioner is not such that it will prevent the Writ

Court from granting relief in terms of the decision in Godrej &

Boyce I.

Arvind Kashinath Dadarkar:

7.   In     Arvind    Kashinath    Dadarkar      vs.    Municipal

Corporation of Greater Mumbai, Writ Petition No.411 of

2013      (“Arvind   Kashinath    Dadarkar”),    disposed    of on

20.10.2022, another Division Bench of the High Court of

Bombay while adverting to Godrej & Boyce I and Apurva

Natvar Parikh & Co. Pvt. Ltd., and Starwing Developers

Private Limited, allowed the writ petition and directed that

TDR be issued to the petitioner therein.

Submissions:

8.   We have heard the arguments of the respective Senior

Counsel and other Counsel on both sides and perused the

material on record.




                                                       Page 31 of 86
Submissions on behalf of the Appellants:

8.1   Learned senior counsel, Sri Pravin Samdani, contended

that the impugned judgment dated 18.12.2018 has, in fact,

upheld petitioners’ right to 100% additional TDR and has

applied the judgment of this Court in Godrej & Boyce I.

However, reliefs were declined to certain writ petitioners on the

ground of delay and laches in claiming the additional TDR in

time. Consequently, the writ petitions were dismissed by the

High Court. Being aggrieved by the dismissal of the writ

petitions, the writ petitioners before the High Court have

preferred these appeals. Therefore, this Court may reverse the

finding of the High Court on the issue of the delay and laches

and grant the reliefs to these appellants as the other writ

petitioners have been granted by the High Court.

8.2   In this regard, it was submitted that the compensation

payable to the landowners/lessees for acquisition of their land

for a public purpose is, in fact, held in trust by the acquiring

body, i.e., the Mumbai Municipal Corporation in the instant

case. Once the compensation is determined, the same was




                                                     Page 32 of 86
payable and the reliefs could not have been denied by the High

Court on the ground of delay or laches. In this context, reliance

was placed on Noida Entrepreneur Association vs. NOIDA,

(2011) 6 SCC 508 (Para 38-39) (“Noida Entrepreneur

Association”).

8.3   It was next submitted that the State is the guardian or

custodian and protector of the rights of the citizens. This casts

a duty and obligation on the State to pay compensation to land

losers for lands compulsorily acquired. The right to receive a

fair compensation is a constitutional right guaranteed under

Article 300A of the Constitution of India which can also be

traced to Article 21 of the Constitution of India as a citizen

cannot be deprived of his property, save in accordance with law.

It was contended that the mandate of Section 126(1)(b) of the

MRTP Act and the DCR be complied with by the respondent -

Mumbai Municipal Corporation vis-à-vis the appellants herein.

Otherwise, the denial of compensation would amount to

usurping the citizens’ property without authority of law and in

breach of the constitutional rights of the citizens.      In this




                                                     Page 33 of 86
context, reliance was placed on Vidya Devi vs. State of

Himachal Pradesh, (2020) 2 SCC 569 (Para 12.9 to 12.14);

Sukh Dutt Ratra vs. State of Himachal Pradesh, (2022)

SCC OnLine SC 410, (Para 13-27); and Lalaram Vs. Jaipur

Development Authority, (2016) 11 SCC 31, (Para 124 &

129); Kazi Moinuddin Kazi Bashiroddin vs. Maharashtra

Tourism Development Corporation (2022) SCC OnLine SC

1325, (Para 26).

8.4    In the above backdrop, learned senior counsel, Sri Pravin

Samdani submitted that the High Court was not right in

dismissing the writ petitions on the ground of delay and laches

when the respondent – Mumbai Municipal Corporation had not

proved that:

      (i)    the delay amounted to laches;
      (ii)   owing to delay and during the interregnum, the

             respondent – Mumbai Municipal Corporation had

             altered its position to its prejudice; and




                                                          Page 34 of 86
      (iii)     certain rights had accrued which could not be

                disturbed       by   grant   of   reliefs   to   the    writ

                petitioners/appellants herein.

       In this context, reliance was placed on Moon Mills Ltd.

vs. M.R. Meher, President, Industrial Court, Bombay, AIR

1967 SC 1450, (Para 9); M/s Dehri Rohtas Light Railway

Company Limited vs. District Board, Bhojpur, (1992) (2)

SCC 598, (Para 13); Hindustan Petroleum Corporation Ltd.

vs. Dolly Das, (1999) 4 SCC 450] (Para 8); and Tukaram

Kana          Joshi   vs.   Maharashtra           Industrial     Development

Corporation (2013) 1 SCC 353, (Para 12); and Mohar Singh

(Dead) Thr. LRs. vs. State of UP Collector, 2023 INSC 1019

(Para 12).

8.5    It     was     further    urged   that     the   Mumbai         Municipal

Corporation has not asserted that owing to the alleged delay on

the part of the appellants herein in making their claim under

Section 126(1)(b) of the MRTP Act, there was any prejudice

caused to it.




                                                                  Page 35 of 86
8.6   It was also submitted that the observations of the High

Court in the impugned judgment that there was a waiver or an

abandonment of their rights by the writ petitioners/appellants

herein are contrary to the facts and law. In this regard

reference was made to Godrej & Boyce Manufacturing Co.

Ltd. vs. Municipal Corporation of Greater Mumbai, (2023)

SCC OnLine SC 592, (Paras 8, 15 and 18) (“Godrej & Boyce

II”); G.T. Lad vs. Chemical and Fibres of India Ltd., (1979)

1 SCC 590, (Para 5 & 6); A.P. SRTC vs. S. Jayaram, (2004)

13 SCC 792, (Para 5); and State of Punjab vs. Davinder Pal

Singh Bhullar, (2011) 14 SCC 770, (Para 37 to 42).

8.7   Petitioners’ counsel therefore sought for allowing these

appeals by setting aside that portion of the order of the High

Court declining to grant relief on the ground of delay and

laches.

8.8   On the merits of the case, Sri Samdani submitted that

Section 2(2) of the MRTP Act defines an amenity which is also

defined under Regulation 3(7) of DCR. Section 126(1)(b) of

MRTP      Act   provides   for   compulsory   acquisition,   wherein



                                                        Page 36 of 86
compensation is provided in the form of FSI or TDR in two

parts: (i) for the land; and (ii) for development/construction of

the amenity at the cost of the owner on the surrendered land in

terms of the DCR. That Regulations 33(1) and 34 prior to their

amendment in the year 2010 provided a mechanism for grant of

TDR for both the first as well as the second component. This

Court had interpreted the aforesaid provisions in the case of

Godrej & Boyce I. This Court observed that the grant of

additional TDR was for construction or development of the

amenity. However, in the year 2010, there was an amendment

which stated that in addition to the land component of

FSI/TDR, the land owner would be entitled to receive only

additional 25% FSI/TDR for construction of road. However, the

additional 25% could be used as FSI on the remainder of the

plot if the remainder of the plot could consume to the extent of

40/80% of the remaining land after surrender. The balance

FSI/TDR was eligible to be paid as TDR under Paras 5 and 6 of

Appendix-VII-A and Regulation 34 of the DCR. This amendment

of 17.06.2010 was subsequent to the judgment of this court in




                                                     Page 37 of 86
Godrej & Boyce I. However, there was no alteration to

Regulation 34 and Paras 5 and 6 of Appendix-VII-A of the DCR.

This amendment was in the form of delegated legislation and

was only prospective in nature. But by the amendment of

16.11.2016, the entire Regulation 34 and Appendix-VII-A was

amended. As a result of the amendment, if the land owner

desired to obtain TDR for the land component, the owner was

eligible to do so at the rate mentioned in Para 4.1 of amended

Regulation. If the landowner also developed the amenity, the

owner became eligible to receive compensatory TDR in terms of

Para 4.2 of the amended Regulation.

8.9   According to learned senior counsel, this amendment is

also prospective. It was further submitted that by the

amendment of Regulation 34 of the DCR, the basis of the

judgment in Godrej & Boyce I was not removed. The intention

of the amendment was to grant additional compensation to the

landowner in view of the enforcement of Right to Fair

Compensation    and   Transparency    in   Land   Acquisition,

Rehabilitation and Resettlement Act, 2013 and not to remove




                                                  Page 38 of 86
the basis of the judgment in Godrej & Boyce I. There was no

intention to validate any action of the Corporation of curtailing

amenity TDR to 25% or to validate Circulars based on which it

was sought to be curtailed to 25%. Therefore, the judgment of

this Court in Godrej & Boyce I remains intact.

8.10    It was further submitted that the right to receive

compensation     for   acquisition    is   a   vested   right   and   a

constitutional right and the same cannot be taken away by an

amendment to the statute.

8.11   It was next submitted that the attempt of the Mumbai

Municipal Corporation to deny balance 75% TDR in view of the

notification dated 16.11.2016 is unsustainable. This is because

the writ petitioners’ right to receive the balance TDR is a vested

right which arose under the old DCR and continues even after

the    amendment.      Further,   a   person     cannot    be   denied

compensation by a subsequent legislation when the entitlement

is recognized under a prior legislation. The High Court has

rightly held that the DCR amended was prospective and not

retrospective.



                                                          Page 39 of 86
Submissions on behalf of the Respondents:

9.    Per contra, learned senior counsel Sri Nadkarni, appearing

for the respondent – Mumbai Municipal Corporation submitted

a chart giving details of each of the appellants/writ petitioners

before the High Court. The relevant chart is extracted

hereinbelow:

SR. NO./   PARTICULARS        DATE    OF   WHETHER             APPLICATION       DELAY
RELEVANT                      HANDING      HANDED              FOR
REGULATION                    OVER    OF   OVER                ADDITIONAL
                              AMENITY      AMENITY             AMENITY
                                           COMPLIES            FSI/TDR
                                           WITH    ALL         AFTER
                                           CONDITIONS          GODRIJ      &
                                                               BOYCE
                                                               JUDGMENT

(06.02.2009)

1. KUKREJA 28.01.1994 –NO— 31.08.2009 6-15 years
REGULATION CONSTRUCTION In the (calculated
34 CO. & ORS. VS. constructed from the date
STATE OF road the sewer of handing
MAHARASHTRA lines were not over of
& ORS. laid down nor amenity)
the street
SLP (C) lights were laid
NO.5273.2019 down. On
failure to
WP(C) comply parties
NO.1898/2009 are required to
pay prorate
charges. As
regard to
street lights
the prorate
charges were
paid after
delay, Sewer
lines were not
paid.

2. NANABHOY 1. YES For 6 cases – 8-16 years
REGULATION JEEJEEBHOY 13.04.2004 11.07.2014 (calculated
33(1) PVT. LTD. & ANR. 2. from the date
VS. STATE OF 20.03.2001 For 4 cases – of handing
MAHARASHTRA 3. 19.08.2014 over of
& ANR. 27.03.2002 amenity)

4. For one case
06.09.2001 – 26.08.2014

Page 40 of 86
SR. NO./ PARTICULARS DATE OF WHETHER APPLICATION DELAY
RELEVANT HANDING HANDED FOR
REGULATION OVER OF OVER ADDITIONAL
AMENITY AMENITY AMENITY
COMPLIES FSI/TDR
WITH ALL AFTER
CONDITIONS GODRIJ &
BOYCE
JUDGMENT
(06.02.2009)
SLP (C) 5.

            NO.8664/2019       13.02.2006
                               6.
            WP          (C)    27.10.1997
            NO.541/2017        7.
                               27.10.1997
                               8.
                               29.10.1997
                               9.
                               21.12.2002
                               10.
                               14.12.2001

                               /22.05.2002

                               11.
                               14.08.2002


3.         JITENDRA       05.03.2005         YES           24.02.2009      4 years
REGULATION AMRITLAL SETH                                                   (calculated
33(1)      &    ORS.  VS.                                                  from the date
           STATE      OF                                                   of    handing
           MAHARASHTRA                                                     over        of
           & ORS.                                                          amenity)

            SLP (C) NO.8204
            / 2019

           WP(C)
           NO.1823/2012
4.         GEETA    ALIAS      20.05.2005    YES           For Balance     4½ years
REGULATION CHANDANI                                        75%             (calculated
34         UMESH                                           additional      from the date
           GANDHI                                          TDR        on   of    handing
                                                           01.12.2009,     over        of
           SLP           (C)                               20.06.2014,     amenity)
           NO.15702/2019                                   01.12.2014,
                                                           20.02.2016
           WP(C)
           NO.839/2015
5.         MCGM        V.      07.02.2007    YES           Balance 75%     No delay case
REGULATION APURVA                                          TDR             as       High
34         NATWAR                                          14.12.2011      Court
           PAREKH & CO.                                    (Godrej    &    allowed the
           PVT.  LTD   &                                   Boyce case –    WP
           ORS.                                            after 2 years
                                                           applied)




                                                                        Page 41 of 86
SR. NO./   PARTICULARS        DATE    OF    WHETHER       APPLICATION          DELAY
RELEVANT                      HANDING       HANDED        FOR
REGULATION                    OVER    OF    OVER          ADDITIONAL
                              AMENITY       AMENITY       AMENITY
                                            COMPLIES      FSI/TDR
                                            WITH    ALL   AFTER
                                            CONDITIONS    GODRIJ      &
                                                          BOYCE
                                                          JUDGMENT
                                                          (06.02.2009)
            SLP         (C)
            NO.13365/2019

            WP(C)
            NO.203/2014

6.         OBEROI             1. 26.05.04   YES           10.06.2016        8 years
REGULATION REALITY   LTD.     2. 16.04.08                                   (calculated
33(1)      ANR. VS. MCGM      3. 29.03.08                                   from the date
           & ANR.                                                           of    handing
                                                                            over        of
            SLP        (C)                                                  amenity)
            NO.8520/2019

            WP(C)
            NO.384/2017


7.         GIRDHARLAL D. 13.12.1995         YES           05.08.2014        18 years
REGULATION RUGHANI ALIAS                                                    (calculated
33(1)      THAKAR HUF &                                                     from the date
           ANR.                                                             of    handing
           VS.                                                              over        of
           STATE       OF                                                   amenity)
           MAHARASTHRA
           & ORS.

            SLP        (C)
            NO.5745/2020

           WP(C)
           NO.2170/2016
8.         JAMEEL      A.     29.07.2004    YES           28.07.2014        4 years from
REGULATION HUSSAIN      &                                                   notification
33(1)      ORS. V.                                                          dated
           STATE      OF                                                    17.06.2010
           MAHARASHTRA
           & ORS.

            SLP        (C)
            NO.8704/2019

           WP(C)
           NO.2871/2015
9.         BYRAMJI       05.06.2007         YES           No                9 years (wrt
REGULATION JEEJEEBHOY                                     Application       the WP filed)
34         PVT LTD. ANR.                                  made        for
           VS. STATE OF                                   75%
           MAHARASHTRA                                    additional.




                                                                       Page 42 of 86
SR. NO./   PARTICULARS       DATE    OF   WHETHER       APPLICATION        DELAY
RELEVANT                     HANDING      HANDED        FOR
REGULATION                   OVER    OF   OVER          ADDITIONAL
                             AMENITY      AMENITY       AMENITY
                                          COMPLIES      FSI/TDR
                                          WITH    ALL   AFTER
                                          CONDITIONS    GODRIJ      &
                                                        BOYCE
                                                        JUDGMENT
                                                        (06.02.2009)

            SLP        (C)
            NO.8552/2019

           WP(C)
           NO.2107/2016
10.        MCGM        V. 29.12.2007      YES           ……………….         1½ years
REGULATION STARWING                                                     (calculated
33(1)                                                                   from the date
           SLP          (C)                                             of    rejection
           NO.10430/2020                                                by the State
                                                                        Government
            WP(C)                                                       on
            NO.2531/2009                                                15.07.2008
                                                                        and
                                                                        thereafter WP
                                                                        filed        on
                                                                        05.12.2009)


9.1    Insofar as the appellant – M/s Kukreja Construction

Company, it was submitted that the conditions which are

required to be complied with for seeking compensation under

Section 126(1)(b) of the MRTP Act have not been met and

therefore, unless and until the said conditions are complied

with, the said appellant would not be entitled to compensation

under the scheme of the Act and the Regulations made

thereunder. As far as the other appellants are concerned, he

fairly submitted that even according to the Mumbai Municipal

Corporation they have complied with the conditions as required

Page 43 of 86
under the scheme and therefore, their cases could be

considered if they are otherwise eligible for compensation being

paid to them in case they are successful in these appeals.

9.2 Learned senior counsel also strenuously sought to

buttress the submissions made on behalf of the Mumbai

Municipal Corporation before the High Court regarding the

judgment of this Court in Godrej & Boyce I, but did not

persuade himself to do so. Ultimately, he supported the order of

the High Court in denying the reliefs to the writ petitioners who

had delayed in making their claims. He contended that the High

Court was right in declining to grant the relief to the said

parties.

9.3 Sri Nadkarni contented that firstly, the High Court was

right in declining relief based on the judgment of this Court in

Godrej and Boyce I owing to delay, as those developers who

already availed of the TDR and accepted the same without any

protest or demur could not again agitate the matter after the

judgement of this Court in Godrej and Boyce I. Secondly, there

was a crystallisation of the compensation payable in the form of

Page 44 of 86
FSI/TDR as on the date of the notice of acquisition which in

this case could be either the publication of the development

plan or the date of preliminary notification under the

Acquisition Act and that the owner or lessee could not have

returned for a second helping or make an additional claim of

100% TDR since the value of the land as on the date when the

project was conceived or when the benefits were received would

have been lesser than the value of the land on the date of the

filing of the writ petition. Thirdly, any grant of additional TDR

despite there being a delay would result in unjust enrichment

of the owner and the lessee who could get an advantage of

escalation in price of land which is contrary to public interest.

Therefore, for this reason also, the High Court was justified in

declining to grant relief on the ground of delay and laches.

Hence, there is no merit in these appeals.

9.4 Learned senior counsel submitted that in the event this

Court is to condone the delay and laches and thereby modifies

the impugned judgment of the High Court then, in the case of

the appellants in CA No. 9702 of 2024, (Kukreja Construction

Page 45 of 86
company and others) this Court may direct that only on

complying with the mandatory requirements could the said

appellant avail of the benefits of additional FSI/TDR in

accordance with law as indicated in the table above.

9.5 Learned senior counsel, Sri Nadkarni, with reference to

our order dated 06.08.2024, sought further instruction on

Estate Investment Company Ltd. and Ever-smile Construction

being granted relief of 100% of TDR rights in terms of Section

126(1)(b) of the MRTP Act as well as the DCR. He fairly

submitted that there is no dispute that the aforesaid two

entities were indeed granted 100% TDR rights. Further, there

has been no appeal filed with regard to the order of the High

Court in Writ Petition No. 1860 of 2017 and Writ Petition

No.2262 of 2010. Learned senior counsel, Sri Nadkarni, also

submitted that insofar as the judgment of the High Court

assailed in Civil Appeal Nos.9711/2024 and 9712/2024, they

may be disposed in light of the prevalent law.

Page 46 of 86
Reply arguments:

10. By way of reply, learned senior counsel, Sri Samdani and

other learned counsel contended that the Mumbai Municipal

Corporation cannot be permitted to raise any contention

contrary to the judgment of this Court in Godrej & Boyce I

which is holding the field and there is no contention raised by

the Municipal Corporation either before the High Court or this

Court which can lead to a reconsideration of the said judgment.

Hence, they sought for application of the judgment of this Court

in Godrej & Boyce I to their cases as well.

10.1 Learned counsel for the respondents in the three appeals

filed by the Mumbai Municipal Corporation supported the

impugned order passed by Bombay High Court and contented

that having regard to the judgment of this Court in Godrej &

Boyce I and the order passed in Civil Appeal No. 1748 of 2015

which arose from the judgment of the Bombay High Court in

the case of Natwar Parikh & Co. Pvt. Ltd, there is no merit in

these appeals. Hence, they contended that the appeals filed by

the Mumbai Municipal Corporation may be dismissed.

Page 47 of 86
Points for consideration:

11. In light of the aforesaid contentions, the following points

would arise for our consideration: –

(i) Whether the High Court was right in declining to

grant relief to the writ petitioners/appellants

herein on the ground of delay and laches?

(ii) Whether the appeals filed by the respondent-

Mumbai Municipal Corporation would call for

any interference by this Court?

(iii) What order?

Godrej & Boyce I:

12. At the outset, it would be useful to refer to the dictum of

this Court in Godrej & Boyce I which has been followed by the

High Court in these cases. In the said case, this Court

considered the scheme of development rights in respect of land

acquired for the purpose specified in plans under Section 126

of the MRTP Act. Three modes of acquisition of land required

for a public purpose specified in the plan are contemplated

under Section 126 of the MRTP Act, which reads as under:

Page 48 of 86

“126. Acquisition of land required for public
purposes specified in plans.— (1) Where after the
publication of a draft Regional plan, a Development or
any other plan or town planning scheme, any land is
required or reserved for any of the public purposes
specified in any plan or scheme under this Act at any
time, the Planning Authority, Development Authority,
or as the case may be, any Appropriate Authority may,
except as otherwise provided in Section 113-A
acquire the land,—

(a) by agreement by paying an amount agreed to, or

(b) in lieu of any such amount, by granting the land-

owner or the lessee, subject, however, to the lessee
paying the lessor or depositing with the Planning
Authority, Development Authority or Appropriate
Authority, as the case may be, for payment to the
lessor, an amount equivalent to the value of the lessor’s
interest to be determined by any of the said Authorities
concerned on the basis of the principles laid down in
the Right and Fair Compensation and Transparency in
Land Acquisition, Rehabilitation and Resettlement Act,
2013, Floor Space Index (FSI) or Transferable
Development Rights (TDR) against the area of land
surrendered free of cost and free from all
encumbrances, and also further additional Floor Space
Index or Transferable Development Rights against the
development or construction of the amenity on the
surrendered land at his cost, as the Final Development
Control Regulations prepared in this behalf provide, or

(c) by making an application to the State Government
for acquiring such land under the provisions of the
Right and Fair Compensation and Transparency in
Land Acquisition, Rehabilitation and Resettlement Act,

Page 49 of 86
2013, and the land (together with the amenity, if any so
developed or constructed) so acquired by agreement or
by grant of Floor Space Index or additional Floor Space
Index or Transferable Development Rights under this
section or under the provisions of the Right and Fair
Compensation and Transparency in Land Acquisition,
Rehabilitation and Resettlement Act, 2013, as the case
may be, shall vest absolutely free from all
encumbrances in the Planning Authority, Development
Authority, or as the case may be, any Appropriate
Authority.

(2) On receipt of such application, if the State
Government is satisfied that the land specified in the
application is needed for the public purpose therein
specified, or if the State Government (except in cases
falling under Section 49 and except as provided in
Section 113-A) itself is of opinion that any land
included in any such plan is needed for any public
purpose, it may make a declaration to that effect in
the Official Gazette, in the manner provided in Section
19 Right to Fair Compensation and Transparency in
Land Acquisition, Rehabilitation and Resettlement Act,
2013, in respect of the said land. The declaration so
published shall, notwithstanding anything contained in
the said Act, be deemed to be a declaration duly made
under the said section:

Provided that, subject to the provisions of sub-
section (4), no such declaration shall be made after the
expiry of one year from the date of publication of the
draft Regional Plan, Development Plan or any other
Plan, or Scheme, as the case may be.

(3) On publication of a declaration under the said
Section 19, the Collector shall proceed to take order for
the acquisition of the land under the said Act; and the

Page 50 of 86
provisions of that Act shall apply to the acquisition of
the said land with the modification that the market
value of the land shall be,—

(i) where the land is to be acquired for the purposes of a
new town, the market value prevailing on the date of
publication of the notification constituting or declaring
the Development Authority for such town;

(ii) where the land is acquired for the purposes of a
Special Planning Authority, the market value prevailing
on the date of publication of the notification of the area
as undeveloped area; and

(iii) in any other case, the market value on the date of
publication of the interim development plan, the draft
development plan or the plan for the area or areas for
comprehensive development, whichever is earlier, or as
the case may be, the date of publication of the draft
Town Planning Scheme:

Provided that, nothing in this sub-section shall affect
the date for the purpose of determining the market
value of land in respect of which proceedings for
acquisition commenced before the commencement of
the Maharashtra Regional and Town Planning (Second
Amendment) Act, 1972:

Provided further that, for the purpose of clause (ii) of
this sub-section, the market value in respect of land
included in any undeveloped area notified under sub-
section (1) of Section 40 prior to the commencement of
the Maharashtra Regional and Town Planning (Second
Amendment) Act, 1972, shall be the market value
prevailing on the date of such commencement.
(4) Notwithstanding anything contained in the proviso
to sub-section (2) and sub-section (3), if a declaration,

Page 51 of 86
is not made, within the period referred to in sub-

section (2) (or having been made, the aforesaid period
expired on the commencement of the Maharashtra
Regional and Town Planning (Amendment) Act, 1993,
the State Government may make a fresh declaration for
acquiring the land under the provisions of the Right
and Fair Compensation and Transparency in Land
Acquisition, Rehabilitation and Resettlement Act, 2013,
in the manner provided by sub-sections (2) and (3) of
this section, subject to the modification that the market
value of the land shall be the market value at the date
of declaration in the Official Gazette, made for acquiring
the land afresh.”

In this case, we are concerned with Section 126(1)(b) of the

MRTP Act.

12.1 Under Section 126(1) of the MRTP Act, when land is

required or reserved for any of the public purposes specified in

any plan or scheme under the Act at any time, the Planning

Authority, the Development Authority, or as the case may

be, any Appropriate Authority may acquire the land by

agreement by paying an amount agreed to landowner or lessee

[Section 126(1)(a)]; the second mode is, in lieu of any such

amount as mentioned above, by granting the landowner or the

lessee, subject, however, to the lessee paying the lessor or

Page 52 of 86
depositing with the Planning Authority, the Development

Authority or Appropriate Authority, as the case may be, for

payment to the lessor, an amount equivalent to the value of the

lessor’s interest to be determined by any of the said Authorities

concerned on the basis of the principles laid down in the Land

Acquisition Act, 1894, Floor Space Index (FSI) or Transferable

Development Rights (TDR):

(i) against the area of land surrendered free of cost and free

from all encumbrances, and also

(ii) further additional FSI or TDR against the development or

construction of the amenity on the surrendered land at his

cost, as the Final Development Control Regulations

prepared in that behalf provide [Section 126(1)(b)].

The third mode being by acquisition of the land

under the relevant Act [Section 126(1)(c)].

12.2 Thus, it is open to the landowner to surrender the plot of

land “free of cost” and “free from all encumbrances” to the

appropriate authority who may acquire the land by granting to

Page 53 of 86
the owner FSI or TDR against the area of the surrendered land.

The scheme further provides for additional FSI or TDR against

the development of construction of amenities (for which the plot

is shown reserved in the plan) by the owner at his own cost.

12.3 In Godrej & Boyce I, the appellants therein had their

plots covered under the development plan as reserved for roads,

which they voluntarily surrendered. In addition, they

constructed on their respective pieces of land the development

plan roads at their own cost and as per the specifications

stipulated in the relevant rules. In the said case, there was no

dispute between the parties in regard to the FSI or TDRs

granted to them for the surrendered plots of land. The

controversy was with regard to the FSI or TDRs for roads

constructed on the surrendered lands at the owner’s cost. The

landowners claimed that for constructing the roads they were

entitled to FSI or TDRs for the whole of the surface area of the

roads. They relied upon Para 6 of Appendix-VII to the DCRs.

The Mumbai Municipal Corporation however relied upon a

Circular dated 09.04.1996 issued by the Municipal

Page 54 of 86
Commissioner, Municipal Corporation of Greater Bombay,

which envisaged a graded scheme for grant of additional

development rights for construction of amenities by the

landowner, e.g. in case of amenities like general hospital,

municipal primary school, etc. which allowed FSI equal to the

built-up area of the structure but in case of DP road only 15%

of the area of the road surface. The Circular was assailed by

the landowners.

12.4 In the said case, the Bombay High Court had accepted

the contention advanced on behalf of the State of Maharashtra

to the effect that by introducing a graded scheme for grant of

additional FSI or TDR the Circular had eliminated the

possibility of any discriminatory or arbitrary action on the part

of the authority competent to issue the development right

certificate. It was contended that grant of further additional

TDR was commensurate to the value of the amenity

constructed/developed on the surrendered land. Therefore, it

was contended that Para 6 of the Appendix-VII, unlike Para 5

didn’t use the words “equal to the gross area of the reserved

Page 55 of 86
plot” or “equal in area”. Instead, Para 6 used the words

“equivalent to the area of construction/development”. That,

Para 6 of Appendix-VII to the Regulations must be read with

Section 126(1)(b) of the Act. It was evident that the said

provision used the words “against the area of the land

surrendered” and “against the development or construction of

amenity on the surrendered land”. Therefore, the grant of

additional development right was proportionate to the value of

the amenity constructed by the owner at his own cost and the

Circular issued by the Municipal Commissioner simply

quantified the exchange value of different kinds of amenities in

percentage terms depending upon their cost of construction

and other relevant considerations.

12.5 However, the aforesaid submission, which was accepted

by the Bombay High Court was not agreed to by this Court and

the judgment of the Bombay High Court was set-aside. While

doing so, the submission on behalf of the appellants therein

was accepted that the provision clearly envisaged grant of the

FSI or TDR under two separate heads: one, for the land, and

Page 56 of 86
the other, for the construction of the amenity for which the land

was designated in the development plan at the cost of the

owner. The Court also held that Section 2(9-A) defined

“development right” to include TDR and Section 126(1)(b)

provided for:

(i) grant of FSI or TDR against the area of land

surrendered free of cost, and

(ii) further, additional FSI or TDR against the

development or construction of the amenity on

the surrendered land at the owner’s cost as the

final Development Control Regulations should

provide.

12.6 In the case of (i) above, FSI or TDR would be equal to the

gross area of the surrendered plot, and for (ii) above i.e. for

construction of the amenity, the extent of the FSI or TDR would

be equivalent to the area of the construction/development

made on the land.

Page 57 of 86
12.7 That Regulation 34 made provisions for transferability of

the development rights and Appendix-VII referred to in

Regulation 34 provided for the extent of FSI or TDR admissible

under the two heads. That the expression “equivalent to the

area” of the construction or development made on the

surrendered land in Para 6 of Appendix-VII would mean

“equivalent to the area of construction/development”, that is to

say, the additional DR would be the same in area as the

amenity constructed/developed on the surrendered land.

Hence, there cannot be a differentiation in the grant of

additional TDR on a variable and sliding scale on the

surrendered land for amenities constructed on the basis of the

Circular issued by the Municipal Commissioner. Also, the

Circular cannot override the provisions of the Regulations. It

was further observed that the expressions “against the area of

the land surrendered free of cost” and “against the development

or construction of amenity on the surrendered land” would mean

“in exchange for, in return for; as an equivalent or set-off for; in

lieu of, instead of”. Section 126(1)(b) was a recompense to the

Page 58 of 86
landowner proportionate to the area of development or

construction of the amenity on the surrendered land. Thus, in

Para 5 of Appendix-VII to the Regulations, the expression

“equal to the gross area of reserved plot” was relatable to the

bare land and in Para 6 of the Appendix, the expression

“equivalent to the area of the construction/development” would

mean that “the area of construction or development” is the

measure of equivalence. Therefore, there could be no other

basis for determining the equivalence. Hence, the Circular was

held to be without authority of law.

Natwar Parikh & Co. Pvt. Ltd.:

13. Prior to the impugned judgments of the High Court, in

Natwar Parikh & Co. Pvt. Ltd., a writ petition was filed before

the Bombay High Court seeking a direction for grant of

additional TDR/development rights certificate (DRC) for the

balance 75% area as set out in the Schedules annexed to the

writ petitions. In that case also, admittedly, the respondents

therein had been granted 25% TDR/DRC in lieu of the

construction of the specified DP Road and there was no

Page 59 of 86
challenge about the actual work done at the relevant time.

Subsequent to the judgment of this Court in Godrej & Boyce I,

the petitioner therein filed the petition. The respondent Mumbai

Municipal Corporation sought to deny the same on a twofold

contention: firstly, there was delay and laches; and, secondly,

an attempt was made to reopen the issues on facts about the

construction of the DP Road. The same were repelled by the

High Court by holding that already 25% TDR had been granted

and therefore, there could be no reopening of the controversy

on that basis and the only question which remained was the

entitlement of the petitioner to remaining 75% TDR/DRC as

prayed.

13.1 A contention was also sought to be raised by the

respondent-Corporation that the petitioner therein had not

built upon the amenity as contemplated under Regulation 34

Appendix-VII Paras 5 and 6. The said contention was also

repelled by holding that the right of the petitioner has already

been crystallised and the cause of action was a continuing one

and hence there was no question of delay and laches.

Page 60 of 86
Consequently, a direction was issued to grant additional TDR

for the balance 75% area. It was also observed that the issues

which were raised in the said case had been concluded by the

judgment of this Court in the case of Municipal Corporation

of Greater Bombay vs. Yeshwant Jagannath Vaity, (2011)

11 SCC 88 (“Yeshwant Jagannath Vaity”), “for other

amenity” also.

13.2 In Civil Appeal No.1748 of 2015 (Municipal

Corporation of Greater Mumbai vs. Natwar Parikh and Co.

Pvt. Ltd.), this Court by order dated 05.05.2016 has

categorically observed that it was too late to re-visit the entire

issue and to take a decision whether the judgment delivered

earlier in Godrej & Boyce I should apply prospectively and not

retrospectively. That is a matter which should have been

agitated when Godrej & Boyce I was being heard. It was

further observed that insofar as the 89 applicants who were

then waiting to take an advantage of the aforesaid decision

rendered by this Court, on the facts of the cases the

applications ought to be considered and if a dispute arises the

Page 61 of 86
appropriate Court would take a decision in the matter.

Consequently, the Civil Appeal filed by the Mumbai Municipal

Corporation were dismissed.

Godrej & Boyce II:

14. It would be useful to refer to another decision of this Court

in the case of Godrej & Boyce II. In the said case, two

questions arose for consideration in the context of grant of DRC

for a total area of 31,057.30 sq. metres, for the construction

and development of the amenity namely, Recreation Ground.

One of the questions considered was whether the High Court

was right in concluding that there was an abandonment of

claim by the appellants therein. Touching upon the facts of the

case, this Court took note of the rejection of the claim by the

Corporation vide communication dated 27.11.1998 for the

grant of additional TDR made by application dated 17.04.1998;

the resolution of the dispute of the said entity with the decision

of this Court dated 06.02.2009 in Godrej & Boyce I (its own

case); application being made for the grant of additional TDR on

03.11.2009 being rejected and a fresh writ petition being filed

Page 62 of 86
in the year 2010. This Court considered the law of

abandonment in the context of the contention raised by the

Mumbai Municipal Corporation and it was observed in

paragraphs 15 to 18 as under:

“15. The law of abandonment is based upon the
maxim invito beneficium non datur. It means that
the law confers upon a man no rights or benefits
which he does not desire. In P. Dasa Muni Reddy v. P.
Appa Rao, this Court held that “abandonment of right is
much more than mere waiver, acquiescence or laches….
Waiver is an intentional relinquishment of a known right
or advantage, benefit, claim or privilege….”. In
paragraph 13 of the said decision, this Court put the
law pithily in the following words:

“13…. There can be no waiver of a non-

existent right. Similarly, one cannot waive
that which is not one’s as a right at the time
of waiver. …”

16. Irrespective of whether the respondents concede or
not, the Circular dated 09.04.1996 curtailed the rights
of the owners to have additional TDR in certain
circumstances. The Circular came under challenge
before this Court and the decision of this Court
in Godrej and Boyce Manufacturing Company
Limited was delivered on 06.02.2009. As we have stated
earlier, the decision in Godrej and Boyce Manufacturing
Company Limited was in the case of the very appellant
No. 1 herein though in respect of some other property.

17. To put it differently, what was cited by the
Municipal Corporation in their order of rejection dated
27.11.1998 as an impediment for the grant of
additional TDR was the subject matter of challenge in

Page 63 of 86
the first round. It was made by the very appellant No. 1
herein, though in respect of another property. If the
said decision in the first round had gone against
appellant No. 1 herein, the rejection of the claim of the
appellants for additional TDR on the basis of “prevailing
policy” would have become final and unquestionable.

18. In other words, during the period from 1996 to
2009, the right to claim additional TDR was in
suspended animation. Therefore, the appellants had to
necessarily wait till the cloud over their right got
cleared. To say that the wait of the appellants during
the period of this cloudy weather, tantamount to
abandonment, is clearly unjustified and unacceptable.

Therefore, the finding recorded by the High Court on
question No. 1 is not in tune with the law or the facts of
the present case and hence question No.1 has to be
answered in favour of the appellants herein.”
(underlining by us)

14.1 The next question considered was whether the finding of

fact arrived at by the High Court that the appellant therein did

not and could not have developed the amenity, calls for any

interference, especially in light of the statutory provisions and

the facts of the case. The statutory provisions in Section

126(1)(b) were adverted to on the approach that the authorities

ought to have in these matters and this Court observed as

under:

Page 64 of 86

“21. As we have noted earlier, clauses (a), (b) and (c)
were inserted by way of substitution in sub-section (1)
of Section 126 under Maharashtra Act 10 of 1994 with
effect from 25.03.1991.

22. As per Section 126(1), whenever the Planning
Authority or Development Authority finds after the
publication of a draft Regional Plan or a Development
Plan that any land is required or reserved for any of the
public purposes mentioned in the plan, such authority
may acquire the land for the said public purpose. This
acquisition can be made by three different methods,
indicated in clauses (a), (b) and (c). The methods of
acquisition prescribed in clauses (a), (b) and (c) of sub-

section (1) of Section 126, in simple terms are as
follows:—

(i) The acquisition may be through an agreement
entered into with the owner, by paying an amount
agreed to;

(ii) Alternatively, the acquisition may be by the grant
of FSI or TDR in lieu of any payment, along with
Additional FSI or Additional TDR against the
development or construction of the amenity on the
surrendered land at the cost of the owner; or

(iii) The acquisition may also be by requesting the State
Government to initiate the process of land
acquisition under the Right to Fair Compensation
and Transparency in Land Acquisition,
Rehabilitation and Resettlement Act, 2013.

23. We are concerned in this case with the second
method of acquisition of land indicated in clause (b) of
sub-section (1) of Section 126. Under this clause, the
owner and the planning authority are granted the
leverage to agree that the compensation for the
acquisition of the land will be for a consideration, not
paid in the form of cash but granted in kind, in the

Page 65 of 86
form of two things, namely, (i) FSI or TDR for the area
of land surrendered; and (ii) additional FSI or
additional TDR against the development or
construction of the amenity on the surrendered land.

24. Once the parties are ad idem on the fact that the
case is covered by clause (b), then what is necessary to
be seen by Courts is : (i) whether the parties had
agreed to give/take FSI or TDR in lieu of the amount of
compensation?; and (ii) whether there was a valid claim
for the grant of additional FSI or additional TDR
towards the development or construction of the
amenity on the surrendered land at the cost of the
owner?.”

14.2 This Court observed therein that there was no dispute on

facts that the appellants therein had surrendered the land and

accepted TDR in lieu of compensation. The only question was

whether parties had satisfied the last limb of clause (b) which

reads as under:

“26. ……and also further additional Floor Space Index
or Transferable Development Rights against the
development or construction of the amenity on the
surrendered land at his cost, as the Final Development
Control Regulations prepared in this behalf provide,”

14.3 It was observed that the owner of the land is under an

obligation to develop or construct the amenity on the

surrendered land at his cost and the Planning Authority has to

Page 66 of 86
reciprocate the same by granting additional FSI or additional

TDR. While considering the said issue, both on facts as well as

in law, this Court referred to the definition of the word

“amenity” and “development” in Section 2(2) and 2(7)

respectively of the Act and observed that the word “amenity”

means several things including recreational grounds in respect

of which the controversy arose in the said case. There was a

dispute as to whether the appellant therein had not developed

the recreational grounds. While considering the expression

“development”, it was observed that the same was of wide

import and in fact clause (b) of sub-section (1) of Section 126 of

the Act has used both the expressions, namely (i) development;

and (ii) construction. Therefore, the word “development” has to

be understood to mean any activity which may or may not

include construction. Therefore, the question in the said case

was, whether, the appellant therein had developed or

constructed any amenity which ought to be tested with

reference to the final DCR. While referring to the definition of

amenity in Regulation 2(7) which includes recreational grounds,

Page 67 of 86
reference was made to Regulation 34 and it was observed that

Appendix-VII was later renumbered as Appendix-VII-A vide

order dated 15.10.1997. It was observed that clauses (5), (6)

and (7) of the Regulation 34 was the substratum of the

controversy before the High Court.

14.4 Going through the entire gamut of correspondence

involved in the said case, it was held that all the activities

undertaken by appellant No.1 therein through the Architects till

handing over of the possession of the land were not towards the

development of amenity and the grant of additional TDR. All

these works were undertaken as part of the effort to make the

Municipal Corporation accept the surrender of land and to

grant TDR. On the facts of the said case, it was held that no

amenity was developed as required by law by appellants Nos.1

and 2 therein to be entitled to additional TDR. Therefore, on

facts, it was held that appellant was not entitled for additional

TDR. Accordingly, the view of the High Court was confirmed

and the appeal was dismissed.

Page 68 of 86
Yeshwant Jagannath Vaity:

15. In Yeshwant Jagannath Vaity, the facts were that the

respondents therein owned 10,000 sq. yards of land in Mulund

village, which came within the area of Greater Bombay. A

development plan was sanctioned for Greater Bombay in the

year 1957. The said land was shown as reserved for public

purpose of construction of a godown. However, the respondents

and four other co-owners entered into a private agreement to

handover possession of 10,000 sq. yards to the Municipal

Corporation of Greater Bombay (MCGB) for temporary use as a

truck terminal. The land was also to be used as a town duty

office. The possession was handed over on 18.09.1961. The

land was not put to any other use till November 1998.

Therefore, Writ Petition No.3437 of 1988 was filed seeking a

declaration that the land was not liable to be acquired which

resulted into a compromise between the parties in which MCGB

agreed to acquire and retain the area of 3500 sq. metres for the

purpose of establishing and constructing an export octroi office.

The respondents therein constructed the export office and also

Page 69 of 86
developed the surrounding area. The possession of the export

office and the courtyard was handed over to the MCGB for

which a possession receipt was also issued. An application was

made by the respondents for TDR in respect of the export office

being 3500 sq. metres equivalent of the 100 per cent of the

built-up area of the export office. However, insofar as the

additional transferable rights in lieu of the development of the

export courtyard surrounding the export office was concerned,

the same was restricted to 466.96 sq. metres being 15 per cent

of the built-up area of the courtyard.

15.1 The respondents not having received a favourable

response to their request filed a writ petition which was allowed

by the High Court. The High Court while granting the relief

relied upon the judgment of this Court in Godrej & Boyce I. In

the appeal filed by the MCGB, several contentions were raised

including the contention regarding the Circular dated

09.04.1996 having no bearing on Godrej & Boyce I, since it

was issued after the landowners had surrendered their plot of

land after construction of the roads as required by the

Page 70 of 86
Municipal Council while in the said case the said Circular was

issued prior to the respondents No.1 and 3 therein completing

the construction of an export office and asphalting of the

courtyard and handing over the possession. Several arguments

were advanced to distinguish the judgment of this Court in

Godrej & Boyce I. This Court observed that the works done by

the respondent therein was an amenity and the Circular dated

09.04.1996 did not have any bearing on the case as it was

issued after the compromise in the Writ Petition on 10.03.1992

and the issuance of the letter of intent dated 22.02.1995.

Accordingly, the appeal filed by the respondent MCGB was

dismissed.

15.2 The reasoning of this Court in the said judgment is

squarely applicable to these cases. This Court held that the

High Court was right in allowing the writ petition filed by the

respondent therein and granting 100% TDR as against the

development of the courtyard by asphalting the same.

Page 71 of 86
Delay and Laches:

16. However, most of the writ petitions which were filed by the

appellants herein were dismissed on the ground of delay and

laches by the Bombay High Court. We have already adverted to

the judgment of this Court in Godrej & Boyce II on the aspect

of abandonment of the claim. The contentions of learned senior

counsel and learned counsel for the appellants would not call

for a reiteration.

17. At this stage, we shall consider some of the judgments

relied upon by the learned senior counsel for the respective

parties.

On the question of discretion of courts in considering the

issue of delay and laches, this Court in Vidya Devi vs. State of

Himachal Pradesh, (2020) 2 SCC 569 (“Vidya Devi”) noted

as under,

“12.12. The contention advanced by the State of delay
and laches of the appellant in moving the Court is also
liable to be rejected. Delay and laches cannot be
raised in a case of a continuing cause of action, or if
the circumstances shock the judicial conscience of the
Court. Condonation of delay is a matter of judicial
discretion, which must be exercised judiciously and

Page 72 of 86
reasonably in the facts and circumstances of a case.

It will depend upon the breach of fundamental rights,
and the remedy claimed, and when and how the delay
arose. There is no period of limitation prescribed for
the courts to exercise their constitutional
jurisdiction to do substantial justice.”
(emphasis supplied)

17.1 On the question of the principles the Court should rely

upon when exercising the discretion to condone delay and

laches, the following judgments are instructive.

(a) In Dehri Rohtas Light Rly. Co. Ltd. vs. District Board,

Bhojpur, (1992) 2 SCC 598, this Court noted that:

“13… The principle on which the relief to the party on
the grounds of laches or delay is denied is that the
rights which have accrued to others by reason of the
delay in filing the petition should not be allowed to be
disturbed unless there is a reasonable explanation for
the delay. The real test to determine delay in such
cases is that the petitioner should come to the writ
court before a parallel right is created and that the
lapse of time is not attributable to any laches or
negligence. The test is not as to physical running of
time. Where the circumstances justifying the
conduct exist, the illegality which is manifest
cannot be sustained on the sole ground of laches.”
(emphasis supplied)

(b) In Tukaram Kana Joshi vs. Maharashtra Industrial

Development Corporation, (2013) 1 SCC 353, this Court

Page 73 of 86
held, albeit in the context of the State taking over possession of

land without any sanction of law, to the following effect:

“12… Our Constitution is an organic and flexible one.
Delay and laches is adopted as a mode of discretion to
decline exercise of jurisdiction to grant relief. There is
another facet. The Court is required to exercise judicial
discretion. The said discretion is dependent on facts
and circumstances of the cases. Delay and laches is
one of the facets to deny exercise of discretion. It is
not an absolute impediment. There can be
mitigating factors, continuity of cause action, etc.
That apart, if the whole thing shocks the judicial
conscience, then the Court should exercise the
discretion more so, when no third-party interest is
involved.”
(emphasis supplied)

(c) In Kazi Moinuddin Kazi Bashiroddin vs. Maharashtra

Tourism Development Corporation, 2022 SCC OnLine SC

1325, at para 26, this Court noted that, in matters relating to

payment of amount of compensation to land losers, if at all two

views are possible, the view that advances the cause of justice

is always to be preferred rather than the other view, which may

draw its strength only from technicalities.

17.2 On the question of abandonment or waiver of rights, this

Court in G.T. Lad vs. Chemical and Fibres of India Ltd.,

Page 74 of 86
(1979) 1 SCC 590 noted, albeit in the context of workmen

abandoning service, that “to constitute abandonment, there

must be total or complete giving up of duties so as to indicate

an intention not to resume the same”. It further noted that

such abandonment is always a question of intention.

17.3 Further, in State of Punjab vs. Davinder Pal Singh

Bhullar, (2011) 14 SCC 770, this Court dealt with the

doctrine of waiver. It held that, to constitute waiver, the person

who is said to have waived, must have intentionally abandoned

his rights with full knowledge after being fully informed of his

rights.

18. In the following Writ Petitions by the impugned order

dated 18.12.2018 the Bombay High Court observed as follows

and dismissed the Writ Petitions on the ground of delay and

laches.

“ (i) WP No.1898 of 2009 –
Kukreja Construction and Others vs. The State
of Maharashtra and Others.

35. In Writ Petition No.1898/2009, the petitioners’
land was reserved for 18.3 meters wide DP Road.
The petitioners surrendered the reserved land and
were granted TDR in lieu of the reserved land.

Page 75 of 86
Thereafter, the petitioners constructed DP Road as
claimed in the petition and a completion certificate
was issued on 19th August 1994. According to the
case of the petitioners, they carried out work of
storm water drain for which competition certificate
was issued 17th March 2003. According to their
case, the TDR in respect of the land was issued on
16th March 1994 and 5th April 2003. On 21st July
2003, the petitioners through their Architect applied
for grant of additional TDR under clause (6) of
Appendix-VII. But the application made by the
petitioner (Exhibit-I) shows that on 21st July 2003,
only 25% additional TDR was claimed in respect of
amenity of DP Road. It is not the case of the
petitioners that thereafter they followed the said
application by issuing reminders. For six years or
more, no claim was made for 100% TDR on account
of construction of the amenity. However, on 28th
August 2009, through their Architect, the
petitioners applied for grant of additional TDR for
the amenity equivalent to 100% of the area. The said
application was made only after the decision of the
Apex Court in the case of Godrej & Boyce
Manufacturing Co. Ltd. (supra) and the present
petition was lodged on 15th September 2009.
Therefore, in facts of the case, no relief can be
granted as for a period of more than six years after
surrender, no claim was made for 100% TDR.


(ii) WP No.1823 of 2009 –
     Jitendra  Amritlal   Sheth       vs.   State     of
     Maharashtra and Others.
   37.     Now,    we    come    to   Writ    Petition

No.1823/2012. In this case, the possession of DP
Road after its construction was handed over by the
petitioners to the Municipal Corporation on 5th
March 2005. On 24th February 2009, the petitioners’

Page 76 of 86
Architect for the first time applied for 100% FSI in
lieu of the constructed amenity. There was inaction
for more than 3 years and 11 months and claim for
100% additional TDR was not made. The averments
made in the petition show that on 18th November
2009, a reminder was issued. By communication
dated 7th December 2009, the proposal of the
Architect was specifically rejected. The petition was
affirmed on 30th July 2012 i.e. two years after the
prayer for grant of 100% TDR was turned down. The
explanation for delay given by way of amendment to
the petition is that on 7th March 2010, a file
containing correspondence and judgments of the
Supreme Court was handed over to the attorneys. It
is stated that amendment of 17th June 2010 to the
DCR was made available to the petitioners in July
2010. On 8th January 2011, the Legal Consultant of
the fourth petitioner by writing an email
enquired with the Solicitors whether draft was
ready. On 25th January 2011, it is claimed that the
draft was forwarded. Thereafter, on 18th July 2011,
a meeting was held between the petitioners, their
Legal Consultant and Architect. It is claimed that
the documents were furnished by the Architect to
their advocate on 15th June 2012 and, ultimately,
on 30th July 2012, the petition was filed. This is
hardly an explanation for delay of 2½ years,
especially when in the facts, of the case after
construction of DP Road, the possession of the same
was handed over on 5th March 2005. There is no
explanation for not claiming 100% TDR within three
years from that date. Even after entrusting the case
to the Advocate, there is a long delay. Hence,
considering the gross delay and laches which is not
at all explained, this is a case where a Writ Court
should not allow the party to invoke its extra
ordinary jurisdiction under Article 226 of the
Constitution of India.

Page 77 of 86

(iii) WP No.839 of 2015 –
Geeta alias Chandani Umesh Gandhi vs. The
State of Maharashtra and others.

38. In Writ Petition No.839/2015, the possession
of DP Road was handed over to the Municipal
Corporation on 20th May 2005. On 31st December
2006, 25% FSI/TDR in respect of the constructed
road was granted. On 1st December 2009, the
petitioner through her Architect requested to release
balance 75% TDR towards the amenity developed.
The perusal of the averments made in the petition
shows that after lapse of 4½ years thereafter, by a
letter dated 20th June 2014, the petitioner requested
the Municipal Corporation to issue balance 75%
TDR. Thereafter, there was a legal notice sent on 1st
December 2014. The petition was filed one year
thereafter in January 2015. There is absolutely no
explanation as to why there is a complete inaction
on the part of the petitioner from 1st December 2009
when the petitioner’s Architect applied for grant of
remaining 75% additional TDR till 20th June 2014
when similar request was made by the petitioner. As
there is no explanation for this inaction for a period
of more 4½ years and the delay involved thereafter,
this is not a fit case wherein a Writ Court should
exercise jurisdiction under Article 226 of the
Constitution of India.

(iv) WP No.2871 of 2015 –
Jameel A. Hussain and Others vs. State of
Maharashtra and Others.

39. In Writ Petition No.2871/2015, the
reservation of the land claimed by the petitioners
was for DP Road. The possession of the developed
portion of the reserved land was taken over by the
said Corporation on 29th July 2004. The completion
certificate was issued on 23rd August 2014. It is

Page 78 of 86
claimed in the petition that FSI in respect of
surrender of land was granted but FSI in respect of
amenity constructed thereon was never granted.
Going by the averments made in the petition,
though the petitioners claim to have surrendered
the reserved land with amenity on 29th July 2004,
the petitioners never applied for grant of 100% TDR
in respect of the amenity. Even after the decision of
the Apex Court in the case of Godrej & Boyce
Manufacturing Co. Ltd. (supra) which is of 6th
February 2009, the petitioners did not apply for
grant of additional FSI/ TDR in respect of amenity
surrendered in the year 2004 and for the first time
by a letter dated 17th February 2012, the petitioners
applied for grant of additional TDR. The proposal for
grant of additional TDR was rejected on 30th
January 2015. Thereafter the petition was filed.
Thus, after surrendering the reserved land on 29th
July 2004, the petitioners never claimed TDR in
respect of the amenity developed by them till 17th
February 2012. The application was made three
years after the decision of the Apex Court in the
case of Godrej & Boyce Manufacturing Co. Ltd.
(supra). Considering this conduct of the petitioners
which virtually amounts to abandonment of their
right, no relief can be granted to the petitioners in
this petition.

(v) WP No.2107 of 2016 –
M/s Byramjee Jeejeebhoy Pvt. Ltd. and Another
vs. The Municipal Corporation of Greater
Mumbai and Others.–

40. In Writ Petition No.2107/2016, according to
the case of the petitioners, they constructed DP
Road. They surrendered the reserved land on 5th
June 2007. Their Architects/ Licensed Surveyors
made an application on 4th September 2009 for

Page 79 of 86
grant of 100% additional TDR in the light of the
decision of the Apex Court. A legal notice was issued
by their advocate on 7th December 2009. Thereafter,
the petitioners took no steps and after a gap of 6½
years on 21st July 2016, the petitioners called upon
the said Corporation to grant additional FSI/TDR.
The correspondence made by the petitioners in the
year 2009 was based on the decision of the Apex
Court in the case of Godrej & Boyce
Manufacturing Co. Ltd. (supra). The petitioners
sought to rely upon the subsequent decision of the
Apex Court dated 5th May 2016 in the case
of Municipal Corporation of Greater Mumbai v.
Natvar Parikh & Co. Pvt. Ltd. (Civil Appeal
No.1479/2015) which followed the decision of the
Apex Court in the case of Godrej & Boyce
Manufacturing Co. Ltd. (supra). There is no
explanation offered in the petition as to why there
was complete inaction on the part of the petitioners
from 2009 to 2016. Therefore, considering this
conduct of the petitioners, they are dis-entitled to
any relief.

(vi) WP No.2170 of 2016 –
Girdharlal D. Rughani Alia Thakkar H.U.F. and
Another vs. The State of Maharashtra and
Others.–

41. In Writ Petition No.2170/2016, the case of the
petitioners is that on 20th October 1995 they handed
over the possession of their land reserved for DP
Road to the said Corporation. They claimed that
after completing the construction of DP Road on 20th
October 1994, a completion certificate was granted
by the Municipal Corporation. It is not the case of
the petitioners that thereafter they applied for grant
of additional 100% TDR in respect of the amenity
developed. Only on 5th August 2014 (i.e. ten years

Page 80 of 86
after developing the amenity) that the petitioners
applied for grant of additional TDR through their
Architect. For a period of 10 years, the petitioners
never claimed 100% additional TDR in respect of the
amenity. Even thereafter, no action is taken and the
present petition is filed in July 2016. Considering
the conduct of the petitioners, they are not entitled
to any relief.

(vii) WP No.384 of 2017 –
Oberoi Realty Limited and Another vs. Municipal
Corporation of Greater Mumbai and Others.–

42. In Writ Petition No.384/2017, the case of the
petitioners is that between 2004 and 2008, they
developed seven DP Roads and handed over the
possession thereof to the said Corporation. However,
they made representation for the first time on 10th
June 2016 claiming additional TDR in respect of
amenity developed. The representation was rejected
on 30th November 2016 by the said Corporation.
Thus, even after the decision in the case of Godrej
& Boyce Manufacturing Co. Ltd. (supra), the
petitioners did not apply for grant of additional TDR.
The petitioners sought additional TDR after lapse of
eight years and more. Therefore, for a period of eight
years or more, the petitioners never claimed
additional TDR. Hence, considering the delay and
laches on the part of the petitioners, no relief can be
granted.

(viii) WP No.541 of 2017 –

Nanabhoy Jeejeebhoy Pvt. Ltd. and Another vs.
The State of Maharashtra and Others. –

43. In Writ Petition No.541/2017, the case of the
petitioners is that there were eleven reservations on
their property for DP Roads. The petitioners have

Page 81 of 86
referred to the said reservations as DP Road-I to DP
Road-XI. According to the case of the petitioners,
after developing the amenities, the possession of
DP Roads was handed over to the said Corporation
on 13th April 2004, 20th March 2001, 27th March
2002, 6th September 2001, 13th February 2006,
27th October 1997, 27th October 1997, 29th October
1997, 21st December 2002, 22nd May 2002 and 14th
August 2002 respectively. For the first time
additional TDR was claimed by the petitioners by
making application on 11th July 2014. Thus, in all
cases except one, the possession was handed over
after the development of DP Roads before the year
2003. In some cases, the possession of DP Road
was handed over in the year 1997. In one case, the
possession was handed over in the year 2006.
Thus, after lapse of several years after handing
over possession of DP Roads i.e. in 2014, belatedly
a request was made for grant of additional TDR.
The request was made after a gap of about 8 to 13
years for which there is no explanation. Thus, the
petitioners by their conduct have virtually
abandoned their claim for additional FSI/TDR in
respect of amenity.”

In all these cases, we find that the writ

petitioners/appellants herein had surrendered the reserved

land and had also been granted 25% TDR and a representation

for additional TDR was made after the judgment of this Court in

Godrej & Boyce I and in some cases, the representation was

made early but in other cases, the representations were made

Page 82 of 86
after some time. It is also noted in Civil Appeal No.1748 of

2015, in the case of Natwar Parikh, this Court had stated

that the decision in Godrej & Boyce I could not be revisited

inasmuch as the Mumbai Municipal Corporation could not seek

to reargue the matter. Also, the facts in each case on the

questions of delay was to be considered as observed by this

Court. The issue of abandonment of claim has also been

considered and negatived in the judgment of this Court in

Godrej & Boyce II.

We have referred to the decisions of this Court where the

question of delay and laches would not arise in matters such as

the present cases. When relief in the nature of compensation is

sought, as in the instant case, once the compensation is

determined in the form of FSI/TDR, the same is payable even in

the absence of there being any representation or request being

made. In fact, a duty is cast on the State to pay compensation

to the land losers as otherwise there would be a breach of

Article 300-A of the Constitution. As rightly contended by the

learned senior counsel for the writ petitioners/appellants

Page 83 of 86
herein, the respondent-Mumbai Municipal Corporation has not

established that owing to a short delay even if it has occurred

in any of these cases owing to uncertainty in law, the

Corporation has been prejudiced by the same or that the third-

party rights had been created which could not be disturbed

owing to delay or laches. The calculation of period of delay in

the table submitted by learned senior counsel for the Mumbai

Municipal Corporation is not acceptable in view of our

discussion above. The decisions referred to by us above would

clearly indicate that neither the doctrine of delay and laches nor

the principle of abandonment of claim or waiver would apply in

these cases. Rather the delay has occurred on the part of the

Mumbai Municipal Corporation in complying with the

Regulations insofar as these appellants are concerned.

18.1 In view of the aforesaid discussion, we hold that the

Bombay High Court was not right in dismissing the writ

petitions on the ground of delay and laches. Hence, those

portions of the impugned order of the High Court are set aside.

Page 84 of 86

19. We also do not find any merit in the three appeals filed by

the Mumbai Municipal Corporation. Having regard to the earlier

judgments of this Court, we find that the reasoning of the High

Court on merits in the three impugned decisions discussed

above is just and proper which would not call for any

interference by this Court.

20. Consequently, the civil appeals filed by the writ

petitioners/appellants herein are allowed as under:

(i) Those portions of the impugned order dated

18.12.2018 by which the writ petitions were

dismissed on the ground of delay and laches are

set aside and the respondent Mumbai Municipal

Corporation is directed to consider the case of

those writ petitioners/appellants herein in light of

the judgments of this Court in Godrej & Boyce I

and release the balance FSI/TDR to the

appellants.

(ii) However, in the case of appellant-Kukreja

Construction company and others, the Mumbai

Page 85 of 86
Municipal Corporation is directed to consider the

nature of the amenities constructed and thereafter

to consider their case for additional FSI/TDR.

(iii) The said exercise shall be carried out as

expeditiously as possible and within a period of

three months from today.

20.1 The Civil Appeals filed by the Mumbai Municipal

Corporation are dismissed and the cases of the respondents in

those civil appeals shall be considered in terms of the

judgments of this Court in Godrej & Boyce I and the balance

FSI/TDR shall be released to the respondents therein within a

period of three months from today.

Parties to bear their respective costs.

…………….………………………………J.
(B.V. Nagarathna)

…………….………………………………J.
(Nongmeikapam Kotiswar Singh)
New Delhi;

September 13, 2024.

Page 86 of 86

Source link

Leave a Reply

Your email address will not be published. Required fields are marked *